NOAA – La Jolla Laboratory Replacement October December 18, 2009 Final Construction Documents
TABLE OF CONTENTS 00010 - 1
DIVISION 0 – BIDDING AND CONTRACTING REQUIREMENTS
CONSTRUCTION AGREEMENT (NOT INCLUDED) (Amendment 2) GEOTECHNICAL REPORT (NOT INCLUDED) (Amendment 2)
CERTFICATES OF COMPLIANCE
SECTION 00010 - TABLE OF CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
01060 REGULATORY/PERMITTING REQUIREMENTS
01065 SAFETY
01290 PAYMENT PROCEDURES
01310 PROJECT MANAGEMENT AND COORDINATION
01320 CONSTRUCTION PROGRESS DOCUMENTATION
01322 PHOTOGRAPHIC DOCUMENTATION
01330 SUBMITTAL PROCEDURES (Reissued Amendment 2)
01352 LEED REQUIREMENTS
01353 INDOOR AIR QUALITY MANAGEMENT DURING CONSTRUCTION
01354 INDOOR AIR QUALITY TESTING BEFORE OCCUPANCY
01400 QUALITY CONTROL (Reissued Amendment 2)
01420 REFERENCES
01500 TEMPORARY FACILITIES AND CONTROLS (Reissued Amendment 2)
01524 CONSTRUCTION WASTE MANAGEMENT
01540 SECURITY
01600 PRODUCT REQUIREMENTS
01635 SUBSTITUTION PROCEDURES
01701 EXECUTION REQUIREMENTS
01702 CLOSEOUT PROCEDURES AND FINAL ACCEPTANCE
01731 CUTTING AND PATCHING
01781 PROJECT RECORD DOCUMENTS
01782 OPERATION AND MAINTENANCE DATA
01800 COMMISSIONING
01810 FUNCTIONAL PERFORMANCE TESTING (FPT) PROCEDURES
01820 DEMONSTRATION AND TRAINING
DIVISION 2 - SITE CONSTRUCTION
02230 SITE CLEARING
02231 TREE PROTECTION AND TRIMMING
02260 EXCAVATION SUPPORT AND PROTECTION
02300 EARTHWORK (Reissued Amendment 2)
02510 WATER DISTRIBUTION
02530 SANITARY SEWERAGE
02630 STORM DRAINAGE
02741 ASPHALT PAVING (Reissued Amendment 2) 02751 CEMENT CONCRETE PAVEMENT (Revised 12/18/2009)
02752 CONCRETE PAVERS FOR GREEN ROOF
NOAA – La Jolla Laboratory Replacement October December 18, 2009
TABLE OF CONTENTS 00010 - 2
02770 TACTILE WARNING SURFACES (PRECAST CONCRETE)
02810 IRRIGATION SYSTEMS
02811 IRRIGATION SYSTEM FOR GREEN ROOF
02915 SOILS FOR GREEN ROOF (Reissued Amendment 2)
02930 PLANTS FOR GREEN ROOF
02931 LANDSCAPING
DIVISION 3 - CONCRETE
03300 CAST-IN-PLACE CONCRETE (Reissued Amendment 2) 03331 CAST-IN-PLACE ARCHITECTURAL CONCRETE (Deleted Amendment 2)
03450 ARCHITECTURAL PRECAST CONCRETE STAIRS
03532 ARCHITECTURAL CONCRETE TOPPING
DIVISION 4 - MASONRY
04810 UNIT MASONRY ASSEMBLIES (Revised 12/18/2009)
DIVISION 5 - METALS
05120 STRUCTURAL STEEL
05210 STEEL JOISTS (Revised 12/18/2009)
05310 STEEL DECK
05400 COLD-FORMED METAL FRAMING (Revised 12/18/2009) 05500 METAL FABRICATIONS (Revised 12/18/2009)
05511 METAL STAIRS
05521 PIPE AND TUBE RAILINGS
05721 ORNAMENTAL RAILINGS
05730 MISCELLANEOUS INTERIOR FORMED METAL
05811 ARCHITECTURAL JOINT SYSTEMS (Reissued Amendment 2)
DIVISION 6 - WOOD AND PLASTICS
06100 ROUGH CARPENTRY
06160 SHEATHING (Reissued Amendment 2) 06402 INTERIOR ARCHITECTURAL WOODWORK (Reissued Amendment 2)
06615 ENGINEERED STONE COUNTERTOPS
06640 PLASTIC PANELING
DIVISION 7 - THERMAL AND MOISTURE PROTECTION
07131 PLAZA DECK/FOUNDATION WATERPROOFING (Reissued Amendment 2) 07162 CRYSTALLINE WATERPROOFING (Issued Amendment 2) 07182 PEDESTRIAN DECK COATINGS (Reissued Amendment 2)
07210 BUILDING INSULATION
07552 STYRENE-BUTADIENE-STYRENE (SBS) MODIFIED BITUMINOUS MEMBRANE ROOFING
(Reissued amendment 2)
NOAA – La Jolla Laboratory Replacement October December 18, 2009
TABLE OF CONTENTS 00010 - 3
07620 SHEET METAL FLASHING AND TRIM
07710 MANUFACTURED ROOF SPECIALTIES
07716 EXPANSION JOINT ASSEMBLIES
07720 ROOF ACCESSORIES (Reissued Amendment 2)
07811 SPRAYED FIRE-RESISTIVE MATERIALS
07841 THROUGH-PENETRATION FIRESTOP SYSTEMS
07842 FIRE-RESISTIVE JOINT SYSTEMS
07920 JOINT SEALANTS
DIVISION 8 - DOORS AND WINDOWS
08110 STEEL DOORS AND FRAMES (Reissued Amendment 2)
08119 FIRE RATED DOORS AND FRAMES
08130 STAINLESS-STEEL DOORS AND FRAMES (Reissued Amendment 2)
08211 FLUSH WOOD DOORS
08310 HORIZONTAL ACCESS DOOR
08340 OVERHEAD COILING GRILLES
08362 OVERHEAD COILING DOORS
08411 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08450 ALL-GLASS ENTRANCES AND STOREFRONTS
08520 ALUMINUM WINDOWS
08710 DOOR HARDWARE (Reissued Amendment 2)
08800 GLAZING
08816 DECORATIVE GLASS (Reissued Amendment 2)
08830 MIRRORS
08911 GLAZED ALUINUM CURTAINWALLS
DIVISION 9 - FINISHES
09111 NON-LOAD-BEARING STEEL FRAMING
09220 PORTLAND CEMENT PLASTER (Reissued Amendment 2) 09250 GYPSUM BOARD (Reissued Amendment 2) (Revised 12/18/2009)
09265 GYPSUM BOARD SHAFT-WALL ASSEMBLIES
09310 CERAMIC TILE (Reissued Amendment 2) (Revised 12/18/2009)
09511 ACOUSTICAL PANEL CEILINGS
09547 LINEAR WOOD CEILINGS (Issued Amendment 2)
09548 STAINLESS STEEL WALL PANELS
09638 STONE FLOORING
09651 RESILIENT FLOOR TILE
09652 RESILIENT SHEET FLOORING (Reissued Amendment 2)
09653 RESILIENT WALL BASE AND ACCESSORIES
09671 RESINOUS FLOORING AND WALL FINISH
09680 CARPET
09681 CARPET TILE
09720 WALL COVERINGS
09751 INTERIOR STONE FACING (Deleted Amendment 2) 09762 CONCRETE FLOOR SEALER/HARDENER (Issued Amendment 2) 09841 ACOUSTICAL WALL PANELS (Reissued Amendment 2)
09911 EXTERIOR PAINTING
09912 INTERIOR PAINTING
NOAA – La Jolla Laboratory Replacement October December 18, 2009
TABLE OF CONTENTS 00010 - 4
09931 WOOD STAINS AND TRANSPARENT FINISHES
09960 HIGH PERFORMANCE COATINGS
DIVISION 10 - SPECIALTIES
10155 TOILET COMPARTMENTS
10265 IMPACT-RESISTANT WALL PROTECTION
