ScheduleofItemsAlaganik_Rev8June2012.pdf

PDF 141 KB Posted

Attached to
AlaganikSloughBoat Ramp
Solicitation number
AG-0120-S-12-0011
Issued by

About this file

Revised Section B Schedule of Items dated 8 June 2012

View the file

Other files

Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AG-0120-S-12-0011, Amendment 004

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS SCHEDULE OF ITEMS

ALAGANIK SLOUGH BOAT RAMP REPLACEMENT

BASE BID SCHEDULE OF ITEMS – Revised 8 June 2012

1. PREPARATION – General Requirements

2. RAMP EARTHWORK

EXCAVATION

DQ 2,010 CY

GEOTEXTILE

DQ 2,100 SY

ROCK BORROW

DQ 220 CY

BASE COURSE

DQ 230 CY

RIPRAP

DQ 1,325 CY

TYPE D-1 CRUSHED

AGGREGATE

DQ 70 CY

3. BOAT RAMP ITEMS

PRECAST CONCRETE PLANKS,

INCLUDING ANCHORING

SYSTEM

AQ 72 EA

4. ACCESSIBLE LOADING PLATFORM

CONCRETE SIDEWALK

AQ 180 SF

CAST-IN-PLACE CONCRETE

CANTILEVER RETAINING

WALL

LSQ 1 LS

GALVANIZED STEEL 3-RAIL

HANDRAIL

AQ 12 LF

4" x 6" ALASKA YELLOW

CEDAR RUB RAIL

AQ 30 LF

TOTAL

PRICE

ITEM

NO.

ITEM

METHOD

OF

MEAS.

QUANTITY UNIT

UNIT

PRICE

AMOUNT

MOBILIZATION LSQ 1 LS

CLEARING AND GRUBBING

DQ 1,120 SY

TEMPORARY CONSTRUCTION

FENCING AND GATE

LSQ 1 LS

CONSTRUCTION SURVEYING

LSQ 1 LS

5. OTHER ITEMS

CONSTRUCTION AREA BMPs

0017 DEWATERING CONTROLS LSQ 1 LS $_______ $________

TOTAL BASE BID:

OPTIONAL BID SCHEDULE OF ITEMS

SCHEDULE OF ITEMS – OPTION A: DEMOLISH EXISTING BOAT RAMP

NO.

ITEM

METHOD

OF

MEAS.

QUANTITY UNIT

UNIT

PRICE

AMOUNT

A-001

DEMOLITION OF EXISTING

PLANKS

DQ 660 SF

A-002

PLANTS

AQ 12 EA

A-003

MOBILIZATION AND

DEMOBILIZATION

SCHEDULE OF ITEMS – OPTION B: RAMP CURBING

NO.

ITEM

METHOD

OF

MEAS.

QUANTITY UNIT

UNIT

PRICE

AMOUNT

B-001 8" x 8" ALASKA YELLOW

CEDAR CURB

AQ 164 LF

B-002

MOBILIZATION AND

DEMOBILIZATION

SCHEDULE OF ITEMS – OPTION C: PARKING LOT RECONSTRUCTION

NO.

ITEM

METHOD

OF

MEAS.

QUANTITY UNIT

UNIT

PRICE

AMOUNT

C-001

CLEARING AND GRUBBING

DQ 480 SY

C-002

EXCAVATION

DQ 100 CY

C-003

GEOTEXTILE

DQ 600 SY

C-004

TYPE D-1 CRUSHED

AGGREGATE

DQ 100 CY

C-005

MOBILIZATION AND

DEMOBILIZATION

TOTAL PRICE

SCHEDULE OF ITEMS – OPTION D: PARKING AREA FINISHES

NO.

ITEM

METHOD

OF

MEAS.

QUANTITY UNIT

UNIT

PRICE

AMOUNT

D-001 BOULDERS, 3’ x 3’ x 3’

AQ 69 EA

D-002

TRAFFIC SIGN AND POST,

"KEEP RIGHT"

AQ 1 EA

D-003

MOBILIZATION AND

DEMOBILIZATION

BID SUMMARY

TOTAL PRICE

BASE BID

OPTION A

OPTION B

OPTION C

OPTION D

METHOD OF MEASUREMENT: UNITS:

AQ = ACTUAL QUANTITY CY = CUBIC YARD

DQ = DESIGN QUANTITY LS = LUMP SUM

LSQ = LUMP SUM QUANTITY EA = EACH

SF = SQUARE FOOT

LF = LINEAR FOOT

NOTES:

1) The delineation of base bid and option items as stated in this Schedule of Items governs the project bidding. Drawings and specifications regarding the optional items do not infer that these items will be constructed with the base bid award.

2) The total contract award amount will be the sum of the base bid and options which when combined are within the project budget.

3) The Contracting Officer will make the decision regarding which options to award at the time of award. Priority will be given to contractors who can complete the most options within the project budget.

4) For purposes of progress payments pursuant to the clause at FAR 52.232-5 (Payments Under

Fixed-Price Construction Contracts), this work is divided into pay items as shown above. The sum of the pay item amounts shall equal the total prices given. During the performance of the contract, payment will be made based on the method of measurement and estimated quantities indicated in the schedule. All other work and materials will be considered incidental to and included in the payment of pay items awarded.

5) Mobilization and Demobilization for Option items will only be paid if the option item is not awarded with the initial base bid award.

NOTE: Bidders are required to submit unit prices and extensions for all pay items. Failure to submit prices for all items will render the bid nonresponsive and will not be considered for award.

File details come from the government source that posted it. Updated .