About this file

J.1 -02 SPECIFICATIONS - FILE 5

View the file

Other files

File Type Posted
SF-30 Amendment 03.pdf PDF
BiddersSign-InSheet.pdf PDF
sf-30 amend 02.pdf PDF
of 17.pdf PDF
SF-30 AMEND NO 01.pdf PDF
SF 30 AMEND NO 02.pdf PDF
AG-3615-S-10-0001 newark replace annex hvac IFB amend 02 COVERLETTER.docx DOCX document
260502_Minor Electrical Demolition.DOC DOC document
013300 Submittal Procedures.doc DOC document
230593_Testing Adjusting and Balancing for HVAC Systems.doc DOC document
260526_Grounding Bonding for Electrical Systems.DOC DOC document
230553_Identification for HVAC Piping and Equipment.DOC DOC document
2003.162.031-USDA-TS-22x34-Model.PDF PDF
DE6.dvb DVB file
095100_Acoustical Ceilings.DOC DOC document
SF-LLL FORM.pdf PDF
238113_Packaged Terminal Air Conditioners.DOC DOC document
230513_Common Motor Requirements For HVAC Equipment.DOC DOC document
2003.162.031-M101-USDA 22x34.PDF PDF
260529_Hangers Supports for Electrical Systems.DOC DOC document
022250-Minor Demolition for Remodeling.doc DOC document
230500_Common Work Results For HVAC.doc DOC document
260519_Low-Voltage Electrical Power Conductors Cables.DOC DOC document
099000-Paints and Coatings.doc DOC document
2003.162.031-A101-USDA 22x34.PDF PDF
260553_Identification for Electrical Systems.DOC DOC document
NEWARK RECOVERY - UPGRADE ANNEX BUILDING HVAC FAC 2005-37.DOCX DOCX document
AG-3615-S-10-0001 newark replace annex hvac IFB COVERLETTER.docx DOCX document
013000 Administrative Requirements.doc DOC document
233300_Air Duct Accessories.DOC DOC document
283111 Digital Addressable Fire Alarm System.DOC DOC document
017000 Execution and Closeout Requirements.doc DOC document
233713_Diffusers Registers Grilles and Louvers.DOC DOC document
260533_Raceway Boxes for Electrical Systems.DOC DOC document
2003.162.031-Specification Cover.pdf PDF
230700_HVAC Insulation.doc DOC document
2003.162.031-M201-USDA 22x34.PDF PDF
233113_Metal Ducts.DOC DOC document
2003.162.031-E101-USDA 22x34.PDF PDF
016000 Product Requirements.doc DOC document
2003.162.031-M001-Layout.PDF PDF
2003.162.031-M102-USDA 22x34.PDF PDF
2003.162.031-M202-USDA 22x34.PDF PDF
000110ST - Table of Contents.doc DOC document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECTEXT® 2005, Copyright July 2005 Revised 07/2005

The Construction Sciences Research Foundation For use by licensed SPECTEXT® subscribers only.

SECTION 014000 - QUALITY REQUIREMENTS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Quality control and control of installation.

B. Tolerances

C. References.

D. Mock-up requirements.

E. Testing and inspection services.

F. Manufacturers' field services.

G. Examination.

H. Preparation.

1.2 QUALITY CONTROL AND CONTROL OF INSTALLATION

A. Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings but not in the specifications will be interpreted as being in both.

B. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality.

C. Comply with manufacturers' instructions, including each step in sequence.

D. When manufacturers' instructions conflict with Contract Documents, request clarification from Architect/Engineer before proceeding.

E. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

F. Perform Work by persons qualified to produce required and specified quality.

G. Verify field measurements are as indicated on Shop Drawings or as instructed by manufacturer.

H. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, or disfigurement.

1.3 TOLERANCES

A. Monitor fabrication and installation tolerance control of products to produce acceptable Work. Do not permit tolerances to accumulate.

B. Comply with manufacturers' tolerances. When manufacturers' tolerances conflict with Contract Documents, request clarification from Architect/Engineer before proceeding.

C. Adjust products to appropriate dimensions; position before securing products in place.

1.4 REFERENCES

A. For products or workmanship specified by association, trade, or other consensus standards, comply with requirements of standard, except when more rigid requirements are specified or are required by applicable codes.

B. Conform to reference standard by date of issue current on date of Contract Documents, except where specific date is established by code.

C. Obtain copies of standards where required by product specification sections.

D. When specified reference standards conflict with Contract Documents, request clarification from Architect/Engineer before proceeding.

E. Neither contractual relationships, duties, nor responsibilities of parties in Contract nor those of Architect/Engineer shall be altered from Contract Documents by mention or inference otherwise in reference documents.