10431 SIGNAGE (Reissued Amendment 2)
10505 SOLID PLASTIC LOCKERS
10522 FIRE EXTINGUISHER CABINETS
10523 FIRE EXTINGUISHERS
10531 TERRA COTTA CLAY TILE BAGUETTE SYSTEM
10801 TOILET AND BATH ACCESSORIES
DIVISION 11 – EQUIPMENT
11132 PROJECTION SCREENS
11150 PARKING CONTROL EQUIPMENT (Deleted Amendment 2)
11160 LOADING DOCK EQUIPMENT
11610 FUME HOODS AND EXHAUST DEVICES (Reissued Amendment 2) 11640 LABORATORY EQUIPMENT (Reissued Amendment 2)
DIVISION 12 – FURNISHINGS
12051 FURNITURE AND FURNISHINGS – GENERAL REQUIREMENTS
12494 ROLLER SHADES
12630 LABORATORY CASEWORK AND OTHER FURNISHINGS (Reissued Amendment 2)
12692 ENTRANCE GRIDS
DIVISION 13 - SPECIAL CONSTRUCTION
13034 CLEANROOM WALL SYSTEMS
13035 CONTROLLED ENVIRONMENT ROOMS (Reissued Amendment 2)
13037 CLEANROOM CEILINGS SYSTEMS
13090 RADIATION PROTECTION
13131 ACRYLIC AQUARIUM WINDOWS
13700 BASIC ELECTRONIC SECURITY REQUIREMENTS
13710 CARD ACCESS CONTROL SYSTEM
13712 CLOSED CIRCUIT VIDEO EQUIPMENT (Reissued Amendment 2)
13718 SECURITY EQUIPMENT CABINETS
13726 SECURITY DEVICES
13852 DIGITAL, ADDRESSABLE FIRE ALARM SYSTEM
13930 WET-PIPE FIRE SUPPRESSION SPRINKLERS
13935 DRY-PIPE FIRE SUPPRESSION SPRINKLERS
13967 CLEAN-AGENT EXTINGUISHING SYSTEMS
13974 FIRE SUPPRESSION STANDPIPES
NOAA – La Jolla Laboratory Replacement October December 18, 2009
TABLE OF CONTENTS 00010 - 5
DIVISION 14 - CONVEYING SYSTEMS
14210 ELECTRIC TRACTION PASSENGER ELEVATORS
14213 ELECTRIC TRACTION SERVICE ELEVATORS
14621 HOIST AND RAIL SYSTEM (Reissued Amendment 2)
DIVISION 15 - MECHANICAL/PLUMBING SECTIONS
15051 COMMON WORK RESULTS FOR FIRE SUPPRESSION
15052 COMMON WORK RESULTS FOR PLUMBING
15053 COMMON WORK RESULTS FOR HVAC
15057 COMMON MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT
15058 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT
15061 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
15062 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT
15072 VIBRATION AND SEISMIC CONTROLS FOR FIRE-SUPPRESSION PIPING AND
EQUIPMENT
15073 VIBRATION AND SEISMIC CONTROLS FOR PLUMBING PIPING AND
EQUIPMENT
15074 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT
15076 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
15077 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
15082 PLUMBING INSULATION
15083 HVAC AND PROCESS INSULATION
15091 SLEEVES AND SLEEVE SEALS FOR FIRE SUPPRESSION PIPING
15092 SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING
15093 SLEEVES AND SLEEVE SEALS FOR HVAC PIPING
15096 ESCUTCHEONS FOR FIRE SUPPRESSION PIPING
15097 ESCUTCHEONS FOR PLUMBING PIPING
15098 ESCUTCHEONS FOR HVAC PIPING
15111 GENERAL-DUTY VALVES FOR PLUMBING PIPING
15112 GENERAL-DUTY VALVES FOR HVAC PIPING
15123 EXPANSION FITTINGS AND LOOPS FOR PLUMBING PIPING
15124 EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING
15126 METERS AND GAGES FOR PLUMBING PIPING
15127 METERS AND GAGES FOR HVAC PIPING
15140 DOMESTIC WATER PIPING
15145 DOMESTIC WATER PIPING SPECIALTIES
15150 SANITARY WASTE AND VENT PIPING
15155 SANITARY WASTE PIPING SPECIALTIES
15160 STORM DRAINAGE PIPING
15165 STORM DRAINAGE PIPING SPECIALTIES
15181 HYDRONIC PIPING
15185 HYDRONIC PUMPS
15189 HVAC WATER TREATMENT
15195 FACILITY NATURAL-GAS PIPING
15214 COMPRESSED-AIR PIPING FOR LABORATORY FACILITIES
15223 CHEMICAL WASTE SYSTEMS FOR LABORATORY
15253 COMPRESSED-AIR EQUIPMENT FOR LABORATORY FACILITIES
15410 PLUMBING FIXTURES
NOAA – La Jolla Laboratory Replacement October December 18, 2009
TABLE OF CONTENTS 00010 - 6
15413 TECHNOLOGY TANK LIFE SUPPORT SYSTEMS
15415 DRINKING FOUNTAINS AND WATER COOLERS
15441 DOMESTIC WATER PUMPS
15445 SEWAGE PUMPS
15446 SUMP PUMPS
15450 POTABLE-WATER STORAGE TANKS
15469 WATER SOFTENERS
15471 AQUARIA LIFE SUPPORT SYSTEM
15487 DOMESTIC WATER HEAT EXCHANGERS
15513 CONDENSING BOILERS
15550 BREECHINGS, CHIMNEYS, AND STACKS
15555 DRAFT CONTROL DEVICES
15625 MAGNETIC BEARING CENTRIFUGAL WATER CHILLERS – 42 DEGREE CHILLED
WATER
15626 ROTARY SCREW WATER CHILLERS – 29 DEGREE CHILLED WATER
15635 REFRIGERANT DETECTION AND ALARM
15640 COOLING TOWERS
15710 HYDRONIC HEAT EXCHANGERS
15725 MODULAR INDOOR CENTRAL-STATION AIR-HANDLING UNITS
15734 COMPUTER-ROOM AIR-CONDITIONERS
15736 FILTER FAN UNITS
15762 UNIT HEATERS
15763 FAN-COIL UNITS
15815 METAL DUCTS
15820 DUCT ACCESSORIES
15836 AXIAL FANS
15838 POWER VENTILATORS, DUST COLLECTION, PAINT SPRAY BOOTH
15840 AIR TERMINAL UNITS
15855 DIFFUSERS, REGISTERS, AND GRILLES
15900 HVAC INSTRUMENTATION AND CONTROLS
15940 SEQUENCE OF OPERATION
15950 TESTING, ADJUSTING, AND BALANCING
15995 MECHANICAL SYSTEM COMMISSIONING
15996 BUILDING AUTOMATION SYSTEM COMMISSIONING
DIVISION 16 - ELECTRICAL SECTIONS
16051 COMMON WORK RESULTS FOR ELECTRICAL
16052 COMMON WORK RESULTS FOR COMMUNICATIONS
16053 COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY
16055 OVERCURRENT PROTECTIVE DEVICE COORDINATION
16060 GROUNDING AND BONDING
16073 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
16074 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS
16075 ELECTRICAL IDENTIFICATION
16120 CONDUCTORS AND CABLES
16123 CONTROL-VOLTAGE ELECTRICAL POWER CABLES
16130 RACEWAYS AND BOXES
16139 CABLE TRAYS
16140 WIRING DEVICES
16145 LIGHTING CONTROL DEVICES
