AG-0120-S-12-0011 Alaganik Slough Boat Ramp Master Specifications
View the file
Other files for this federal contract opportunity
Show all 27
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 00 00 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS January 31, 2012
Alaganik Slough Boat Ramp Replacement 00 00 00-i
ALAGANIK SLOUGH
BOAT RAMP REPLACEMENT
CONTRACT SPECIFICATIONS
Task Order No. AG-0120-D-09-0020
(TtEC Project No. 106-3954)
Prepared for
Chugach National Forest
U.S. Forest Service
3301 C Street, Suite 202
Anchorage, AK 99503
Prepared by
Tetra Tech EC, Inc.
19803 North Creek Parkway
Bothell, WA 98011
May 28, 2010
Revised January 31, 2012
This is not a legal engineering document, but an electronic duplicate.
The original, signed and sealed by the engineer, is stored in the Chugach National Forest Contracting Officer’s document control office.
Alaganik Slough Boat Ramp Replacement 00 00 00-ii
Alaganik Slough Boat Ramp Replacement
Contract Specifications
TABLE OF CONTENTS
Section Specification Title Page
00 00 00 PROCUREMENT AND CONTRACTING REQUIREMENTS
01 00 00 GENERAL REQUIREMENTS
PART 1 – GENERAL
1.1 SUMMARY OF WORK................................................................................01 00 00-2
1.2 EXISTING CONDITIONS ............................................................................01 00 00-2
1.3 NOT USED ....................................................................................................01 00 00-3
1.4 FIELD ENGINEERING AND SURVEYING ...............................................01 00 00-3
1.5 MEETINGS ...................................................................................................01 00 00-4
1.6 SUBMITTAL PROCEDURES ......................................................................01 00 00-5
1.7 CONSTRUCTION SCHEDULES .................................................................01 00 00-5
1.8 CONSTRUCTION WORK PLAN ................................................................01 00 00-6
1.9 PERMIT REQUIREMENTS .........................................................................01 00 00-6
1.10 NOT USED ....................................................................................................01 00 00-6
1.11 SHOP DRAWINGS .......................................................................................01 00 00-6
1.12 MANUFACTURER’S INSTRUCTIONS AND CERTIFICATES ...............01 00 00-6
1.13 PROJECT RECORD DOCUMENTS ...........................................................01 00 00-6
1.14 QUALITY CONTROL ..................................................................................01 00 00-7
1.15 NOT USED ....................................................................................................01 00 00-7
1.16 TEMPORARY CONSTRUCTION CONTROLS – ISOLATION &
DEWATERING .............................................................................................01 00 00-7
1.17 SITE ACCESS AND FENCING ...................................................................01 00 00-8
1.18 FIELD OFFICE AND STORAGE .................................................................01 00 00-8
1.19 POLLUTION AND ENVIRONMENTAL CONTROL ................................01 00 00-8
1.20 DELIVERY, HANDLING, STORAGE AND PROTECTION .....................01 00 00-8
1.21 PRODUCT OPTIONS ...................................................................................01 00 00-9
1.22 NOT USED ..................................................................................................01 00 00-9
1.23 FINAL INSPECTION ....................................................................................01 00 00-9
1.24 NOT USED ....................................................................................................01 00 00-9
1.25 MEASUREMENT AND PAYMENT ...........................................................01 00 00-9
PART 2 – PRODUCTS
NOT USED
Alaganik Slough Boat Ramp Replacement 00 00 00-iii
PART 3 – EXECUTION
02 40 00 DEMOLITION
1.1 SECTION INCLUDES ..................................................................................02 40 00-1
1.2 RELATED SECTIONS .................................................................................02 40 00-1
1.3 MEASUREMENT AND PAYMENT ...........................................................02 40 00-1
1.4 SUBMITTALS ...............................................................................................02 40 00-1
1.5 NOT USED ....................................................................................................02 40 00-1
3.1 EXAMINATION ...........................................................................................02 40 00-2
3.2 EROSION/POLLUTION CONTROL ...........................................................02 40 00-2
3.3 TEMPORARY DEWATERING ...................................................................02 40 00-2
3.4 EXISTING CONDITIONS ............................................................................02 40 00-2
3.5 NOT USED ....................................................................................................02 40 00-2
3.6 SITE DEMOLITION .....................................................................................02 40 00-2
3.7 NOT USED ....................................................................................................02 40 00-2
3.8 STOCKPILING OF MATERIALS ................................................................02 40 00-2
3.9 DISPOSAL OF MATERIALS .......................................................................02 40 00-2
03 30 00 CAST-IN-PLACE CONCRETE
1.1 SECTION INCLUDES ..................................................................................03 30 00-1
1.2 RELATED SECTIONS .................................................................................03 30 00-1
1.3 MEASUREMENT AND PAYMENT ...........................................................03 30 00-1
1.4 SUBMITTALS ...............................................................................................03 30 00-1
1.5 REFERENCES ..............................................................................................03 30 00-1
1.6 QUALITY CONTROL ..................................................................................03 30 00-2
1.7 PRODUCT DELIVERY, PLACEMENT, AND CURING ...........................03 30 00-2
2.1 CONCRETE MATERIALS ...........................................................................03 30 00-2
2.2 ADMIXTURES .............................................................................................03 30 00-2
2.3 JOINT DEVICES AND FILLER MATERIALS ...........................................03 30 00-2
2.4 CONCRETE MIX ..........................................................................................03 30 00-2
3.1 EXAMINATION ...........................................................................................03 30 00-3
Alaganik Slough Boat Ramp Replacement 00 00 00-iv
3.2 PREPARATION ............................................................................................03 30 00-3
