This addendum to ITB-25-PW-002 addresses clarifications from prospective bidders for the City of Umatilla's N/S Golden Gem Utility Improvements project in Florida. The addendum confirms two critical specifications: all watermain and force main installations under roadways must utilize Ductile Iron Pipe (DIP) rather than PVC, and the existing watermain is DIP material. These clarifications are essential for bidders preparing cost estimates and construction methodologies for the infrastructure project involving new water lines, sewer lines, pavement reconstruction, and site restoration. The original bid submission deadline is February 13, 2025, at 2:00 p.m., with a mandatory pre-bid conference having been held on January 16, 2025. All prospective bidders are required to acknowledge receipt of this addendum by signature and include the acknowledgment with their bid submission.

The addendum does not introduce new pricing terms, set-asides, or funding modifications to the original solicitation. Rather, it provides technical clarifications that directly impact material specifications and construction methodology, requiring bidders to adjust their proposals accordingly. The changes ensure compliance with infrastructure standards and compatibility with existing utility systems in the Umatilla area. Bidders must incorporate these DIP requirements into their project plans and cost proposals while maintaining adherence to the City's existing contract terms, bonding requirements, wage decisions, and technical qualifications outlined in the original ITB-25-PW-002 solicitation documents.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. 1

DATE: January 24, 2025

BID NO: ITB-25-PW-002

PROJECT: City of Umatilla, N/S Golden Gem Utility Improvements

ALL PROSPECTIVE BIDDERS ARE HEREBY NOTIFIED OF THE

CHANGES OR ALTERATIONS IN THE ABOVE-REFERENCED

PROJECT

Questions from Bidders:

1. Will Ductile Iron Pipe be required under the road crossing?

Response: Yes, all watermain and force main will be DIP under roadways.

2. Is the existing water main's to be wet tapped PVC or DIP or other?

Response: Existing watermain is DIP. Added note to plan.

ALL BIDDERS ARE REQUESTED TO ACKNOWLEDGE RECEIPT OF THIS

ADDENDUM BY SIGNING BELOW AND SUBMITTING THE BID.

ACKNOWLEDGE RECEIPT- ADDENDUM NO. 1

NAME OF BIDDER ________________________________________________

SIGNATURE _____________________________________________________

TITLE ____________________________ DATE _________________________

File details come from the government source that posted it. Updated .