Solicitation #AB1330-10-RP-0005 – Page 1
ATTACHMENT J.2.3
PAST PERFORMANCE QUESTIONNAIRE
SOLICITATION #AB1330-10-RP-0005
RECOVERY--CONSTRUCTION OF NOAA'S LA JOLLA LABORATORY
REPLACEMENT PROJECT
LA JOLLA, CALIFORNIA
Instructions to Offerors: Past performance of offerors will be evaluated to determine the extent to which offerors have successfully performed projects of similar scope. Offerors shall complete Section A for each project of similar scope completed or substantially completed (95-99%) over the last five years. Past performance information and questionnaires shall also be submitted for all proposed major subcontractors.
A copy of Section A for each project submission and shall be included with the proposal. The questionnaire shall be submitted to references to return to the Contract Specialist.
SECTION A - PROJECT REFERENCE
TO BE COMPLETED BY OFFEROR FOR EACH SIMILAR PROJECT/CONTRACT
COMPLETED OR SUBSTANTIALLY COMPLETED
Providing Reference for: Offeror/Firm Name:
Contract Number:
Contract Title:
Location:
Type of Contract:
Contract Award Date:
Contract Performance Period:
Contracting Activity: (Name, Mailing Address, Phone Number, & Email Address)
Solicitation #AB1330-10-RP-0005 – Page 2
SECTION B - REFERENCE QUESTIONNAIRE
TO BE COMPLETED BY CLIENT/CUSTOMER REFERENCE
AND SUBMIT TO AGENCY
Please complete Section B of this questionnaire based on the following guidance. Handwritten responses are sufficient as long as legible. Please provide candid responses as the information you provide will be used in the awarding of a federal contract. Therefore, it is important that your information be as factual, accurate, and complete as possible. Your input is important to us and responses are needed by January 12, 2010 for inclusion in the evaluation process.
Name of Prime Contractor Performing the Contract (as shown on the contract documents):
Original Contract Amount: $ Final Contract Amount: $ Original Completion Date:
Final Completion Date:
Owner/Customer Point of Contact: (Include Name, Position Title, Current Phone Number, Mailing Address, Email Address, & Fax Number)
Was Offeror the Prime Contractor or Subcontractor
Prime _________ Subcontractor ___________
Was this work with a
Commercial/Private ____ Federal Gov't ____ Local/State Gov't ____ entity
Percentage of work performed by Offeror:
Provide a description of the contract scope of work as it relates to the evaluation criteria. Definition of “relevant" or “similar” project is defined as new or renovating construction of a biological research laboratory, hospital, research institution/laboratory with construction costs greater than $50 million AND a description of the work performed by the Offeror (if offeror performed work as a subcontractor). (Attach additional sheets if necessary). Description shall be in sufficient detail for the Government to determine relevancy to this project. Description shall provide specific details and shall not restate the criteria.
Provide any information on problems encountered and the corrective actions taken:
Key Personnel Assigned:
(Project Manager, On-site Superintendent, etc.)
Were they assigned for Duration of Project?
_____ Yes _____ No If No, please explain
Solicitation #AB1330-10-RP-0005 – Page 3
Other information the Customer Client deems necessary for the Government’s evaluation of past performance in terms of customer satisfaction, such as any negative past performance information that will assist the Government in fairly and accurately evaluating the company's past performance (e.g., why liquidated damages were assessed, resolution of claims, or why performance evaluation was marginal, etc.):
Liquidated Damages Assessed the Offeror: Yes _____ No _____
If Yes, please explain.
Any Claims Filed Under the Contract: Yes _____ No _____
If Yes, please explain.
Customer Evaluation of Work Performed: (Along with the completion of the information noted below, please attach any specific work or performance evaluation(s), letters of appreciation/commendation, letters of recommendation, etc. as evidence of customer satisfaction.)
When responding to the items listed below, choose the letter that most accurately describes the contractor's performance or situation. For any Outstanding, Good, or Unsatisfactory rating, please provide an explanatory narrative in the remarks column. This narrative need not be lengthy just detailed. Other comments are optional. If an item is not applicable choose "N/A". If more space is required use additional pages.