3.3 TEMPORARY DEWATERING ...................................................................03 30 00-3
3.4 PLACING CONCRETE ................................................................................03 30 00-3
3.5 CONCRETE FINISHING ..............................................................................03 30 00-3
3.6 CURING AND PROTECTION .....................................................................03 30 00-3
3.7 FIELD QUALITY CONTROL ......................................................................03 30 00-3
3.8 DEFECTIVE CONCRETE ............................................................................03 30 00-3
3.9 TOLERANCES ..............................................................................................03 30 00-3
03 40 00 PRECAST CONCRETE
1.1 SECTION INCLUDES ..................................................................................03 40 00-1
1.2 RELATED SECTIONS .................................................................................03 40 00-1
1.3 MEASUREMENT AND PAYMENT ...........................................................03 40 00-1
1.4 SUBMITTALS ...............................................................................................03 40 00-1
1.5 REFERENCES ..............................................................................................03 40 00-1
1.6 QUALITY CONTROL ..................................................................................03 40 00-1
1.7 PRODUCT DELIVERY, STORAGE AND HANDLING ............................03 40 00-2
2.1 MANUFACTURERS ....................................................................................03 40 00-2
2.2 MATERIALS .................................................................................................03 40 00-2
2.3 PRECAST CONCRETE BOAT RAMP PLANKS .......................................03 40 00-2
3.1 EXAMINATION AND PREPARATION .....................................................03 40 00-3
3.2 INSTALLATION ...........................................................................................03 40 00-3
3.3 TOLERANCES ..............................................................................................03 40 00-3
31 00 00 EARTHWORK
1.1 SECTION INCLUDES ..................................................................................31 00 00-1
1.2 RELATED SECTIONS .................................................................................31 00 00-1
1.3 MEASUREMENT AND PAYMENT ...........................................................31 00 00-1
1.4 SUBMITTALS ...............................................................................................31 00 00-1
1.5 REFERENCES ..............................................................................................31 00 00-2
2.1 MATERIALS .................................................................................................31 00 00-2
2.2 SOURCE QUALITY CONTROL .................................................................31 00 00-4
PART 3 – EXECUTION
3.1 EXAMINATION ...........................................................................................31 00 00-4
3.2 PREPARATION ............................................................................................31 00 00-4
3.3 CONSTRUCTION .........................................................................................31 00 00-5
Alaganik Slough Boat Ramp Replacement 00 00 00-v
3.4 TOLERANCE ................................................................................................31 00 00-7
3.5 QUALITY CONTROL ..................................................................................31 00 00-7
3.6 PROTECTION ...............................................................................................31 00 00-7
3.7 CLEANING ...................................................................................................31 00 00-7
31 05 19 GEOTEXTILES FOR EARTHWORK
1.1 SECTION INCLUDES ..................................................................................31 05 19-1
1.2 RELATED SECTIONS .................................................................................31 05 19-1
1.3 NOT USED ....................................................................................................31 05 19-1
1.4 SUBMITTALS ...............................................................................................31 05 19-1
1.5 REFERENCES ..............................................................................................31 05 19-1
1.6 DEFINITIONS ...............................................................................................31 05 19-2
1.7 QUALITY ASSURANCE .............................................................................31 05 19-2
1.8 DELIVERY, STORAGE, AND HANDLING ...............................................31 05 19-2
2.1 MANUFACTURER ......................................................................................31 05 19-2
2.2 MATERIALS .................................................................................................31 05 19-2
3.1 EXAMINATION AND PREPARATION .....................................................31 05 19-3
3.2 INSTALLATION ...........................................................................................31 05 19-4
32 40 00 BOULDERS
1.1 SECTION INCLUDES ..................................................................................32 40 00-1
1.2 RELATED SECTIONS .................................................................................32 40 00-1
1.3 NOT USED ....................................................................................................32 40 00-1
1.4 SUBMITTALS ...............................................................................................32 40 00-1
2.1 MATERIALS .................................................................................................32 40 00-1
3.1 GENERAL .....................................................................................................32 40 00-1
32 93 00 PLANTS
1.1 SECTION INCLUDES ..................................................................................32 93 00-1
1.2 RELATED SECTIONS .................................................................................32 93 00-1
1.3 NOT USED ....................................................................................................32 93 00-1
1.4 SUBMITTALS ...............................................................................................32 93 00-1
1.5 DEFINITION .................................................................................................32 93 00-1
1.6 DELIVERY, STORAGE AND HANDLING ................................................32 93 00-1
Alaganik Slough Boat Ramp Replacement 00 00 00-vi
1.7 PLANTING SEASON ...................................................................................32 93 00-1
2.1 MATERIALS .................................................................................................32 93 00-2
3.1 GENERAL .....................................................................................................32 93 00-3