NOAA – La Jolla Laboratory Replacement October December 18, 2009
TABLE OF CONTENTS 00010 - 7
16211 ELECTRICITY METERING
16215 ELECTRICAL POWER MONITORING AND CONTROL
16231 PACKAGED ENGINE GENERATORS
16264 STATIC UNINTERRUPTIBLE POWER SUPPLY
16269 VARIABLE FREQUENCY CONTROLLERS
16289 TRANSIENT VOLTAGE SUPPRESSION
16410 ENCLOSED SWITCHES AND CIRCUIT BREAKERS
16415 TRANSFER SWITCHES
16420 ENCLOSED CONTROLLERS
16441 SWITCHBOARDS
16442 PANELBOARDS
16461 LOW-VOLTAGE TRANSFORMERS
16491 FUSES
16511 INTERIOR LIGHTING
16521 EXTERIOR LIGHTING
16571 CENTRAL DIMMING CONTROLS
16714 COMMUNICATIONS EQUIPMENT ROOM FITTINGS
16716 COMMUNICATIONS BACKBONE CABLING
16717 COMMUNICATIONS HORIZONTAL CABLING
16718 CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY
16800 SOLAR PHOTOVOLTAIC SYSTEM (Reissued Amendment 2)
16995 ELECTRICAL SYSTEM COMMISSIONING
DIVISION 17 - COMMUNICATIONS SECTIONS
17100 VOICE-OVER-IP (VOIP) SYSTEM
NOAA - La Jolla Laboratory Replacement Project October 9 December 18, 2009
CEMENT CONCRETE PAVEMENT 02751 - 1
SECTION 02751 - CEMENT CONCRETE PAVEMENT
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes exterior cement concrete pavement for the following:
1. Driveways and roadways.
2. Parking lots.
3. Curbs and gutters.
4. Walkways.
B. Related Sections include the following:
1. Division 2 Section "Earthwork" for subgrade preparation, grading, and subbase course.
2. Division 3 Section "Cast-in-Place Concrete” for general building applications of concrete.
1.3 DEFINITIONS
A. Cementitious Materials: Portland cement alone or in combination with one or more of blended hydraulic cement, fly ash and other pozzolans, and ground granulated blast-furnace slag.
1.4 SUBMITTALS
A. Product Data: For each type of manufactured material and product indicated.
B. Design Mixtures: For each concrete pavement mixture. Include alternate mixture designs when characteristics of materials, Project conditions, weather, test results, or other circumstances warrant adjustments.
C. Samples: 10-lb sample of exposed aggregate.
D. Qualification Data: For testing agency.
CEMENT CONCRETE PAVEMENT 02751 - 2
E. Material Test Reports: From a qualified testing agency indicating and interpreting test results for compliance of the following with requirements indicated, based on comprehensive testing of current materials:
1. Aggregates. Include service record data indicating absence of deleterious expansion of concrete due to alkali-aggregate reactivity.
F. Material Certificates: Signed by manufacturers certifying that each of the following materials complies with requirements:
1. Cementitious materials.
2. Steel reinforcement and reinforcement accessories.
3. Fiber reinforcement.
4. Admixtures.
5. Curing compounds.
6. Applied finish materials.
7. Bonding agent or epoxy adhesive.
8. Joint fillers.
G. Field quality-control test reports.
1.5 QUALITY ASSURANCE
A. Manufacturer Qualifications: Manufacturer of ready-mixed concrete products who complies with ASTM C 94/C 94M requirements for production facilities and equipment.
1. Manufacturer certified according to NRMCA's "Certification of Ready Mixed Concrete Production Facilities."
B. Testing Agency Qualifications: An independent agency qualified according to ASTM C 1077 and ASTM E 329 for testing indicated, as documented according to ASTM E 548.
1. Personnel conducting field tests shall be qualified as ACI Concrete Field Testing Technician, Grade 1, according to ACI CP-01 or an equivalent certification program.
C. ACI Publications: Comply with ACI 301, "Specification for Structural Concrete," unless modified by requirements in the Contract Documents.
D. Concrete Testing Service: Engage a qualified independent testing agency to perform material evaluation tests and to design concrete mixtures.
E. Mockups: Cast mockups of full-size sections of concrete pavement to demonstrate typical joints, surface finish, texture, color, and standard of workmanship.
1. Build mockups in the location and of the size indicated or, if not indicated, as directed by Architect.
2. Notify Architect seven days in advance of dates and times when mockups will be constructed.
3. Obtain Architect's approval of mockups before starting construction.
CEMENT CONCRETE PAVEMENT 02751 - 3
4. Maintain approved mockups during construction in an undisturbed condition as a standard for judging the completed pavement.
5. Demolish and remove approved mockups from the site when directed by Architect.
6. Approved mockups may become part of the completed Work if undisturbed at time of
Substantial Completion.
F. Preinstallation Conference: Conduct conference at Project site to comply with requirements in Division 1 Section "Project Management and Coordination."
1. Before submitting design mixtures, review concrete pavement mixture design and examine procedures for ensuring quality of concrete materials and concrete pavement construction practices. Require representatives, including the following, of each entity directly concerned with concrete pavement, to attend conference:
a. Contractor's superintendent.
b. Independent testing agency responsible for concrete design mixtures.
c. Ready-mix concrete producer.
d. Concrete pavement subcontractor.
