SummaryofSolicitationContractDates.pdf

PDF 177 KB Posted

Attached to
AlaganikSloughBoat Ramp Federal contract opportunity
Solicitation number
AG-0120-S-12-0011
Issued by
Department of Agriculture Forest Service R10-Alaska Region

About this file

Summary of solicitation and contract date milestones

View the file

Other files for this federal contract opportunity

Other files attached to AlaganikSloughBoat Ramp, newest first.
File Type Posted
Amend006.pdf PDF
AG0120S120011_Amend005.pdf PDF
AG0120S120011_PrePreproposal_Attendance.pdf PDF
AlaganikSpecFinalRev8Jun2012PESeal.pdf PDF
ScheduleofItemsAlaganik_Rev8June2012.pdf PDF
AG0120S120011_A004_SF30Atch.pdf PDF
11-II-0159-SA AII_Alaganik Boat Ramp_CRDCHA.pdf PDF
Sections_CF_WageDet_Rev5July2012.pdf PDF
AG0120S120011_A004_SF30.pdf PDF
AlaganikBoatRampRplDwg_Rev31May12.pdf PDF
AG0120S120011_A003.pdf PDF
AG0120S120011_Amend002.pdf PDF
AG0120S120011_A002_Atch1.pdf PDF
USACE_Permit.pdf PDF
AG0120S120011_Amend001_SF30.pdf PDF
AG0120S120011_PrePreproposal_Attendance.pdf PDF
DBA_GnlDec_AK1_Modification4_17Feb2012.docx DOCX document
11-II-0158 AI_Boat Ramp_Alaganik Slough_USFS.pdf PDF
AG0120S120011_PreProposalMtgNotes.pdf PDF
11-II-0159 SA AI_Boat Ramp_CRDCHA.pdf PDF
MASTERSpecsforContracting._31.Jan.2012.pdf PDF
ErrataSheet2-9.pdf PDF
Alaganik_Boat_Ramp_Final_Dwgs.pdf PDF
AG0120S120011_AlaganikSloughBoatRampFNL.pdf PDF
Dowl_Geotech_Report.pdf PDF
AG0120S120011_ReturnPkg_AlaganikSloughBoatRamp.docx DOCX document
Alaganik Slough Boat Ramp Hydrodynamic Report 2010-0210.pdf PDF
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Alaganik Slough Boat Ramp Summary of Contract Dates

Date Milestone Reference

August 16, 2012 Bids are due to USFS office Solicitation

October 1, 2012 Construction may proceed NEPA DM 3/6/12

April 1, 2013 Last day USFS can award option items

Solicitation

Prior to May 1, 2013 Dewatering structure installed NEPA DM 3/6/12

June 30, 2013 Instream Work Completed & dewatering structure removed.

NEPA DM 3/6/12

May 1, 2013 – June 30, 2013 No clearing or grubbing NEPA DM 3/6/12

August 31, 2013 All work complete. Solicitation

File details come from the government source that posted it. Updated .