TYPE OF EVALUATION: FINAL INTERIM (____% COMPLETE)
EVALUATION OF PERFORMANCE ELEMENTS
CHECK ONE FOR EACH ELEMENT: O = OUTSTANDING; S = SATISFACTORY; M = MARGINAL;
U=UNSATISFACTORY; N/A = NOT APPLICABLE
QUALITY CONTROL O S M U N/A
REMARKS
QUALITY OF WORKMANSHIP
ADEQUACY OF THE CQC PLAN
IMPLEMENTATION OF THE CQC PLAN
QUALITY OF QC DOCUMENTATION
ADEQUACY OF SUBMITTALS
ADEQUACY OF QC TESTING
USE OF SPECIFIED MATERIALS
IDENTIFICATION/CORRECTION OF DEFICIENT WORK IN A TIMELY
MANNER
EFFECTIVENESS OF MANAGEMENT O S M U N/A
COOPERATION AND RESPONSIVENESS
MANAGEMENT OF RESOURCES/PERSONNEL
COORDINATION AND CONTROL OF SUBCONTRACTOR(S)
EFFECTIVENESS OF JOB-SITE SUPERVISION
COMPLIANCE WITH LAWS AND REGULATIONS
PROFESSIONAL CONDUCT
Solicitation #AB1330-10-RP-0005 – Page 4
REVIEW/RESOLUTION OF SUBCONTRACTOR'S ISSUES
REASONABLENESS OF MODIFICATIONS/CHANGES
READILY/REASONABLY ADDRESS RIPPLE EFFECT SUCH AS TIME
EXTENSIONS, EXTENDED OVERHEAD, ETC.
TIMELY PERFORMANCE O S M U N/A
ADEQUACY OF INITIAL PROGRESS SCHEDULE
ADHERENCE TO APPROVED SCHEDULE
RESOLUTION OF DELAYS
SUBMISSION OF UPDATED AND REVISED PROGRESS SCHEDULES
SUBMISSION OF COSTING INFORMATION, I.E., CHANGES, CLAIMS,
ETC.
COMPLETION OF PUNCHLIST ITEMS
WARRANTY RESPONSE
COMPLIANCE WITH SAFETY AND LABOR STANDARDS O S M U N/A
ADEQUACY OF SAFETY PLAN
IMPLEMENTATION OF SAFETY PLAN
COMPLIANCE WITH DAVIS-BACON
KNOWN VIOLATIONS OF SAFETY, LABOR, AND/OR
ENVIRONMENTAL LAWS
OVERALL RATING (X appropriate block)
OUTSTANDING SATISFACTORY MARGINAL UNSATISFACTORY
If given a choice, would you award a contract to this firm again?
_______YES _______ NO Explain:
SURVEY COMPLETED BY: (Survey shall be completed by the contracting agent and/or their representative responsible for the construction contract administration, or from the facility owner/user and must be submitted directly to the Agency by email to the address noted below.)
CLIENT/CUSTOMER FIRM/ORGANIZATION NAME TELEPHONE NUMBER
EMAIL ADDRESS FAX NUMBER
CLIENT/CUSTOMER NAME (PRINT) TITLE
CLIENT/CUSTOMER SIGNATURE DATE
Solicitation #AB1330-10-RP-0005 – Page 5
QUESTIONNAIRE MUST BE SUBMITTED DIRECTLY TO THE AGENCY BY:
EMAIL TO: Ms. Judi M. Jzyk, Contract Specialist
DOC/NOAA/WAD
judi.m.jzyk@noaa.gov
OR
FAX 206/527-7126
All information will be treated confidentially under source selection procedures. Receipt of this information is due by January 12, 2010. To obtain confirmation of receipt of this information, please call 206/526-6039.
mailto:judi.m.jzyk@noaa.gov
| ATTACHMENT J.2.3 |
| PAST PERFORMANCE QUESTIONNAIRE |
File details come from the government source that posted it. Updated .