1.6 PROJECT CONDITIONS
A. Traffic Control: Maintain access for vehicular and pedestrian traffic as required for other construction activities.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. In other Part 2 articles where titles below introduce lists, the following requirements apply to product selection:
1. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, products specified.
2. Products: Subject to compliance with requirements, provide one of the products specified.
3. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, manufacturers specified.
4. Manufacturers: Subject to compliance with requirements, provide products by one of the manufacturers specified.
2.2 FORMS
A. Form Materials: Plywood, metal, metal-framed plywood, or other approved panel-type materials to provide full-depth, continuous, straight, smooth exposed surfaces.
1. Use flexible or curved forms for curves with a radius 100 feet or less.
CEMENT CONCRETE PAVEMENT 02751 - 4
B. Form-Release Agent: Commercially formulated form-release agent that will not bond with, stain, or adversely affect concrete surfaces and will not impair subsequent treatments of concrete surfaces.
2.3 STEEL REINFORCEMENT
A. Plain-Steel Welded Wire Reinforcement: ASTM A 185, fabricated from as-drawn steel wire into flat sheets.
B. Deformed-Steel Welded Wire Reinforcement: ASTM A 497, flat sheet.
C. Epoxy-Coated Welded Wire Fabric: ASTM A 884/A 884M, Class A, plain steel.
D. Reinforcing Bars: ASTM A 615/A 615M, Grade 60; deformed.
E. Galvanized Reinforcing Bars: ASTM A 767/A 767M, Class II zinc coated, hot-dip galvanized after fabrication and bending; with ASTM A 615/A 615M, Grade 60 deformed bars.
F. Epoxy-Coated Reinforcing Bars: ASTM A 775/A 775M or ASTM A 934/A 934M; with ASTM A 615/A 615M, Grade 60 deformed bars.
G. Steel Bar Mats: ASTM A 184/A 184M; with ASTM A 615/A 615M, Grade 60, deformed bars;
assembled with clips.
H. Plain Steel Wire: ASTM A 82.
I. Deformed-Steel Wire: ASTM A 496.
J. Epoxy-Coated-Steel Wire: ASTM A 884/A 884M, Class A coated, plain.
K. Joint Dowel Bars: Plain steel bars, ASTM A 615/A 615M, Grade 60. Cut bars true to length with Ends Square and free of burrs.
L. Epoxy-Coated Joint Dowel Bars: ASTM A 775/A 775M; with ASTM A 615/A 615M, Grade 60, plain steel bars.
M. Tie Bars: ASTM A 615/A 615M, Grade 60, deformed.
N. Hook Bolts: ASTM A 307, Grade A, internally and externally threaded. Design hook-bolt joint assembly to hold coupling against pavement form and in position during concreting operations, and to permit removal without damage to concrete or hook bolt.
O. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars, welded wire reinforcement, and dowels in place. Manufacture bar supports according to CRSI's "Manual of Standard Practice" from steel wire, plastic, or precast concrete of greater compressive strength than concrete, and as follows:
1. Equip wire bar supports with sand plates or horizontal runners where base material will not support chair legs.
CEMENT CONCRETE PAVEMENT 02751 - 5
2. For epoxy-coated reinforcement, use epoxy-coated or other dielectric-polymer-coated wire bar supports.
P. Epoxy Repair Coating: Liquid two-part epoxy repair coating, compatible with epoxy coating on reinforcement.
Q. Zinc Repair Material: ASTM A 780.
2.4 CONCRETE MATERIALS
A. Cementitious Material: Use one of the following cementitious materials, of the same type, brand, and source throughout the Project:
1. Portland Cement: ASTM C 150, Type II, gray. Supplement with the following:
a. Fly Ash: ASTM C 618, Class C.
b. Ground Granulated Blast-Furnace Slag: ASTM C 989, Grade 100 or 120.
2. Blended Hydraulic Cement: ASTM C 595, Type IP, portland-pozzolan cement.
B. Normal-Weight Aggregates: ASTM C 33, Class 4S coarse aggregate, uniformly graded.
Provide aggregates from a single source with documented service record data of at least 10 years' satisfactory service in similar pavement applications and service conditions using similar aggregates and cementitious materials.
1. Maximum Coarse-Aggregate Size: 18 mm (3/4 inch) nominal.
2. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement.
C. Exposed Aggregate: Selected, hard, and durable; washed; free of materials with deleterious reactivity to cement or that cause staining; from a single source, with gap-graded coarse aggregate as follows:
1. Aggregate Sizes: 8 mm to 13 mm (3/8 to 5/8 inch) nominal.
D. Water: ASTM C 94/C 94M.
E. Air-Entraining Admixture: ASTM C 260.
F. Chemical Admixtures: Provide admixtures certified by manufacturer to be compatible with other admixtures and to contain not more than 0.1 percent water-soluble chloride ions by mass of cementitious material.
1. Water-Reducing Admixture: ASTM C 494/C 494M, Type A.
2. Retarding Admixture: ASTM C 494/C 494M, Type B.
3. Water Reducing and Retarding Admixture: ASTM C 494/C 494M, Type D.
4. High-Range, Water-Reducing Admixture: ASTM C 494/C 494M, Type F.
5. High-Range, Water-Reducing and Retarding Admixture: ASTM C 494/C 494M, Type G.
6. Plasticizing and Retarding Admixture: ASTM C 1017/C 1017M, Type II.
CEMENT CONCRETE PAVEMENT 02751 - 6
2.5 FIBER REINFORCEMENT
A. Synthetic Fiber: Monofilament or fibrillated polypropylene fibers engineered and designed for use in concrete pavement, complying with ASTM C 1116, Type III, 1/2 to 1-1/2 inches long.
1. Available Products:
a. Monofilament Fibers:
1) Axim Concrete Technologies; Fibrasol IIP.
2) Euclid Chemical Company The; Fiberstrand 100.
3) FORTA Corporation; Forta Mono.
4) Grace, W. R. & Co.--Conn.; Grace MicroFiber.
5) Metalcrete Industries; Polystrand 1000.
6) SI Concrete Systems; Fibermix Stealth.
7) Or Equal
b. Fibrillated Fibers:
1) Axim Concrete Technologies; Fibrasol F.
2) FORTA Corporation; Forta.
3) Euclid Chemical Company The; Fiberstrand F.
4) Grace, W. R. & Co.--Conn.; Grace Fibers.
5) SI Concrete Systems; Fibermesh.
6) Or Equal.
2.6 CURING MATERIALS
A. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. dry.
B. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.
C. Water: Potable.
D. Evaporation Retarder: Waterborne, monomolecular film forming; manufactured for application to fresh concrete.
1. Available Products:
a. Axim Concrete Technologies; Cimfilm.
b. Burke by Edeco; BurkeFilm.
c. ChemMasters; Spray-Film.
d. Conspec Marketing & Manufacturing Co., Inc.; Aquafilm.
e. Dayton Superior Corporation; Sure Film.
f. Euclid Chemical Company The; Eucobar.
g. Kaufman Products, Inc.; Vapor Aid.
h. Lambert Corporation; Lambco Skin.
