013000 Administrative Requirements.doc

DOC document 35 KB Posted

Attached to
RECOVERY Replace Annex Building HVAC, Beneficial Insects Introduction Research Unit (BIIRU), Newark, DE
Solicitation number
AG-3615-S-10-0001
Issued by

About this file

J.1 -02 SPECIFICATIONS - FILE 3

View the file

Other files

File Type Posted
SF-30 Amendment 03.pdf PDF
BiddersSign-InSheet.pdf PDF
sf-30 amend 02.pdf PDF
of 17.pdf PDF
SF-30 AMEND NO 01.pdf PDF
SF 30 AMEND NO 02.pdf PDF
AG-3615-S-10-0001 newark replace annex hvac IFB amend 02 COVERLETTER.docx DOCX document
260502_Minor Electrical Demolition.DOC DOC document
013300 Submittal Procedures.doc DOC document
230593_Testing Adjusting and Balancing for HVAC Systems.doc DOC document
260526_Grounding Bonding for Electrical Systems.DOC DOC document
230553_Identification for HVAC Piping and Equipment.DOC DOC document
2003.162.031-USDA-TS-22x34-Model.PDF PDF
DE6.dvb DVB file
095100_Acoustical Ceilings.DOC DOC document
SF-LLL FORM.pdf PDF
238113_Packaged Terminal Air Conditioners.DOC DOC document
230513_Common Motor Requirements For HVAC Equipment.DOC DOC document
2003.162.031-M101-USDA 22x34.PDF PDF
260529_Hangers Supports for Electrical Systems.DOC DOC document
022250-Minor Demolition for Remodeling.doc DOC document
230500_Common Work Results For HVAC.doc DOC document
260519_Low-Voltage Electrical Power Conductors Cables.DOC DOC document
099000-Paints and Coatings.doc DOC document
2003.162.031-A101-USDA 22x34.PDF PDF
260553_Identification for Electrical Systems.DOC DOC document
NEWARK RECOVERY - UPGRADE ANNEX BUILDING HVAC FAC 2005-37.DOCX DOCX document
AG-3615-S-10-0001 newark replace annex hvac IFB COVERLETTER.docx DOCX document
233300_Air Duct Accessories.DOC DOC document
283111 Digital Addressable Fire Alarm System.DOC DOC document
017000 Execution and Closeout Requirements.doc DOC document
014000 Quality Requirements.doc DOC document
233713_Diffusers Registers Grilles and Louvers.DOC DOC document
260533_Raceway Boxes for Electrical Systems.DOC DOC document
2003.162.031-Specification Cover.pdf PDF
230700_HVAC Insulation.doc DOC document
2003.162.031-M201-USDA 22x34.PDF PDF
233113_Metal Ducts.DOC DOC document
2003.162.031-E101-USDA 22x34.PDF PDF
016000 Product Requirements.doc DOC document
2003.162.031-M001-Layout.PDF PDF
2003.162.031-M102-USDA 22x34.PDF PDF
2003.162.031-M202-USDA 22x34.PDF PDF
000110ST - Table of Contents.doc DOC document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECTEXT® 2005, Copyright July 2005 Revised 07/2005

The Construction Sciences Research Foundation For use by licensed SPECTEXT® subscribers only.

SECTION 013000 - ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Coordination and project conditions.

B. Preconstruction meeting.

C. Site mobilization meeting.

D. Progress meetings.

E. Cutting and patching.

F. Special procedures.

1.2 COORDINATION AND PROJECT CONDITIONS

A. Coordinate scheduling, submittals, and Work of various sections of Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.

B. Coordinate scheduling of the Work with the Owner to minimize interference with normal operations. Work to commence during the Spring or Fall, when heating and cooling demands are minimized and progress in one zone at a time for four heating/cooling zones. Sequence and priority of heating/cooling zones as determined by the Owner.

C. Verify utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, operating equipment.

D. Coordinate space requirements, supports, and installation of mechanical and electrical Work indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

E. In finished areas, conceal pipes, ducts, and wiring within construction. Coordinate locations of fixtures and outlets with finish elements.

F. Coordinate completion and clean-up of Work of separate sections in preparation for Substantial Completion.

G. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner's activities.