SECTION 01 00 00 – GENERAL REQUIREMENTS January 31, 2012
Alaganik Slough Boat Ramp Replacement 01 00 00-1
01 00 00 GENERAL REQUIREMENTS
1.0 SECTION INCLUDES
1.1 Summary of Work
1.2 Existing Conditions
1.3 Coordination
1.4 Field engineering and surveying
1.5 Meetings
1.6 Submittal procedures
1.7 Construction schedules
1.8 Construction Work Plan
1.9 Permit Requirements
1.10 Not used
1.11 Shop drawings
1.12 Manufacturer’s instructions and certificates
1.13 Record drawings
1.14 Quality Control
1.15 Examination
1.16 Temporary Construction Controls – isolation & dewatering
1.17 Site access and fencing
1.18 Field office and storage
1.19 Pollution and environmental control
1.20 Delivery, handling, storage and protection
1.21 Product options
1.22 Substitutions
1.23 Final Inspection
1.24 Not Used
1.25 Measurement and payment
Alaganik Slough Boat Ramp Replacement 01 00 00-2
1.1 SUMMARY OF WORK
A. In summary, the project generally consists of the following:
1. Ensure site access is restricted to the public both the land-side and the water-side of the project.
2. Establish and maintain best management practices for site erosion and sediment control.
3. Isolate the in-stream portion of the site. Dewater as needed.
4. Clear, grub, and grade subgrade for new boat ramp.
5. Provide and place geotextile, rip-rap, and crushed aggregates for new boat ramp.
6. Provide and place pre-cast concrete boat ramp planks, including anchoring system.
7. Construct an accessible boat loading platform, consisting of a cast-in-place concrete cantilever retaining wall, sidewalk, and handrail.
8. Clear, grub, and grade subgrade for new parking lot improvements.*
9. Provide and place geotextile and crushed aggregates for parking lot improvements.*
10. Install traffic control sign(s).*
11. Demolish the existing boat ramp. *
12. Re-plant disturbed areas.*
13. Provide and install timber curbs. *
14. Provide and place boulders in and around parking lot. *
* Note: these items are “optional” bid items.
The work must be completed in accordance with the Contract Drawings and
Specifications.
B. The existing boat ramp provides insufficient access to deeper water, particularly during low tide levels/river stages. The primary purpose of this project is to construct a new boat ramp that will allow access to deeper water during a wider range of water levels.
1.2 EXISTING CONDITIONS
A. The Alaganik Slough Boat Ramp is located within the Alaganik Slough Day Use
Area, 20 miles southeast of Cordova, Alaska, within the Copper River Delta. The
Alaganik Slough Day Use Area is accessed from Cordova via a gravel road intersecting the Copper River Highway at approximately milepost 17. Cordova may be accessed by daily Alaska Airlines jet service from Anchorage and Juneau. It is also accessible by Alaska Marine Highway ferry service from Valdez and Whittier on a daily basis.
B. A site survey, limited geotechnical investigation, and hydraulic analysis have been conducted in support of the design of the replacement ramp. Field investigation notes and laboratory results are referenced in Section J.
Alaganik Slough Boat Ramp Replacement 01 00 00-3
C. Hydrodynamic conditions in the slough are influenced by tidal fluctuations and glacial melt, snow, and rainfall. While there is no existing tide/river stage gauge data for the site, measurements recorded during field work conducted in September 2009 indicate that daily water levels fluctuations are at least several feet. Tidal variations under extreme conditions may be considerably greater. Predictions of 50-year high water and 6-month low-water levels are shown on the Drawings. These estimates are based on a limited hydraulic analysis, attached to these specifications per Section J, conducted to support the project design. The average flow velocity measured in the slough during the September 2009 field study was 2.5 feet/second. These predictions and measurements are provided for information only. Contractor shall verify expected range of water elevations during period of construction.
D. Contractor shall be responsible for verifying all site characteristics and conditions pertinent to its bidding and execution of the work. Verifications should include but are not limited to anticipated high- and low-water elevations.
1.3 [NOT USED]
1.4 FIELD ENGINEERING AND SURVEYING
A. Contractor shall provide all materials, labor, equipment, and incidentals necessary and required to conduct surveys with sufficient precision to establish elevations, lines, and levels, and to certify that elevations and locations of the Work conform with Contract
Documents.
B. All site survey work shall be performed under the direction of an Alaska-licensed professional land surveyor who will be responsible for conducting field surveying and related engineering and reporting associated with certain quality control surveying, measurement for payment surveys, and construction record surveying and documentation, as specified in this section.
C. Contractor shall locate reference datum and protect survey control and reference points. Contractor shall promptly report to Contracting Officer the loss, damage, or destruction of any reference point or relocation required because of changes in grades or other reasons. Contractor shall replace dislocated survey control points based on original survey control at no additional cost to Contracting Officer. Replacement of dislocated survey control points shall be done by a licensed land surveyor in the State of Alaska. Survey accuracy and precision used to relocate disturbed control points shall be equal to or better than that used to set the original control.
D. Contractor shall be responsible for the accuracy of all surveys performed under this
Contract, including those of its subcontractors. Any work performed not conforming to the lines, grades, elevations and locations indicated on the Drawings due to survey error shall be the responsibility of Contractor, and Contractor shall repair or relocate such work to its proper location at no additional cost to the Government.
E. The following shall be submitted in accordance with the provisions the SUBMITTAL
PROCEDURES Paragraph below.
Alaganik Slough Boat Ramp Replacement 01 00 00-4
1. Within 14 calendar days of Notice to Proceed, Contractor shall furnish Engineer field survey data documenting that the job is survey staked.
2. Upon completion of the work, Contractor shall submit Field Record Documents to Engineer under the provisions of the PROJECT RECORD DOCUMENTS paragraph below.
3. Prior to start of work, Contractor shall provide proof of recent calibration of instruments by state-certified calibration and testing laboratory.