CEMENT CONCRETE PAVEMENT 02751 - 7
i. L&M Construction Chemicals, Inc.; E-Con.
j. MBT Protection and Repair, ChemRex Inc.; Confilm.
k. Meadows, W. R., Inc.; Sealtight Evapre.
l. Metalcrete Industries; Waterhold.
m. Nox-Crete Products Group, Kinsman Corporation; Monofilm.
n. Sika Corporation, Inc.; SikaFilm.
o. Symons Corporation; Finishing Aid.
p. Vexcon Chemicals, Inc.; Certi-Vex EnvioAssist.
q. Or equal.
E. Clear Waterborne Membrane-Forming Curing Compound: ASTM C 309, Type 1, Class B.
1. Available Products:
a. Anti-Hydro International, Inc.; AH Curing Compound #2 DR WB.
b. Burke by Edoko; Aqua Resin Cure.
c. ChemMasters; Safe-Cure Clear.
d. Conspec Marketing & Manufacturing Co., Inc.; W.B. Resin Cure.
e. Dayton Superior Corporation; Day Chem Rez Cure J-11-W.
f. Euclid Chemical Company The; Kurez DR VOX.
g. Kaufman Products, Inc.; Thinfilm 420.
h. Lambert Corporation; Aqua Kure-Clear.
i. L&M Construction Chemicals, Inc.; L&M Cure R.
j. Meadows, W. R., Inc.; 1100 Clear.
k. Nox-Crete Products Group, Kinsman Corporation; Resin Cure E.
l. Symons Corporation; Resi-Chem Clear.
m. Tamms Industries Inc.; Horncure WB 30.
n. Unitex; Hydro Cure 309.
o. Vexcon Chemicals, Inc.; Certi-Vex Enviocure 100.
p. Or Equal.
F. White Waterborne Membrane-Forming Curing Compound: ASTM C 309, Type 2, Class B.
1. Available Products:
a. Anti-Hydro International, Inc.; AH Curing Compound #2 WP WB.
b. Burke by Edoco; Resin Emulsion White.
c. ChemMasters; Safe-Cure 2000.
d. Conspec Marketing & Manufacturing Co., Inc.; W.B. Resin Cure.
e. Dayton Superior Corporation; Day-Chem White Pigmented Cure J-10-W.
f. Euclid Chemical Company The; Kurez VOX White Pigmented.
g. Kaufman Products, Inc.; Thinfilm 450.
h. Lambert Corporation; Aqua Kure-White.
i. L&M Construction Chemicals, Inc.; L&M Cure R-2.
j. Meadows, W. R., Inc.; 1200-White.
k. Symons Corporation; Resi-Chem White.
l. Tamms Industries, Inc.; Horncure 200-W.
m. Unitex; Hydro White.
n. Vexcon Chemicals, Inc.; Certi-Vex Enviocure White 100.
o. Or Equal.
CEMENT CONCRETE PAVEMENT 02751 - 8
2.7 RELATED MATERIALS
A. Expansion- and Isolation-Joint-Filler Strips: ASTM D 1751, asphalt-saturated cellulosic fiber.
B. Color Pigment: ASTM C 979, synthetic mineral-oxide pigments or colored water-reducing admixtures; color stable, free of carbon black, nonfading, and resistant to lime and other alkalis.
1. Available Manufacturers:
a. Bayer Corporation.
b. ChemMasters.
c. Conspec Marketing & Manufacturing Co., Inc.
d. Davis Colors.
e. Elementis Pigments, Inc.
f. Hoover Color Corporation.
g. Lambert Corporation.
h. Scofield, L. M.Company.
i. Solomon Colors.
j. Or Equal.
2. Color: As selected by Architect from manufacturer's full range.
C. Slip-Resistive Aggregate Finish: Factory-graded, packaged, rustproof, nonglazing, abrasive aggregate of fused aluminum-oxide granules or crushed emery with emery aggregate containing not less than 50 percent aluminum oxide and not less than 20 percent ferric oxide; unaffected by freezing, moisture, and cleaning materials.
D. Bonding Agent: ASTM C 1059, Type II, non-redispersible, acrylic emulsion or styrene butadiene.
E. Epoxy Bonding Adhesive: ASTM C 881, two-component epoxy resin, capable of humid curing and bonding to damp surfaces, of class suitable for application temperature and of grade to requirements, and as follows:
1. Types IV and V, load bearing, for bonding hardened or freshly mixed concrete to hardened concrete.
F. Chemical Surface Retarder: Water-soluble, liquid-set retarder with color dye, for horizontal concrete surface application, capable of temporarily delaying final hardening of concrete to a depth of 3 mm to 6 mm (1/8 to 1/4 inch).
1. Available Products:
a. Burke by Edeco; True Etch Surface Retarder.
b. ChemMasters; Exposee.
c. Conspec Marketing & Manufacturing Co., Inc.; Delay S.
d. Euclid Chemical Company The; Surface Retarder S.
e. Kaufman Products, Inc.; Expose.
f. Metalcrete Industries; Surftard.
g. Nox-Crete Products Group, Kinsman Corporation; Crete-Nox TA.
h. Scofield, L. M. Company; Lithotex.
CEMENT CONCRETE PAVEMENT 02751 - 9
i. Sika Corporation, Inc.; Rugasol-S.
j. Vexcon Chemicals, Inc.; Certi-Vex Envioset.
k. Or Equal.
G. Pigmented Mineral Dry-Shake Hardener: Factory-packaged dry combination of Portland cement, graded quartz aggregate, color pigments, and plasticizing admixture. Use color pigments that are finely ground, nonfading mineral oxides interground with cement.
1. Available Products:
a. Conspec Marketing & Manufacturing Co., Inc.; Conshake 600 Colortone.
b. Dayton Superior Corporation; Quartz Tuff.
c. Euclid Chemical Company The; Surflex.
d. Lambert Corporation; Colorhard.
e. L&M Construction Chemicals, Inc.; Quartz Plate FF.
f. MBT Protection and Repair, ChemRex Inc.; Mastercron.
g. Metalcrete Industries; Floor Quartz.
h. Scofield, L. M. Company; Lithochrome Color Hardener.
i. Symons Corporation; Hard Top.
j. Or Equal
2. Color: As selected by Architect from manufacturer's full range.
H. Rock Salt: Sodium chloride crystals, kiln dried, coarse gradation with 100 percent passing 8 mm (3/8-inch) sieve and 85 percent retained on a 3 mm (No. 8) sieve.
