Addendum826016HG.pdf
PDF 469 KB Posted
- Attached to
- U. S. Highway 27 Water Main Replacement
- Solicitation number
- IFB 26-016-HG
- Issued by
- Lake County, Florida
About this file
This is Addendum No. 8 issued by the City of Leesburg, Florida's Procurement Manager Hosea Goodwyn on August 6, 2026, for IFB 26-016-HG: U.S. Highway 27 Water Main Replacement project. The addendum addresses 15 questions and clarifications from interested bidders regarding project specifications, quantities, materials, and procedures. Key revisions include correcting the asphalt open cut and repair parking lot quantity from 3,200 square yards to 356 square yards, adding a line item for "All Other Work Not Previously Listed" to accommodate ductile iron pipe and newly installed sidewalk payment, confirming that doghouse-style manholes with concrete base slabs are acceptable for gate valves, and clarifying that gate valves in manhalls must be flanged. The addendum specifies that asphalt restoration at the boat ramp entrance has been revised to open cutting of the driveway, that tie-ins to existing piping shall use 45-degree bends where possible with existing mains capped when cut, and that the City will consider change orders for differing subsurface conditions. The City will provide a lay-down yard for equipment and materials, and meter box replacement is not anticipated. Water mains removed from service shall be capped with fire hydrants removed, but grout filling is not required. The revised Itemized Price Schedule dated August 6, 2026 reflects these modifications and includes both Phase 1 base bid items and Additive Alternate 1 (Phase 2) items.
Bidders must acknowledge receipt of Addendum No. 8 by indicating receipt on the Proposal Bid Form, and if a bid has already been submitted, it must be revised electronically to include this addendum. All bids received will be construed as acknowledgments of receipt of the addendum. The addendum establishes that the project will be awarded based on the Base Bid (Phase 1) alone, not on a combined total of base bid and alternate. The revised price schedule encompasses Phase 1 base bid items such as mobilization, maintenance of traffic, construction staking, pressure testing, density testing, disinfection and bacteriological sampling, erosion control, parking lot restoration, various sizes of C900 PVC pipe, gate valves, air release valves, water service connections, fire hydrant assemblies, directional bore segments, and Bahia sod restoration, along with Phase 2 additive alternate items following similar categories with adjusted quantities. The itemized price schedule provides unit prices and total price columns for all bid items in both phases, with a final line calculating total costs for the base bid and combined base bid plus additive alternate.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATE: August 6, 2026 TO: All Interested Bidders and Other Interested Parties FROM: Hosea Goodwyn, Procurement Manager
The City makes the following changes, additions, deletions, information, and/or clarifications and now considers the addendum a part of the IFB Document. Bidders must acknowledge receipt of this addendum by indicating receipt in the space provided on the Proposal Bid Form.
If the bidder has already submitted the Proposal Bid Form to the City’s Procurement Division, the Bidder should revise their electronic submission to include this addendum. In any case, the submission of a bid is an acknowledgment of receipt of the addendum. The City will construe all bids received as though the Bidder has received and acknowledged the addendum.
Below is the City’s reply to RFIs (Request for Information – a/k/a bid inquiries or questions) submitted by interested parties by the posted deadline to submit RFIs.
Q1. Based on the bid form, please confirm that the project will be awarded based on the lowest combined total of the base bid and alternate.
A1. Please refer to the Proposal Bid Form. *Award base off Base Bid (Phase 1).
Q2. The bid form quantity on bid item 8 of Phase 1 shows a quantity of 3200 SY. The plans only show about 300 LF of open cut and repair parking lot at the Boat Ramp. Please verify the quantities.
A2. The quantity in the bid form is incorrect. The bid form has been revised to show 356 SY of asphalt open cut and repair.
Q3. Is Ductile iron pipe to be bid in the PVC Pay item?
A3. A line item was added to each phase for All Other Work Note Previously Listed.
Q4. For gate valves in manholes, can the manhole be doghouse bottom?
A4. Yes, doghouse manholes are acceptable. A concrete base slab shall be cast in place if the dog house manholes are utilized.
Q5. Are the gate valves placed in manholes to be flanged gate valves?
A5. Yes, gate valves in the manholes are to be flanged.
Q6. Upon site visit there was observed to be newly installed sidewalk. How will this be paid?
A6. A line item was added to each phase for All Other Work Note Previously Listed.
IFB 26-016-HG
U.S. Highway 27 Water Main Replacement
Addendum No. 8
Q7. Phase 1 sheet C-9 entrance to boat ramp is indicated for both asphalt restoration and drill.
Is asphalt restoration necessary in this area.
A7. Phase 1 Sheet C-9 has been revised to show open cutting of the driveway.
Q8. Do water service connections require replacement of meter box?
A8. Replacement of meter boxes is not anticipated.
Q9. Where plans state to connect via "cut in"; with exception of fire hydrant pipe, what type of cut in is expected? Bend and or tee? Is the existing main remaining in service or is the existing main to be capped?
A9. Tie-ins to existing piping shall be made with 45 degree bends where possible. The existing main is to be capped where it is cut.
Q10. Since the plans are arial and conditions have changed, how will changed field conditions be handled? Will Contractor be allowed change order if items encountered are not on plans?
A10. In the event that unknown subsurface conditions are encountered change orders will be considered for differing site conditions.