1.5 MEETINGS
A. A preconstruction meeting will be held by the Contracting Officer’s
Representative(s), and the Contractor. The Notice to Proceed will be issued after that meeting.
1. The purpose of the preconstruction meeting is to designate responsible personnel, verify understanding of the Drawings and Specifications, and establish working relationships.
2. Matters requiring coordination will be discussed and procedures for handling such matters established. At a minimum, the agenda will include the following:
a. Contractor’s schedule
b. Work plan
c. On-site coordination
d. Coordination with other contractor(s) at adjacent boardwalk project
e. Transmittal, review, and distribution of Contractor’s submittals as indicated in
1.4 of each section.
f. Health and safety planning and concerns
g. Permits: as required
h. Submittal and processing of Contractor’s periodic progress payments
i. Traffic and site access control (both land-side and water-side)
j. Progress meetings
k. Quality Control Plan
l. Temporary sediment isolation & dewatering controls
m. Pollution & Environmental Control, SWPPP submittal.
n. Demolition & Disposal plan (if Option A is awarded).
o. Precast Plank Shop Drawings & Product Data
B. Weekly progress meetings may be held during construction by the Contracting
Officer’s Representative(s) and the Contractor to review progress of work, maintain
Alaganik Slough Boat Ramp Replacement 01 00 00-5 coordination efforts, discuss changes in scheduling, and resolve problems which may develop.
C. A special meeting may be held when and if a problem or deficiency develops, or is likely to occur. At a minimum, the meeting will be attended by the Contractor and the
Contracting Officer.
1.6 SUBMITTALS
A. Submittal documents shall identify Project, Contractor, subcontractor or supplier; and pertinent Contract Document references.
B. Contractor shall certify that review, verification of Products required, field dimensions, adjacent construction Work, and coordination of information are in accordance with requirements of the Work and Contract Documents.
C. Identify product or system limitations which may be detrimental to successful performance of completed Work.
D. Contracting Officer will review the submittals, mark the document with appropriate notations, or comments and return the marked document to the Contractor for revision or filing in the Project record. Revise and resubmit submittals as required;
identify changes made since previous submittal.
E. Contractor shall prepare and submit a Construction Work Plan, per the
CONSTRUCTION WORK PLAN paragraph below, summarizing the proposed methods, equipment, and sequencing of key elements of the Work. At a minimum, the Contractor’s Construction Work Plan shall include the informational requirements listed under SUBMITTALS for each section of the Specifications, as applicable. The
Contractor’s Construction Work Plan shall be submitted to the Contracting Officer within 10 calendar days after date of Notice to Proceed.
1.7 CONSTRUCTION SCHEDULES
A. Submit schedules weekly and with each Application for Payment, identifying changes since previous version. Indicate estimated percentage of completion for each item of
Work at each submission. If no changes are made to the schedule, indicate such information on the weekly schedule submittal.
B. Submit a Gantt chart with separate lines for each section of Work, identifying the first work day of each week. Chart shall be submitted in Adobe PDF format, formatted to print on 11” x 17” paper.
Alaganik Slough Boat Ramp Replacement 01 00 00-6
1.8 CONSTRUCTION WORK PLAN
A. Within 10 calendar days after date of Notice to Proceed, Contractor shall submit a detailed Construction Work Plan describing the equipment, methods, materials and sequencing that will be used to complete all elements of the Work, including excavation, fill placement, and compaction. The work plan shall also address quality control and the use of temporary controls. Specific work elements to be included
Construction Work Plan are identified in the subsequent sections of these specifications.
1.9 PERMIT REQUIREMENTS
A. Permits have been secured from the US Army Corp of Engineers and the State of
Alaska Department of Fish & Game.
B. Permit language from ADF&G stipulates a requirement to isolate the in-stream construction area from the Slough to eliminate sedimentation potential. To comply with salmon migration windows, the isolation structure must be in place before May
01 and removed before June 30. In-stream work may occur behind the isolation structure as necessary throughout this time frame. Structure removal must be coordinated with existing ramp demolition if it is awarded as part of this contract.
C. Per the ADF&G permit, any stranded fish must be returned to the free flowing Slough immediately upon isolation. The USFS will coordinate the trapping and relocation of stranded fish at no cost to the contractor as long as 48 hour notice is provided.
C. During any dewatering activities, water must be pumped to a sedimentation basin or other upland site.
D. No vegetation clearing activities shall occur between May 01 and July 01 to avoid disturbance to nesting migratory birds and waterfowl. Note that the majority of needed clearing was completed in 2011 via a separate contract. Other out-of-stream construction activities may be conducted during this nesting window and may continue through August 31, 2012.
1.10 [NOT USED]
1.11 SHOP DRAWINGS
A. When required by individual specification sections, provide shop drawings signed and sealed by a professional engineer responsible for designing components shown on shop drawings.
1. Include signed and sealed calculations to support design.
2. Submit drawings and calculations in a form suitable for submission to and approval by CO.
3. Make revisions and provide additional information when required.
B. All drawings and submittal data shall be submitted in Adobe PDF format, formatted to print on 8½” x 11” or 11” x 17” paper, and in quality suitable for reproduction.
Alaganik Slough Boat Ramp Replacement 01 00 00-7
C. All drawings and submittal data shall be marked with Contractor’s submittal review stamp and signature, certifying review of submittal, verification of field measurements, and compliance with Contract Documents.