2.8 WHEEL STOPS
A. Wheel Stops: Precast, air-entrained concrete.
1. Length: 1829 mm [6 FT].
2. Dowels: Galvanized steel, 19 mm [3/4 inch] in diameter, 254 mm [10-inch] minimum length.
3. Adhesive: As recommended by wheel stop manufacturer for application to concrete pavement.
H.
2.82.9 CONCRETE MIXTURES
A. Prepare design mixtures, proportioned according to ACI 301, for each type and strength of normal-weight concrete determined by either laboratory trial mixes or field experience.
1. Use a qualified independent testing agency for preparing and reporting proposed concrete mixture designs for the trial batch method.
B. Proportion mixtures to provide normal-weight concrete with the following properties:
1. Compressive Strength 28 Days: 20684 kP (3000 psi).
2. Maximum Water-Cementitious Materials Ratio at Point of Placement: 0.58.
CEMENT CONCRETE PAVEMENT 02751 - 10
3. Slump Limit: 100 mm (4 inches), plus or minus 25 mm (1 inch).
C. Chemical Admixtures: Use admixtures according to manufacturer's written instructions.
1. Use water-reducing admixture in concrete, as required, for placement and workability.
2. Use water reducing and retarding admixture when required by high temperatures, low humidity, or other adverse placement conditions.
D. Color Pigment: Add color pigment to concrete mixture according to manufacturer's written instructions and to result in hardened concrete color consistent with approved mockup.
2.92.10 CONCRETE MIXING
A. Ready-Mixed Concrete: Measure, batch, and mix concrete materials and concrete according to ASTM C 94/C 94M and ASTM C 1116. Furnish batch certificates for each batch discharged and used in the Work.
1. When air temperature is between 30 deg C (85 deg F) and 32.2 deg C (90 deg F), reduce mixing and delivery time from 1-1/2 hours to 75 minutes; when air temperature is above 32.2 deg C 90 deg F reduce mixing and delivery time to 60 minutes.
B. Project-Site Mixing: Measure, batch, and mix concrete materials and concrete according to ASTM C 94/C 94M. Mix concrete materials in appropriate drum-type batch machine mixer.
1. For concrete mixes of 1 cu. yd. or smaller, continue mixing at least 1-1/2 minutes, but not more than 5 minutes after ingredients are in mixer, before any part of batch is released.
2. For concrete mixes larger than 1 cu. yd., increase mixing time by 15 seconds for each additional 1 cu. yd.
3. Provide batch ticket for each batch discharged and used in the Work, indicating Project identification name and number, date, mixture type, mixing time, quantity, and amount of water added.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine exposed subgrades and subbase surfaces for compliance with requirements for dimensional, grading, and elevation tolerances.
B. Proof-roll prepared subbase surface below concrete pavements with heavy pneumatic-tired equipment to identify soft pockets and areas of excess yielding.
1. Completely proof-roll subbase in one direction and repeat in perpendicular direction.
Limit vehicle speed to (3 mph) 5 km/h.
2. Proof-roll with a loaded 10-wheel tandem-axle dump truck weighing not less than 14 metric tons (15 tons).
CEMENT CONCRETE PAVEMENT 02751 - 11
3. Subbase with soft spots and areas of pumping or rutting exceeding depth of 12 mm (1/2 inch) require correction according to requirements in Division 2 Section "Earthwork."
C. Proceed with concrete pavement operations only after nonconforming conditions have been corrected and subgrade is ready to receive pavement.
3.2 PREPARATION
A. Remove loose material from compacted subbase surface immediately before placing concrete.
3.3 EDGE FORMS AND SCREED CONSTRUCTION
A. Set, brace, and secure edge forms, bulkheads, and intermediate screed guides for pavement to required lines, grades, and elevations. Install forms to allow continuous progress of work and so forms can remain in place at least 24 hours after concrete placement.
B. Clean forms after each use and coat with form-release agent to ensure separation from concrete without damage.
3.4 STEEL REINFORCEMENT
A. General: Comply with CRSI's "Manual of Standard Practice" for fabricating, placing, and supporting reinforcement.
B. Clean reinforcement of loose rust and mill scale, earth, ice, or other bond-reducing materials.
C. Arrange, space, and securely tie bars and bar supports to hold reinforcement in position during concrete placement. Maintain minimum cover to reinforcement.
D. Install welded wire reinforcement in lengths as long as practicable. Lap adjoining pieces at least one full mesh, and lace splices with wire. Offset laps of adjoining widths to prevent continuous laps in either direction.
E. Zinc-Coated Reinforcement: Use galvanized steel wire ties to fasten zinc-coated reinforcement. Repair cut and damaged zinc coatings with zinc repair material.
F. Epoxy-Coated Reinforcement: Use epoxy-coated steel wire ties to fasten epoxy-coated reinforcement. Repair cut and damaged epoxy coatings with epoxy repair coating according to ASTM D 3963/D 3963M.
G. Install fabricated bar mats in lengths as long as practicable. Handle units to keep them flat and free of distortions. Straighten bends, kinks, and other irregularities, or replace units as required before placement. Set mats for a minimum 50 mm (2-inch) overlap of adjacent mats.
CEMENT CONCRETE PAVEMENT 02751 - 12
3.5 JOINTS
A. General: Form construction, isolation, and contraction joints and tool edgings true to line with faces perpendicular to surface plane of concrete. Construct transverse joints at right angles to centerline, unless otherwise indicated.
1. When joining existing pavement, place transverse joints to align with previously placed joints, unless otherwise indicated.
B. Construction Joints: Set construction joints at side and end terminations of pavement and at locations where pavement operations are stopped for more than one-half hour unless pavement terminates at isolation joints.
1. Continue steel reinforcement across construction joints, unless otherwise indicated.
Do not continue reinforcement through sides of pavement strips, unless otherwise indicated.
2. Provide tie bars at sides of pavement strips where indicated.
3. Butt Joints: Use bonding agent at joint locations where fresh concrete is placed against hardened or partially hardened concrete surfaces.
4. Keyed Joints: Provide preformed keyway-section forms or bulkhead forms with keys, unless otherwise indicated. Embed keys at least 37.5 mm (1-1/2) inches into concrete.
5. Doweled Joints: Install dowel bars and support assemblies at joints where indicated.
Lubricate or asphalt-coat one-half of dowel length to prevent concrete bonding to one side of joint.
C. Isolation Joints: Form isolation joints of preformed joint-filler strips abutting concrete curbs, catch basins, manholes, inlets, structures, walks, other fixed objects, and where indicated.
1. Locate expansion joints at intervals of 45 meter (50 feet), unless otherwise indicated.
2. Extend joint fillers full width and depth of joint.
3. Terminate joint filler not less than 12.5 mm (1/2 inch) or more than 25 mm (1 inch) below finished surface if joint sealant is indicated.
4. Place top of joint filler flush with finished concrete surface if joint sealant is not indicated.
5. Furnish joint fillers in one-piece lengths. Where more than one length is required, lace or clip joint-filler sections together.