1.5 MOCK-UP REQUIREMENTS

A. Tests will be performed under provisions identified in this section and identified in respective product specification sections.

B. Assemble and erect specified items with specified attachment and anchorage devices, flashings, seals, and finishes.

C. Accepted mock-ups shall be comparison standard for remaining Work.

D. Where mock-up has been accepted by Architect/Engineer and is specified in product specification sections to be removed; remove mock-up and clear area when directed to do so by Architect/Engineer.

1.6 TESTING AND INSPECTION SERVICES

A. Employ and pay for services of an independent testing agency or laboratory acceptable to Owner to perform specified testing.

1. Prior to start of Work, submit testing laboratory name, address, and telephone number, and names of full time registered Engineer and responsible officer.

2. Submit copy of report of laboratory facilities inspection made by Materials Reference Laboratory of National Bureau of Standards during most recent inspection, with memorandum of remedies of deficiencies reported by inspection.

B. The independent firm will perform tests, inspections and other services specified in individual specification sections and as required by Architect/Engineer.

1. Laboratory: Authorized to operate at Project location in State of Delaware.

2. Laboratory Staff: Maintain full time registered Engineer on staff to review services.

3. Testing Equipment: Calibrated at reasonable intervals with devices of an accuracy traceable to National Bureau of Standards or accepted values of natural physical constants.

C. Testing, inspections and source quality control may occur on or off project site. Perform off-site testing as required by Architect/Engineer or Owner.

D. Reports will be submitted by independent firm to Architect/Engineer and Contractor, in duplicate, indicating observations and results of tests and indicating compliance or non-compliance with Contract Documents.

E. Cooperate with independent firm; furnish samples of materials, design mix, equipment, tools, storage, safe access, and assistance by incidental labor as requested.

1. Notify Architect/Engineer and independent firm 24 hours prior to expected time for operations requiring services.

2. Make arrangements with independent firm and pay for additional samples and tests required for Contractor's use.

F. Testing and employment of testing agency or laboratory shall not relieve Contractor of obligation to perform Work in accordance with requirements of Contract Documents.

G. Re-testing or re-inspection required because of non-conformance to specified requirements shall be performed by same independent firm on instructions by Architect/Engineer. Payment for re-testing or re-inspection will be charged to Contractor by deducting testing charges from Contract Sum/Price.

H. Agency Responsibilities:

1. Test samples of mixes submitted by Contractor.

2. Provide qualified personnel at site. Cooperate with Architect/Engineer and Contractor in performance of services.

3. Perform specified sampling and testing of products in accordance with specified standards.

4. Ascertain compliance of materials and mixes with requirements of Contract Documents.

5. Promptly notify Architect/Engineer and Contractor of observed irregularities or non-conformance of Work or products.

6. Perform additional tests required by Architect/Engineer.

7. Attend preconstruction meetings and progress meetings.

I. Agency Reports: After each test, promptly submit two copies of report to Architect/Engineer and to Contractor. When requested by Architect/Engineer, provide interpretation of test results. Include the following:

1. Date issued.

2. Project title and number.

3. Name of inspector.

4. Date and time of sampling or inspection.

5. Identification of product and specifications section.

6. Location in Project.

7. Type of inspection or test.

8. Date of test.

9. Results of tests.

10. Conformance with Contract Documents.

J. Limits On Testing Authority:

1. Agency or laboratory may not release, revoke, alter, or enlarge on requirements of Contract Documents.

2. Agency or laboratory may not approve or accept any portion of the Work.

3. Agency or laboratory may not assume duties of Contractor.

4. Agency or laboratory has no authority to stop the Work.

1.7 MANUFACTURERS' FIELD SERVICES

A. When specified in individual specification sections, require material or product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust and balance of equipment as applicable, and to initiate instructions when necessary.

B. Submit qualifications of observer to Architect/Engineer 30 days in advance of required observations.

C. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers' written instructions.

D. Refer to Section 013300 - Submittal Procedures MANUFACTURERS' FIELD REPORTS article.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 EXAMINATION

A. Verify existing site conditions and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.

B. Verify existing substrate is capable of structural support or attachment of new Work being applied or attached.

C. Examine and verify specific conditions described in individual specification sections.

D. Verify utility services are available, of correct characteristics, and in correct locations.

3.2 PREPARATION

A. Clean substrate surfaces prior to applying next material or substance.

B. Seal cracks or openings of substrate prior to applying next material or substance.

C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying new material or substance in contact or bond.

END OF SECTION

Quality Requirements

01$/:s40$/:s00 -

Upgrade The Annex Building HVAC

Quality Requirements

BIIRU, Newark DE

014000 -