1.12 MANUFACTURER’S INSTRUCTIONS AND CERTIFICATES
A. When specified in individual specification sections, submit manufacturer printed instructions for delivery, storage, assembly, installation, adjusting, and finishing.
B. Indicate material or Product conforms to or exceeds specified requirements. Submit supporting reference data, and certifications as appropriate.
1.13 PROJECT RECORD DOCUMENTS
A. The purpose of the Project Record Documents is to provide factual information regarding all aspects of the Work, both concealed and visible, to enable future modification of the Work to proceed without lengthy and expensive site exploration.
B. Contracting Officer shall supply to the Contractor electronic files of the drawings on compact disc as “.dwg” files compatible with AutoCAD version 2010 or higher.
Contractor shall utilize the electronic files to prepare final project record drawings compatible with AutoCAD 2010 and IBM-compatible equipment.
C. Contractor shall carefully transfer data shown on the Job Set to the corresponding electronic files, coordinating the changes as required. Revised drawings shall clearly indicate each affected detail and drawing and include a full description of changes made during construction and the actual location of items.
D. Call attention to each entry by drawing a "cloud" around the area or areas affected.
E. Make changes neatly and consistently to assure readability and clear reproduction.
F. Contractor is required to supply to the Contracting Officer electronic files of the drawings on compact disc as “.dwg” files compatible with AutoCAD version 2010 with all recorded changes as noted above immediately following approval of and acceptance of all work.
1.14 QUALITY CONTROL
A. Contractor shall submit, as part of the Construction Work Plan, a Quality Control
Plan to ensure that quality control is actively and appropriately being performed throughout the duration of the project. This QC Plan shall include monitoring quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality.
B. Comply with manufacturer’s instructions.
C. Contractor must comply with project specifications and meet all building codes and as minimum quality for the Work.
1.15 NOT USED
1.16 TEMPORARY CONSTRUCTION CONTROLS – ISOLATION & DEWATERING
A. Contractor shall sufficiently examine the site conditions to determine the scope of isolation controls required for the completion of the Work set forth in these Contract
Alaganik Slough Boat Ramp Replacement 01 00 00-8
Specifications and Drawings. Additionally, dewatering may be required at various stages of the ramp and retaining wall construction. Dewatering is the sole responsibility of the contractor and a plan should be included in detail with the contractor’s project proposal.
B. Contractor shall retain the services of an appropriately qualified professional engineer with isolation and dewatering experience to design such controls, and shall assume full responsibility for its performance and safety.
C. Any and all costs for design (including site characterization and engineering), installation, operation and maintenance, and decommissioning of temporary isolation and dewatering controls shall be included in Contractor’s bid price for the Work, in accordance with the MEASUREMENT AND PAYMENT paragraph of this section.
1.17 SITE ACCESS AND FENCING
A. Contractor is not required to maintain public access to the site, however access up to the Alaganik Use Area will be allowed throughout the duration of the project to service the campsites and boardwalk. Parking for the boardwalk will be located approximately 100 yards up the Alaganik Slough Road from the boardwalk. Site access should be restricted at the entrance to the Use Area with a diversion guiding pedestrians to the boardwalk. The Slough serves as an important public access point and therefore swift construction is encouraged for the benefit of public usage.
Contractor is responsible for maintaining site security. USFS, Cordova Ranger
District may approve, on a case-by-case basis, old boat ramp access for administrative purposes. This access will be granted no more than 3 times per week with vehicle and trailer parking at the aforementioned parking area, not within the project site.
Such access will be arranged with the contractor at least 24 hours in advance.
B. It is the contractor’s responsibility to provide mandatory site closure devices (e.g.
signs, fencing) and pedestrian diversion fencing. Additionally, the contractor is responsible for site security around the construction work area and lay-down or “bone yard” site. Any locking mechanisms at the site entrance must be coordinated with the
Contracting Officer to ensure emergency access by the USFS is maintained.
Coordinate with Contracting Officer for acceptance of layout prior to installation.
1.18 FIELD OFFICE AND STORAGE
A. Contractor shall provide its own weather-tight field office and storage, as needed to facilitate the Work. Contractor shall coordinate space for lay-down or “bone yard” area with the Contracting Officer prior to commencement of the Work. Due to the remote location of the Site, utilities (e.g., water, sewer, electricity, etc.) are unavailable, and the Contractor shall make its own arrangements, as needed, to support its temporary facilities.
1.19 POLLUTION AND ENVIRONMENTAL CONTROL
A. Contractor shall include as part of its Construction Work Plan a description of the proposed methods, means, and facilities to prevent contamination of soil, water, and
Alaganik Slough Boat Ramp Replacement 01 00 00-9 atmosphere from discharge of noxious, toxic substances, and pollutants produced by construction operations.
B. Contractor shall be responsible for preparing a Stormwater Pollution Prevention Plan
(SWPPP) to address provisions of EPA’s General Permit for Construction Activities, as administered by the Alaska Department of Environmental Conservation.
Contractor is responsible for selecting, and describing the appropriate best management practices (BMPs) to protect stormwater discharge quality at the construction site. Contractor shall effectively implement selected BMPs to ensure compliance with permit conditions. Contractor shall provide a completed, signed original of the Notice of Intent and Notice of Termination in accordance with permit conditions.
C. Contractor shall include as part of its Construction Work Plan, an Erosion and
Sediment Control Plan.