6. Protect top edge of joint filler during concrete placement with metal, plastic, or other temporary preformed cap. Remove protective cap after concrete has been placed on both sides of joint.
D. Contraction Joints: Form weakened-plane contraction joints, sectioning concrete into areas as indicated. Construct contraction joints for a depth equal to at least one-fourth of the concrete thickness, as follows to match jointing of existing adjacent concrete pavement:
1. Grooved Joints: Form contraction joints after initial floating by grooving and finishing each edge of joint with grooving tool to a 6 mm (1/4-inch) radius. Repeat grooving of contraction joints after applying surface finishes. Eliminate groover marks on concrete surfaces.
2. Sawed Joints: Form contraction joints with power saws equipped with shatterproof abrasive or diamond-rimmed blades. Cut 3 mm (1/8-inch)- wide joints into concrete
CEMENT CONCRETE PAVEMENT 02751 - 13
when cutting action will not tear, abrade, or otherwise damage surface and before developing random contraction cracks.
3. Doweled Contraction Joints: Install dowel bars and support assemblies at joints where indicated. Lubricate or asphalt coat one-half of dowel length to prevent concrete bonding to one side of joint.
E. Edging: Tool edges of pavement, gutters, curbs, and joints in concrete after initial floating with an edging tool to a 6 mm (1/4-inch) radius. Repeat tooling of edges after applying surface finishes. Eliminate tool marks on concrete surfaces.
3.6 CONCRETE PLACEMENT
A. Inspection: Before placing concrete, inspect and complete formwork installation, steel reinforcement, and items to be embedded or cast in. Notify other trades to permit installation of their work.
B. Remove snow, ice, or frost from subbase surface and reinforcement before placing concrete.
Do not place concrete on frozen surfaces.
C. Moisten subbase to provide a uniform dampened condition at time concrete is placed. Do not place concrete around manholes or other structures until they are at required finish elevation and alignment.
D. Comply with ACI 301 requirements for measuring, mixing, transporting, and placing concrete.
E. Do not add water to concrete during delivery or at Project site.
F. Do not add water to fresh concrete after testing.
G. Deposit and spread concrete in a continuous operation between transverse joints. Do not push or drag concrete into place or use vibrators to move concrete into place.
H. Consolidate concrete according to ACI 301 by mechanical vibrating equipment supplemented by hand spading, rodding, or tamping.
1. Consolidate concrete along face of forms and adjacent to transverse joints with an internal vibrator. Keep vibrator away from joint assemblies, reinforcement, or side forms. Use only square-faced shovels for hand spreading and consolidation.
Consolidate with care to prevent dislocating reinforcement, dowels, and joint devices.
I. Place concrete in two operations; strike off initial pour for entire width of placement and to the required depth below finish surface. Lay welded wire fabric or fabricated bar mats immediately in final position. Place top layer of concrete, strike off, and screed.
1. Remove and replace concrete that has been placed for more than 15 minutes without being covered by top layer, or use bonding agent if approved by Architect.
J. Screed pavement surfaces with a straightedge and strike off.
CEMENT CONCRETE PAVEMENT 02751 - 14
K. Commence initial floating using bull floats or darbies to impart an open textured and uniform surface plane before excess moisture or bleed water appears on the surface. Do not further disturb concrete surfaces before beginning finishing operations or spreading surface treatments.
L. Curbs and Gutters: When automatic machine placement is used for curb and gutter placement, submit revised mix design and laboratory test results that meet or exceed requirements. Produce curbs and gutters to required cross section, lines, grades, finish, and jointing as specified for formed concrete. If results are not approved, remove and replace with formed concrete.
M. Slip-Form Pavers: When automatic machine placement is used for pavement, submit revised mix design and laboratory test results that meet or exceed requirements. Produce pavement to required thickness, lines, grades, finish, and jointing as required for formed pavement.
1. Compact subbase and prepare subgrade of sufficient width to prevent displacement of paver machine during operations.
N. When adjoining pavement lanes are placed in separate pours, do not operate equipment on concrete until pavement has attained 85 percent of its 28-day compressive strength.
O. Cold-Weather Placement: Comply with ACI 306.1 and as follows. Protect concrete work from physical damage or reduced strength that could be caused by frost, freezing actions, or low temperatures.
1. When air temperature has fallen to or is expected to fall below 4.deg C (40 deg F), uniformly heat water and aggregates before mixing to obtain a concrete mixture temperature of not less than 10 deg C (50 deg F) and not more than 27 deg C (80 deg F) at point of placement.
2. Do not use frozen materials or materials containing ice or snow.
3. Do not use calcium chloride, salt, or other materials containing antifreeze agents or chemical accelerators unless otherwise specified and approved in mix designs.
P. Hot-Weather Placement: Comply with ACI 301 and as follows when hot-weather conditions exist:
1. Cool ingredients before mixing to maintain concrete temperature below 90 deg F at time of placement. Chilled mixing water or chopped ice may be used to control temperature, provided water equivalent of ice is calculated to total amount of mixing water. Using liquid nitrogen to cool concrete is Contractor's option.
2. Cover steel reinforcement with water-soaked burlap so steel temperature will not exceed ambient air temperature immediately before embedding in concrete.
3. Fog-spray forms, steel reinforcement, and subgrade just before placing concrete.
Keep subgrade moisture uniform without standing water, soft spots, or dry areas.
3.7 FLOAT FINISHING
A. General: Do not add water to concrete surfaces during finishing operations.
CEMENT CONCRETE PAVEMENT 02751 - 15
B. Float Finish: Begin the second floating operation when bleed-water sheen has disappeared and concrete surface has stiffened sufficiently to permit operations. Float surface with power-driven floats, or by hand floating if area is small or inaccessible to power units. Finish surfaces to true planes. Cut down high spots and fill low spots. Refloat surface immediately to uniform granular texture.
1. Burlap Finish: Drag a seamless strip of damp burlap across float-finished concrete, perpendicular to line of traffic, to provide a uniform, gritty texture.
2. Medium-to-Fine-Textured Broom Finish: Draw a soft bristle broom across float-finished concrete surface perpendicular to line of traffic to provide a uniform, fine-line texture.
3. Medium-to-Coarse-Textured Broom Finish: Provide a coarse finish by striating float-finished concrete surface 1.5 mm (1/16) to 3 mm (1/8) inch deep with a stiff-bristled broom, perpendicular to line of traffic.
3.8 CONCRETE PROTECTION AND CURING
A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures.
B. Comply with ACI 306.1 for cold-weather protection.
C. Evaporation Retarder: Apply evaporation retarder to concrete surfaces if hot, dry, or windy conditions cause moisture loss approaching 1.0 kg/sq meter (0.2 lb/sq. ft). x h before and during finishing operations. Apply according to manufacturers written instructions after placing, screeding, and bull floating or darbying concrete, but before float finishing.