1.3 PRECONSTRUCTION MEETING

A. Owner and Architect/Engineer will schedule meeting after Notice of Award.

B. Attendance Required: Owner, Architect/Engineer, and Contractor.

C. Record minutes and distribute copies within five days after meeting to participants, with a copy to the Architect/Engineer, Owner, and those affected by decisions made.

1.4 SITE MOBILIZATION MEETING

A. Architect/Engineer will schedule meeting at Project site prior to Contractor occupancy.

B. Attendance Required: Owner, Architect/Engineer, Contractor, Contractor's Superintendent, and major Subcontractors.

C. Record minutes and distribute copies within five days after meeting to participants, with a copies to the Architect/Engineer, Owner, and those affected by decisions made.

1.5 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the Work at maximum bi-monthly intervals.

B. Architect/Engineer will make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.

C. Attendance Required: Job superintendent, major subcontractors and suppliers, Owner, Architect/Engineer, as appropriate to agenda topics for each meeting.

D. Record minutes and distribute copies within five days after meeting to participants, with a copy to the Architect/Engineer, Owner, and those affected by decisions made.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 CUTTING AND PATCHING

A. Employ skilled and experienced installer to perform cutting and patching.

B. Submit written request in advance of cutting or altering elements affecting:

1. Structural integrity of element.

2. Integrity of weather-exposed or moisture-resistant elements.

3. Efficiency, maintenance, or safety of element.

4. Visual qualities of sight exposed elements.

5. Work of Owner or separate contractor.

C. Execute cutting, fitting, and patching to complete Work, and to:

1. Fit the several parts together, to integrate with other Work.

2. Uncover Work to install or correct ill-timed Work.

3. Remove and replace defective and non-conforming Work.

4. Remove samples of installed Work for testing.

5. Provide openings in elements of Work for penetrations of mechanical and electrical Work.

D. Execute work by methods to avoid damage to other Work, and to provide proper surfaces to receive patching and finishing.

E. Cut masonry and concrete materials using masonry saw or core drill.

F. Restore Work with new products in accordance with requirements of Contract Documents.

G. Fit Work tight to pipes, sleeves, ducts, conduit, and other penetrations through surfaces.

H. Maintain integrity of wall, ceiling, or floor construction; completely seal voids.

I. At penetrations of fire rated walls, partitions, ceiling, or floor construction, completely seal voids with fire rated material to full thickness of penetrated element.

J. Refinish surfaces to match adjacent finishes. For continuous surfaces, refinish to nearest intersection; for assembly, refinish entire unit.

K. Identify hazardous substances or conditions exposed during the Work to Architect/Engineer for decision or remedy.

3.2 SPECIAL PROCEDURES

A. Materials: As specified in product sections, match existing with new products and salvaged products for patching and extending work.

B. Employ skilled and experienced installer to perform alteration work.

C. Cut, move, or remove items as necessary for access to alterations and renovation Work. Replace and restore at completion.

D. Remove unsuitable material not marked for salvage, including rotted wood, corroded metals, and deteriorated masonry and concrete. Replace materials as specified for finished Work.

E. Remove debris and abandoned items from area and from concealed spaces.

F. Prepare surface and remove surface finishes to permit installation of new work and finishes.

G. Close openings in exterior surfaces to protect existing work from weather and extremes of temperature and humidity.

H. Remove, cut, and patch Work in manner to minimize damage and to permit restoring products and finishes to specified condition.

I. Refinish existing visible surfaces to remain in renovated rooms and spaces, to renewed condition for each material, with neat transition to adjacent finishes.

J. Where new Work abuts or aligns with existing, provide smooth and even transition. Patch Work to match existing adjacent Work in texture and appearance.

K. When finished surfaces are cut so that smooth transition with new Work is not possible, terminate existing surface along straight line at natural line of division and submit recommendation to Architect/Engineer for review.

L. Where change of plane of 1/4 inch or more occurs, submit recommendation for providing smooth transition; to Architect/Engineer for review.

M. Trim existing doors to clear new floor finish.

N. Patch or replace portions of existing surfaces which are damaged, lifted, discolored, or showing other imperfections.

O. Finish surfaces as specified in individual product sections.

END OF SECTION

Administrative Requirements

01$/:s30$/:s00 -

Upgrade The Annex Building HVAC

Administrative Requirements

BIIRU, Newark DE

013000 -