D. Contractor shall comply with all applicable environmental, erosion, and water quality control regulations and permit requirements.
1.20 DELIVERY, HANDLING, STORAGE AND PROTECTION
A. Deliver, handle, store, and protect Products in accordance with manufacturer’s instructions.
B. The Contracting Officer will not accept any damaged or otherwise compromised products, regardless of the cause of such damage.
1.21 PRODUCT OPTIONS
A. Products Specified by Reference Standards or by Description Only: Any Product meeting those standards or description.
B. Products Specified by Naming One or More Manufacturers with Provision for
Substitutions: Submit request for substitution for manufacturers not named.
1.22 NOT USED
1.23 FINAL INSPECTION
A. Final Inspection: Final Inspection shall be defined as that period at which all work in the Contract is 100% complete and no minor details remain to be performed.
1. The Contractor shall notify the Contracting Officer in writing, at least 30 days prior to the date requested on which the work will be ready for final inspection.
B. Final pay request will be processed for payment upon final inspection and Contracting
Officer’s certification that work under the contract is 100% complete.
C. Execute final cleaning prior to final inspection. Remove waste and surplus materials, rubbish, and construction equipment and facilities from site.
1.24 [NOT USED]
1.25 MEASUREMENT AND PAYMENT
A. Measurement for payment will be at the lump sum or unit price stipulated in the
Schedule of Items. Payment shall be considered full compensation for furnishing all
Alaganik Slough Boat Ramp Replacement 01 00 00-10 labor, materials and equipment to complete the Work in accordance with the requirements and intent of the Contract Documents, including the Contract
Specifications, and Drawings.
B. Only the pay items listed in the Schedule of Items shall be considered for measurement and payment.
C. Pay Items
Items will be measured and paid per the Schedule of Pay Items and Measurement and
Payment Terms below. The following definitions shall apply:
“Each” or “EA” – These quantities denote one complete unit, which may consist of one or more parts.
“Lump Sum Quantities” or “LS” or “LSQ” - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor needed to complete the job. They will not be measured.
“Linear Foot” or “LF” – Measurement is on a plane parallel to the surface being measured.
“Square Foot,” “SF,” “Square Yard,” or “SY” - Measurement is on a plane parallel to the surface being measured, in either square feet or square yards.
“Cubic Yard” or “CY” - Measurement is computed by the average-end area method from measurements made longitudinally along a centerline or other reference line.
All CY quantities are measured in-place and compacted.
“Designed Quantities” or “DQ” - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units SHOWN in the
SCHEDULE OF ITEMS may be authorized under the following conditions:
(1) As a result of changes in the work authorized by the Contracting Officer.
AND
(2) As a result of the Contracting Officer determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
AND
(3) As a result of the Contractor submitting to the Contracting Officer a written request showing evidence of errors in the original design that cause a pay item
Alaganik Slough Boat Ramp Replacement 01 00 00-11 quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
“Actual Quantities” or “AQ” - These quantities are determined from measurement of completed work. Payment is governed by FAR 52.211-18.
END OF SECTION
SECTION 02 40 00 – DEMOLITION January 31, 2012
Alaganik Slough Boat Ramp Replacement 02 40 00-1
1.1 SECTION INCLUDES
A. Work specified in this section includes, but is not necessarily limited to, the following:
1. Protecting items designated to remain.
2. Demolishing of existing boat ramp.
3. Removing, hauling and disposal of demolished materials.
1.2 RELATED SECTIONS
A. Related Sections:
1. Section 01 00 00 General Requirements
2. Section 31 10 00 Site Clearing
3. Section 32 93 00 Plants
1.3 MEASUREMENT AND PAYMENT
A. Refer to the MEASUREMENT AND PAYMENT paragraph in Section 01 00 00, Part
1.
1.4 SUBMITTALS
A. See SUBMITTAL PROCEDURES paragraph in Section 01 00 00, Part 1.
B. Demolition schedule: Indicate sequence and schedule on overall Project schedule.
C. Within 20 calendar days after date of Notice to Proceed, Contractor shall submit a
Demolition Plan meeting the following minimum requirements:
1. Indicate procedures and operational sequence of demolishment and removal.
2. Address means of protecting the environment, as appropriate.
D. Contractor’s Construction Work Plan shall include a Demolition and Disposal Plan for demolishment, removal, transport and disposal of debris, as required.
1.5 NOT USED
PART 2 - PRODUCTS
Not Used
3.1 EXAMINATION
A. Verify clearing and grubbing and site features and site structures to be protected, removed and demolished.
3.2 EROSION/POLLUTION CONTROL
A. Any required erosion/pollution control measures shall be in place prior to beginning work of this section.
SECTION 02 40 00 – DEMOLITION January 31, 2012
Alaganik Slough Boat Ramp Replacement 02 40 00-2
3.3 TEMPORARY ISOLATION & DEWATERING
A. Implement temporary isolation and dewatering controls in accordance with the
TEMPORARY CONSTRUCTION CONTROLS – ISOLATION & DEWATERING
paragraph in Section 01 00 00, Part 1.
3.4 EXISTING CONDITIONS
A. Demolition work shown on Drawings is schematic in nature. Bidders are encouraged to visit the site to verify quantity and details of demolition work. If any materials are deemed suitable for reuse, contractor must propose such action to the CO for consideration.
B. Provide, erect and maintain temporary construction fencing around the construction area and any existing items or facilities designated by the Contracting Officer to remain.