D. Begin curing after finishing concrete but not before free water has disappeared from concrete surface.
E. Curing Methods: Cure concrete by moisture curing, moisture-retaining-cover curing, curing compound, or a combination of these as follows:
1. Moist Curing: Keep surfaces continuously moist for not less than seven days with the following materials:
a. Water.
b. Continuous water-fog spray.
c. Absorptive cover, water saturated and kept continuously wet. Cover concrete surfaces and edges with 300 mm (12-inch) lap over adjacent absorptive covers.
2. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture-retaining cover for curing concrete, placed in widest practicable width, with sides and ends lapped at least 300 mm (12 inches), and sealed by waterproof tape or adhesive.
Immediately repair any holes or tears during curing period using cover material and waterproof tape.
3. Curing Compound: Apply uniformly in continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas subjected to heavy rainfall within three hours after initial application. Maintain continuity of coating and repair damage during curing period.
CEMENT CONCRETE PAVEMENT 02751 - 16
3.9 PAVEMENT TOLERANCES
A. Comply with tolerances of ACI 117 and as follows:
1. Elevation: 6 mm (1/4 inch).
2. Thickness: Plus 8 mm (3/8 inch), minus 6 mm (1/4 inch).
3. Surface: Gap below 10-foot- 3-m- long, unleveled straightedge not to exceed 6 mm
(1/4 inch).
4. Lateral Alignment and Spacing of Tie Bars and Dowels: 25 mm (1 inch).
5. Vertical Alignment of Tie Bars and Dowels: 6 mm (1/4 inch).
6. Alignment of Tie-Bar End Relative to Line Perpendicular to Pavement Edge: 12 mm
(1/2 inch)
7. Alignment of Dowel-Bar End Relative to Line Perpendicular to Pavement Edge:
Length of dowel 6 mm (1/4 inch) per 100 mm (12 inches).
8. Joint Spacing: 75 mm (3 inches).
9. Contraction Joint Depth: Plus 6 mm (1/4 inch) no minus.
10. Joint Width: Plus 3 mm (1/8 inch), no minus.
3.10 WHEEL STOPS
A. Install wheel stops in bed of adhesive applied as recommended by manufacturer.
B. Securely attach wheel stops to paving with not less than two galvanized-steel dowels located at one-quarter to one-third points. Install dowels in drilled holes in the paving and bond dowels to wheel stop. Recess head of dowel beneath top of wheel stop.
10.
3.103.11 FIELD QUALITY CONTROL
A. Testing Agency: Engage a qualified independent testing and inspecting agency to perform field tests and inspections and prepare test reports.
B. Testing Services: Testing of composite samples of fresh concrete obtained according to ASTM C 172 shall be performed according to the following requirements:
1. Testing Frequency: Obtain at least 1 composite sample for each 90 cu meter (100 cu.
yd.) or fraction thereof of each concrete mix placed each day.
a. When frequency of testing will provide fewer than five compressive-strength tests for each concrete mixture, testing shall be conducted from at least five randomly selected batches or from each batch if fewer than five are used.
2. Slump: ASTM C 143/C 143M; one test at point of placement for each composite sample, but not less than one test for each day's pour of each concrete mix. Perform additional tests when concrete consistency appears to change.
3. Air Content: ASTM C 231, pressure method; one test for each composite sample, but not less than one test for each day's pour of each concrete mix.
CEMENT CONCRETE PAVEMENT 02751 - 17
4. Concrete Temperature: ASTM C 1064; one test hourly when air temperature is 4 deg C (40 deg F) and below and when 27 deg C (80 deg F) and above, and one test for each composite sample.
5. Compression Test Specimens: ASTM C 31/C 31M; cast and laboratory cure one set of three standard cylinder specimens for each composite sample.
6. Compressive-Strength Tests: ASTM C 39/C 39M; test 1 specimen at 7 days and 2 specimens at 28 days.
a. A compressive-strength test shall be the average compressive strength from 2 specimens obtained from same composite sample and tested at 28 days.
C. Strength of each concrete mix will be satisfactory if average of any 3 consecutive compressive-strength tests equals or exceeds specified compressive strength and no compressive-strength test value falls below specified compressive strength by more than 3500 kPa (500 psi).
D. Test results shall be reported in writing to Architect, concrete manufacturer, and Contractor within 48 hours of testing. Reports of compressive-strength tests shall contain Project identification name and number, date of concrete placement, name of concrete testing and inspecting agency, location of concrete batch in Work, design compressive strength at 28 days, concrete mixture proportions and materials, compressive breaking strength, and type of break for both 7- and 28-day tests.
E. Nondestructive Testing: Impact hammer, sonoscope, or other nondestructive device may be permitted by Architect but will not be used as sole basis for approval or rejection of concrete.
F. Additional Tests: Testing and inspecting agency shall make additional tests of concrete when test results indicate that slump, air entrainment, compressive strengths, or other requirements have not been met, as directed by Architect.
G. Remove and replace concrete pavement where test results indicate that it does not comply with specified requirements.
H. Additional testing and inspecting, at Contractor's expense, will be performed to determine compliance of replaced or additional work with specified requirements.
3.113.12 REPAIRS AND PROTECTION
A. Remove and replace concrete pavement that is broken, damaged, or defective or that does not comply with requirements in this Section.
B. Drill test cores, where directed by Architect, when necessary to determine magnitude of cracks or defective areas. Fill drilled core holes in satisfactory pavement areas with Portland cement concrete bonded to pavement with epoxy adhesive.
C. Protect concrete from damage. Exclude traffic from pavement for at least 14 days after placement. When construction traffic is permitted, maintain pavement as clean as possible by removing surface stains and spillage of materials as they occur.
CEMENT CONCRETE PAVEMENT 02751 - 18
D. Maintain concrete pavement free of stains, discoloration, dirt, and other foreign material.
Sweep concrete pavement not more than two days before date scheduled for Substantial Completion inspections.
END OF SECTION 02751
NOAA - La Jolla Laboratory Replacement October 9 December 18, 2009
UNIT MASONRY ASSEMBLIES 04810 -1
SECTION 04810 - UNIT MASONRY ASSEMBLIES
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General Conditions and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Concrete masonry units (CMU's).
B. Related Sections:
1. Division 5 Section "Metal Fabrications" for furnishing steel lintels and shelf angles for unit masonry.
2. Division 7 Section "Sheet Metal Flashing and Trim" for furnishing manufactured reglets installed in masonry joints.
1.3 SUBMITTALS
A. Product Data: For each type of product indicated.
B. LEED Submittals:
1. Product Data for LEED Credits MR 4.1 and 4.2, Recycled Content: For products having recycled content, documentation indicating percentages by weight of postconsumer and preconsumer recycled content; include statement indicating costs for each product having recycled content.
2. Product Certificates for LEED Credits MR 5.1 and Credit MR 5.2, Regional Materials:
For products and materials required to comply with requirements for regional materials indicating location and distance from Project of material manufacturer and point of extraction, harvest, or recovery for each raw material. Include statement indicating cost for each regional material and the fraction by weight that is considered regional.
3. Product…