Q11. At connections, is the existing main to be restrained?
A11. The existing water mains that will be connected to were originally constructed with joint restraints.
Q12. Please verify phase 1 bid item 8 quantity and unit. Is this supposed to be 3200 SY or SF?
A12. The quantity in the bid form is incorrect. The bid form has been revised to show 356 SY of asphalt open cut and repair.
Q13. Other than the abandonment of the existing 12-inch water main from Station 269+00 to
Station 278+64, are there any additional existing water mains that are to be abandoned as part of this project? Additionally, is the abandoned water main to be cut, capped, and filled with grout in accordance with the project requirements? If so, please consider adding separate bid items, measured by linear foot, for each pipe size requiring abandonment, cutting/capping, and grout filling to allow for accurate and consistent bidding.
A13. Refer to Note 42 on Sheet G-1 of the Phase 1 drawings. Water mains that are removed from service shall be capped, and fire hydrants shall be removed. Grout filling of the pipes is not required.
Q14. Regarding the Schedule of Values, Line Item 8 – Open Cut & Repair Parking Lot, the listed quantity appears to indicate replacement of the entire parking lot. Please confirm whether this is the intent, or if the repair is limited to the trench restoration between Station 244+20 and Station 247+80. Based on an assumed 10-foot-wide pavement patch, the estimated restoration area is approximately 400 square yards. If the intent is limited trench restoration, please clarify the basis for the bid quantity or revise the Schedule of Values accordingly.
A14. The quantity in the bid form is incorrect. The bid form has been revised to show 356 SY of asphalt open cut and repair.
Q15. Will the City provide a lay down yard for equipment and material?
A15. Yes, the City of Leesburg will be providing a lay down yard for equipment and materials.
The following document is hereby made part of the solicitation.
1. Revised Itemized Price Schedule dated 8/06/2026
ACKNOWLEDGMENT - Addendum No. 8
Company Name
Signature of Officer
Type/Print Officer's Name & Title
US 27 Water Main Replacement IFB 26-016-HG
REVISED ITEMIZED PRICE SCHEDULE. DATE: 8/06/2026
Item # Description Quantity Unit Unit Price Total Price
Phase 1
1 Mobilization 1 LS $ $ 2 Maintenance of Traffic 1 LS $ $ 3 Construction Staking/As-Built 1 LS $ $ 4 Pressure Test Water Line 1 LS $ $ 5 Density Testing 1 LS $ $ 6 Disinfection/Bac-T Sampling 1 LS $ $ 7 Erosion Control/Silt Fence 15,000 LF $ $ 8 Open Cut & Repair Parking Lot 356 SY $ $ 9 6" C900 PVC Pipe 180 LF $ $ 10 6" Gate Valve & Box 3 EA $ $ 11 8" C900 PVC Pipe 230 LF $ $ 12 8" Gate Valve & Box 9 EA $ $ 13 10" C900 PVC Pipe 110 LF $ $ 14 10" Gate Valve & Box 3 EA $ $ 15 10" Tapping Sleeve and Valve 1 EA $ $ 16 12" C900 PVC Pipe 12,210 LF $ $ 17 12" Gate Valve & Box 35 EA $ $ 18 12" DIP Fittings 1 LS $ $ 19 14" PE 4710 Directional Bore 5,640 LF $ $ 20 2" Air Release Valve and Vault 9 EA $ $ 21 Water Service Connection 8 EA $ $ 22 New Fire Hydrant Assembly - Complete 14 EA $ $ 23 Connect to Existing WM 18 EA $ $ 24 Temporary Jumper Connection 1 EA $ $ 25 Restoration - Bahia Sod 15,000 SY $ $ 26 NPDES Permit 1 LS $ $
27 All Other Work Not Previously Listed $ $ Total Project Costs (Base Bid) $
Additive Alternate 1 (Phase 2)
Item # Description Quantity Unit Unit Price Total Price 1 Mobilization 1 LS $ $ 2 Maintenance of Traffic 1 LS $ $ 3 Construction Staking/As-Built 1 LS $ $ 4 Pressure Test Water Line 1 LS $ $ 5 Density Testing 1 LS $ $ 6 Disinfection/Bac-T Sampling 1 LS $ $ 7 Erosion Control/Silt Fence 12,000 LF $ $ 8 10" C900 PVC Pipe 24 LF $ $ 9 10" Gate Valve & Box 2 EA $ $
10 10" Tapping Sleeve and Valve 2 EA $ $ 11 12" C900 PVC Pipe 7,474 LF $ $ 12 12" Gate Valve & Box 20 EA $ $ 13 12" DIP Fittings 1 LS $ $ 14 14" PE 4710 Directional Bore 2,014 LF $ $ 15 2" Air Release Valve and Vault 7 EA $ $ 16 Water Service Connection 8 EA $ $ 17 New Fire Hydrant Assembly - Complete 11 EA $ $ 18 Connect to Existing WM 3 EA $ $ 19 Temporary Jumper Connection 1 EA $ $ 20 Restoration - Bahia Sod 12,000 SY $ $ 21 NPDES Permit 1 LS $ $ 22 All Other Work Not Previously Listed $ $
Total Costs (Additive Alternate Bid 1) $
Total Cost (Base Bid + Additive Alternate Bid)