3.5 [NOT USED}
3.6 SITE DEMOLITION
A. Sprinkle debris with water, as necessary, to limit dust to lowest practicable level.
B. Existing utilities (e.g., culverts) within the project area shall remain in operation throughout construction.
3.7 [NOT USED]
3.8 STOCKPILING OF MATERIALS
A. Contractor may not have sufficient area on site to stockpile excavated materials for later use in the project. If additional stockpile area is required to complete the Work, Contractor shall arrange offsite stockpile areas. No additional payments will be made for stockpiling excavated materials offsite. Stockpiling of salvaged materials shall be carefully segregated into well defined stockpiles.
3.9 DISPOSAL OF MATERIALS
A. Refuse resulting from site preparation shall be disposed by Contractor in a manner consistent with all government regulations.
1. No on-site burning permitted.
2. Do not leave refuse material on the project site, shoved onto abutting private properties, or buried in embankments or trenches on the project site.
3. Maintain hauling routes clean and free of debris resulting from work of this section.
B. Contractor shall arrange an offsite disposal location for excess excavated material and demolished boat ramp planks.
SECTION 03 30 00 – CAST-IN-PLACE CONCRETE January 31, 2012
Alaganik Slough Boat Ramp Replacement 03 30 00-1
A. This section includes cast-in-place concrete to be used in the construction of a cantilever retaining wall and a sidewalk.
1.2 RELATED SECTIONS
A. Related Sections:
1. Section 01 00 00 General Requirements.
1.3 MEASUREMENT AND PAYMENT
A. Refer to MEASUREMENT AND PAYMENT paragraph in Section 01 00 00, Part 1.
1.4 SUBMITTALS
A. Section 01 00 00 – General Requirements: Submittal procedures.
B. At least 40 days prior to scheduled production, Contractor shall submit concrete mix design for each specified class of concrete to the Contracting Officer for approval.
C. Contractor’s Construction Work Plan. Contractor shall describe in its Construction
Work Plan the temporary construction controls (including dewatering), equipment, construction methods, and sequencing (relative to other Work elements) that will be used for completion of the Work specified in this section of the Contract
Specifications and associated Drawings.
D. Project Record Drawings: Accurately record location and details of finished cast-in-place concrete work in accordance with Section 01 00 00 General Requirements.
1.5 REFERENCES
A. American Concrete Institute:
1. ACI 318 – Building Code Requirements for Structural Concrete.
B. ASTM International:
1. ASTM A185 – Steel Welded Wire Fabric, Plain, for Concrete Reinforcement.
2. ASTM A615 – Standard Specification for Deformed and Plain Carbon-Steel
Bars for Concrete Reinforcement.
3. ASTM C150 – Standard Specification for Portland Cement.
1.6 QUALITY CONTROL
A. Contractor’s personnel shall be regularly engaged in the placement and finishing of reinforced cast-in-place concrete, and shall be subject to the approval of the
Contracting Officer. Placement of the cast-in-place concrete for the cantilever retaining wall or sidewalk shall not proceed until approval of the forms, steel reinforcement, slump test, and concrete mix design has been given by the Contracting
Officer.
1.7 PRODUCT DELIVERY, PLACEMENT, AND CURING
A. Deliver, place, and cure cast-in-place concrete by methods consistent with the 2004
ADOT&PF, Section 501 – Structural Concrete, specifications for construction of retaining walls and sidewalks. Do not backfill against concrete structures until the
Alaganik Slough Boat Ramp Replacement 03 30 00-2 concrete has attained a compressive strength of at least 80% of the specified compressive strength.
2.1 CONCRETE MATERIALS
A. Cement: ASTM C150: Type II Portland Cement.
B. Aggregate, Sand, Water, and Admixtures: Determined by concrete supplier as appropriate to the design requirements listed in section 2.4 below, for a marine environment and in accordance with ACI 318.
C. Compressive strength: 3,000 psi at 28 days.
D. Reinforcing steel
1. Bars: ASTM A615, grade 60, deformed.
2.2 ADMIXTURES
Procure commercial concrete admixtures, conforming to the requirements of the
ADOT&PF for purposes of constructing a reinforced concrete cantilever retaining wall and a sidewalk.
2.3 JOINT DEVICES AND FILLER MATERIALS
Supply commercially available concrete joint devices and filler materials applicable to sidewalk construction.
2.4 CONCRETE MIX
Procure commercial structural grade concrete from a local source, conforming to the requirements of the ADOT&PF for purposes of constructing a reinforced concrete cantilever retaining wall and a sidewalk. Supply a copy of the concrete mix design, including any admixtures, for each specified class of concrete to the Contracting Officer 40 days prior to the date of placement for approval. Retaining wall shall be constructed with
ADOT&PF Class A concrete, and sidewalk shall be constructed with ADOT&PF Class W concrete.
A. Comply with the ADOT&PF STANDARD SPECIFICATIONS FOR HIGHWAY
CONSTRUCTION, 2004.
3.2 PREPARATION
A. Comply with the ADOT&PF STANDARD SPECIFICATIONS FOR HIGHWAY
CONSTRUCTION, 2004.
3.3 TEMPORARY DEWATERING
CONSTRUCTION, 2004.
Alaganik Slough Boat Ramp Replacement 03 30 00-3
3.4 PLACING CONCRETE
A. Comply with the ADOT&PF STANDARD SPECIFICATIONS FOR HIGHWAY
CONSTRUCTION, 2004.
