Addendum1026016HG.pdf
PDF 306 KB Posted
- Attached to
- U. S. Highway 27 Water Main Replacement
- Solicitation number
- IFB 26-016-HG
- Issued by
- Lake County, Florida
About this file
This is Addendum No. 10 to Invitation for Bid (IFB) 26-016-HG for the U.S. Highway 27 Water Main Replacement project issued by the City of Leesburg, Florida on August 12, 2026. The addendum revises the Itemized Price Schedule, which details line items for Phase 1 (base bid) and Additive Alternate 1 (Phase 2). Phase 1 encompasses 27 line items including mobilization, maintenance of traffic, construction staking, testing services, erosion control (15,000 linear feet of silt fence), parking lot repairs (356 square yards), various water main pipe installations (6-inch through 14-inch directional bore totaling approximately 20,274 linear feet), valve and hydrant installations, service connections, and site restoration using Bahia sod (15,000 square yards). Phase 2 comprises 21 line items with similar components scaled for the second phase, including 12,000 linear feet of silt fence, 7,498 linear feet of pipe work, and 12,000 square yards of sod restoration. Bidders must acknowledge receipt of this addendum on their Proposal Bid Form, and submission of a bid constitutes acknowledgment of receipt. The original bid due date was July 29, 2026 at 11:00 a.m., with the contract term spanning 21 months (Phase 1 for 12 months and Phase 2 for 9 months).
All bids must include unit prices and total prices for each line item in the revised schedule. The engineer's estimate totals $4.66 million for Phase 1 and $2.51 million for Phase 2, with a combined total of $7.17 million. Bidders must be Florida-licensed Certified Contractors. A 5 percent bid guarantee, 100 percent performance and payment bond, and $1 million comprehensive general liability insurance per occurrence are required. Payment terms are net 30 days with 90 percent upon certification and 10 percent retained until final acceptance and expiration of the two-year maintenance period. Liquidated damages are assessed at $1,685 per calendar day for delays beyond substantial completion. No set-asides, Davis-Bacon wage requirements, Maintenance Bond requirements, Build by America requirements, or minority contracting goals apply to this project.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IFB 26-016-HG
U.S. Highway 27 Water Main Replacement
Addendum No. 10
DATE: August 12, 2026 TO: All Interested Bidders and Other Interested Parties FROM: Hosea Goodwyn, Procurement Manager
The City makes the following changes, additions, deletions, information, and/or clarifications and now considers the addendum a part of the IFB Document. Bidders must acknowledge receipt of this addendum by indicating receipt in the space provided on the Proposal Bid Form.
If the bidder has already submitted the Proposal Bid Form to the City’s Procurement Division, the Bidder should revise their electronic submission to include this addendum. In any case, the submission of a bid is an acknowledgment of receipt of the addendum. The City will construe all bids received as though the Bidder has received and acknowledged the addendum.
The following changes are hereby made part of the solicitation.
1. IFB-26-016-HG ATTACHMENT C – ITEMIZED PRICE SCHEDULE REVISED DATE 8.12.2026
ACKNOWLEDGMENT - Addendum No. 10
Company Name
Signature of Officer
Type/Print Officer's Name & Title
US 27 Water Main Replacement IFB 26-016-HG ITEMIZED
PRICE SCHEDULE REVISED DATE: 8/12/2026
Item # Description Quantity Unit Unit Price Total Price
Phase 1 1 Mobilization 1 LS $ $ 2 Maintenance of Traffic 1 LS $ $ 3 Construction Staking/As-Built 1 LS $ $ 4 Pressure Test Water Line 1 LS $ $ 5 Density Testing 1 LS $ $ 6 Disinfection/Bac-T Sampling 1 LS $ $ 7 Erosion Control/Silt Fence 15,000 LF $ $ 8 Open Cut & Repair Parking Lot 356 SY $ $ 9 6" C900 PVC Pipe 180 LF $ $ 10 6" Gate Valve & Box 3 EA $ $ 11 8" C900 PVC Pipe 230 LF $ $ 12 8" Gate Valve & Box 9 EA $ $ 13 10" C900 PVC Pipe 110 LF $ $ 14 10" Gate Valve & Box 3 EA $ $ 15 10" Tapping Sleeve and Valve 1 EA $ $ 16 12" C900 PVC Pipe 12,210 LF $ $ 17 12" Gate Valve & Box 35 EA $ $ 18 12" DIP Fittings 1 LS $ $ 19 14" PE 4710 Directional Bore 5,640 LF $ $ 20 2" Air Release Valve and Vault 9 EA $ $ 21 Water Service Connection 8 EA $ $ 22 New Fire Hydrant Assembly - Complete 14 EA $ $ 23 Connect to Existing WM 18 EA $ $ 24 Temporary Jumper Connection 1 EA $ $ 25 Restoration - Bahia Sod 15,000 SY $ $ 26 NPDES Permit 1 LS $ $
27 Sidewalk Replacement 200 SY $ $
Total Project Costs (Base Bid) $
Additive Alternate 1 (Phase 2) Item # Description Quantity Unit Unit Price Total Price
1 Mobilization 1 LS $ $ 2 Maintenance of Traffic 1 LS $ $ 3 Construction Staking/As-Built 1 LS $ $ 4 Pressure Test Water Line 1 LS $ $ 5 Density Testing 1 LS $ $ 6 Disinfection/Bac-T Sampling 1 LS $ $ 7 Erosion Control/Silt Fence 12,000 LF $ $ 8 10" C900 PVC Pipe 24 LF $ $ 9 10" Gate Valve & Box 2 EA $ $
10 10" Tapping Sleeve and Valve 2 EA $ $ 11 12" C900 PVC Pipe 7,474 LF $ $ 12 12" Gate Valve & Box 20 EA $ $ 13 12" DIP Fittings 1 LS $ $ 14 14" PE 4710 Directional Bore 2,014 LF $ $ 15 2" Air Release Valve and Vault 7 EA $ $ 16 Water Service Connection 8 EA $ $ 17 New Fire Hydrant Assembly - Complete 11 EA $ $ 18 Connect to Existing WM 3 EA $ $ 19 Temporary Jumper Connection 1 EA $ $ 20 Restoration - Bahia Sod 12,000 SY $ $ 21 NPDES Permit 1 LS $ $
Total Costs (Additive Alternate Bid 1) $
Total Cost (Base Bid + Additive Alternate Bid)
Company Name:
Bidder Signature:
| IFB 26-016-HG |
| ACKNOWLEDGMENT - Addendum No. 10 |