3.5 CONCRETE FINISHING
A. Comply with the ADOT&PF STANDARD SPECIFICATIONS FOR HIGHWAY
CONSTRUCTION, 2004.
3.6 CURING AND PROTECTION
A. Comply with the ADOT&PF STANDARD SPECIFICATIONS FOR HIGHWAY
CONSTRUCTION, 2004.
3.7 FIELD QUALITY CONTROL
A. Comply with the ADOT&PF STANDARD SPECIFICATIONS FOR HIGHWAY
CONSTRUCTION, 2004.
3.8 DEFECTIVE CONCRETE
A. Comply with the ADOT&PF STANDARD SPECIFICATIONS FOR HIGHWAY
CONSTRUCTION, 2004.
3.9 TOLERANCES
CONSTRUCTION, 2004.
SECTION 03 40 00 – PRECAST CONCRETE January 31, 2012
Alaganik Slough Boat Ramp Replacement 03 40 00-1
A. This section includes precast concrete boat ramp planks and associated anchoring and curbs.
1.2 RELATED SECTIONS
A. Related Sections:
1. Section 01 00 00 General Requirements.
1.3 MEASUREMENT AND PAYMENT
A. Refer to MEASUREMENT AND PAYMENT paragraph in Section 01 00 00, Part 1.
1.4 SUBMITTALS
A. Section 01 00 00 – General Requirements: Submittal procedures.
B. Within 20 calendar days after date of Notice to Proceed, Contractor shall submit Shop
Drawings meeting the following minimum requirements:
1. Fully dimensioned shop and installation drawings. Include details for clearances, reinforcement material and sizes, weld plates and welding, anchors, accessories, joints, and surface finishing.
C. Within 20 calendar days after date of Notice to Proceed, Contractor shall submit
Product Data: Manufacturer’s catalog sheets, specifications, and installation instructions. Include precast manufacturer’s instructions and limitations.
D. Contractor’s Construction Work Plan. Contractor shall describe in its Construction
Work Plan the temporary construction controls (including dewatering, if applicable), equipment, construction methods, and sequencing (relative to other Work elements) that will be used for completion of the Work specified in this section of the Contract
Specifications and associated Drawings. Include proposed methods of installation, including anchoring and inter-plank connections.
E. Project Record Drawings: Accurately record location and details of finished precast concrete work in accordance with Section 01 00 00 General Requirements.
1.5 REFERENCES
A. American Concrete Institute:
1. ACI 318 – Building Code Requirements for Structural Concrete.
B. ASTM International:
1. ASTM A615 – Standard Specification for Deformed and Plain Carbon-Steel
Bars for Concrete Reinforcement.
2. ASTM C150 – Standard Specification for Portland Cement.
1.6 QUALITY CONTROL
A. Manufacture: Precast concrete boat ramp planks shall be plant fabricated.
B. Manufacturer’s Qualifications: The manufacturer of the precast boat ramp planks shall be regularly engaged in the production of such products, shall have furnished such products for five similar projects that have been in service for not less than three
Alaganik Slough Boat Ramp Replacement 03 40 00-2 years, and shall be subject to the approval of the Contracting Officer. Work on the precast slabs shall not proceed until approval of the proposed manufacturer has been given by the Contracting Officer.
1.7 PRODUCT DELIVERY, STORAGE AND HANDLING
A. Deliver, store and handle precast materials by methods that will prevent damage, in accordance with Section 01 00 00, Part 1, PRODUCT DELIVERY, HANDLING, STORAGE and PROTECTION.
2.1 MANUFACTURERS
A. Acceptable manufacturers:
1. Anchorage Sand and Gravel
2. Fairbanks Precast Concrete
3. Or approved equal
2.2 MATERIALS
Precast concrete boat ramp plank materials shall satisfy the following criteria.
A. Cement: ASTM C150: Type II Portland Cement, or as determined appropriate to the design requirements by the precast fabricator.
B. Aggregate, Sand, Water, and Admixtures: Determined by precast fabricator as appropriate to the design requirements, for a marine environment and in accordance with ACI 318.
C. Compressive strength: 4,000 psi at 28 days.
D. Reinforcing steel
1. Bars: ASTM A615, deformed.
E. Wire rope: Stainless steel wire rope, per plans.
F. Bolts and nuts: Hot-dip galvanized (AASHTO M 111), per plans.
2.3 PRECAST CONCRETE BOAT RAMP PLANKS
A. Size: as indicated on the Drawings.
B. Finish: V-grooves, 1”x 1” and aligned 60° to the longitudinal axis of the launching ramp. Alternative finishes must be submitted for approval by the Contracting Officer.
C. Precast concrete boat ramp planks shall be supplied with all accessories required for installation and anchoring in accordance with the Drawings. Materials include, but are not limited to stainless steel wire rope, Alaska Yellow Cedar curbs, galvanized bolts and nuts, as indicated on the Drawings. Inter-plank connection details must be submitted for approval by the Contracting Officer, in accordance with SUBMITTALS paragraph above.
Alaganik Slough Boat Ramp Replacement 03 40 00-3
3.1 EXAMINATION AND PREPARATION
A. Verify site subgrade has been prepared in accordance with the Drawings and Section
31 00 00 – Earthwork of these Specifications. Examine and verify site conditions are ready to receive work.
3.2 INSTALLATION
A. Install precast concrete boat ramp planks as shown on the drawings and in accordance with the manufacturer’s instructions and…