This is a Past Performance Reference Questionnaire attachment to solicitation FA4626-26-R-0009 for the repair and renovation of Dormitory 742 at Great Falls Air Force Base, issued by the Department of the Air Force Global Strike Command. Offerors must submit between three and five recent and relevant past performance references with proposals due by 18 May 2026 at 2:00 p.m. Mountain Daylight Time. "Recent" references must be projects completed within the five years preceding April 2021, and "relevant" references must be similar in scope, size, and complexity to the solicitation requirements with contract values exceeding $5,000,000.
The questionnaire requires offerors to document specific project details including contract numbers, performance dates, dollar values, customer information with points of contact, competitive award status, contractor role (prime, subcontractor, or key personnel), descriptions of work performed, and identification of whether projects involved renovation or repair of dormitories, hotels, or large office facilities with partial demolition and reconstruction. Offerors must also demonstrate their proposed Project Manager's direct involvement and lead role on comparable projects. The evaluation criteria emphasize experience with coordination and integration of multiple building systems (HVAC, electrical, fire protection, plumbing, architectural, civil, mechanical, and structural), as well as management of project schedules, subcontractors, and risk. The questionnaire includes 24 performance rating questions using a five-point scale (Exceptional, Very Good, Satisfactory, Marginal, Unsatisfactory) to be completed by the customer reference, addressing contractor management capabilities, personnel qualifications, quality control, schedule adherence, problem resolution, subcontractor payment practices, and overall performance assessment.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 7 Controlled Unclassified Information (CUI)
FA4626-26-R-0009
When completed, this document is Source Selection Information IAW RFO 2.101 and 3.104. Past Performance Reference
Past Performance Reference Sheet In accordance with (IAW) paragraph 4 of Section L of this solicitation, please provide between three (3) and five (5) recent and relevant past performance references. As a reminder, “recent” is defined as “completed projects within the last five (5) years from April 2021”, and “relevant” is defined as the degree to which past performance projects are similar in scope, size, and complexity to the requirements of this solicitation and valued at more than $5,000,000.00.” Include rationale supporting your assertion of relevance. In assessing relevancy, the government will consider, at a minimum:
· Experience with renovation or repair of dormitory, hotel, or lager office-type facilities including partial demolition and reconstruction.
· Coordination and integration of multiple building systems (e.g., HVAC, electrical, fire protection, plumbing, architectural, civil, mechanical, and structural).
· Management of project schedule, subcontractors, and overall project risk.
· Relevancy will also consider the extent to which the referenced projects demonstrate the experience of the proposed Project Manager in performing similar work, particularly where the individual served in a lead role on projects of comparable size, scope, and complexity. Greater consideration may be given to references that the proposed Project Manager was directly responsible for overall project execution and outcomes on projects of similar scope, size, and complexity. Offerors shall include rationale supporting their assertion of relevancy.
One of the considerations in proposal evaluation is the verification of the offerors past performance on contracts or other work efforts, which reflect the offeror's ability to perform on the proposed effort.
Past performance references must be provided within Volume I – Past Performance of your company’s proposal, which is to be submitted and received no later than 18 May 2026 at 2:00 p.m. Mountain Daylight Time (MDT).
Attachment 7 Controlled Unclassified Information (CUI)
When completed, this document is Source Selection Information IAW RFO 2.101 and 3.104. Past Performance Reference Sheet
Section 1: Past Performance Reference:
a. Contract/Task Order Number:
b. Dates of Performance:
c. Contract Dollar Value:
d. Name of Customer:
e. Name and contact information of customer POC:
f. Was this a competitively awarded contract? ☐ Yes ☐ No
g. Contractor’s Role: ☐ Prime Contractor ☐ Subcontractor ☐ Key Personnel
h. All subcontractors, teaming arrangements, and/or joint venture partners.
i. Description of work performed:
j. Did the project involve renovation or repair of:
· ☐ Dormitory
· ☐ Hotel
· ☐ Large Office Facility
· ☐ Other _______________________ Did the project include:
· ☐ Partial Demolition
· ☐ Reconstruction
k. Did the project require coordination and integration of multiple building systems?
If yes, check all that apply:
· ☐ HVAC
· ☐ Electrical
· ☐ Plumbing
· ☐ Fire Protection
· ☐ Structural
· ☐ Architectural
· ☐ Civil
· ☐ Mechanical
l. Who was the Project Manager directly responsible for overall project execution?
m. Did the proposed Project Manager serve in a lead role on this project? ☐ Yes ☐ No
If yes, describe their role and level of responsibility:
| o. | Is there a CPARS for this Project ☐ Yes | ☐ No |
| - If there is no CPARS please have the below questionnaire filled out by the Customer referenced above in (d) for this work. |
Section 2: Past Performance Questionnaire In the table below, indicate your rating for the contractor’s performance by placing an “X” in the appropriate block to the right of each question. We depend on information received from organizations such as yours, which have had first-hand experience with the offeror, for the evaluation of the offeror's performance on those contracts or work efforts. Provide supporting information for each response in the space provided. Attach additional pages if more space is needed. The performance rating scale is defined as follows:
| Code | Performance Rating |
| E | EXCEPTIONAL – Performance meets contractual requirements and exceeds many requirements to the Government’s benefit. The contractual performance being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective. |
V VERY GOOD – Performance meets contractual requirements and exceeds some requirements to the Government’s benefit. The contractual performance being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
S SATISFACTORY – Performance meets contractual requirements. The contractual performance being assessed contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
M MARGINAL – Performance does not meet some contractual requirements. The contractual performance being assessed reflects a serious problem for which the contractor has not yet identified corrective actions or the contractor’s proposed actions appear only marginally effective or were not fully implemented.
U UNSATISFACTORY – Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance being assessed contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
N/A NOT APPLICABLE – Unable to provide a rating. Contract did not include performance for this aspect, performance was not observed, or information was not available. Do not know.
Note: The following are SAMPLE questions. Past Performance evaluation teams MUST construct a simple and concise Past Performance Questionnaire, tailored to seek out key information tied to the significant aspects of the planned acquisition. Avoid questions that can be answered with a “yes” or “no” but instead include probing and direct questions to draw out the required information desired.
| E |
| V |
| S |
| M |
| U |
| N/A |
1. Provided experienced managers and supervisors with the technical and administrative abilities needed to meet contract requirements.
SUPPORTING INFORMATION:
2. Demonstrated the ability to hire, maintain, and replace, if necessary, qualified personnel during the contract period.
3. Delegated authority to project managers and supervisors commensurate with contract requirements.
4. Home office participated in solving significant local problems. SUPPORTING INFORMATION:
5. Followed approved quality control plan. SUPPORTING INFORMATION:
6. Provided effective quality control and/or inspection procedures to meet contract requirements.
7. Corrected deficiencies in timely manner and pursuant to their quality control procedures.
8. Provided timely resolution of contract discrepancies. SUPPORTING INFORMATION:
When completed, this document is Source Selection Information IAW RFO 2.101 and 3.104. Past Performance Reference
| E |
| V |
| S |
| M |
| U |
| N/A |
9. Identified problems as they occurred. SUPPORTING INFORMATION:
10. Suggested alternative approaches to problems. SUPPORTING INFORMATION:
11. Displayed initiative to solve problems. SUPPORTING INFORMATION:
12. Developed realistic progress schedules. SUPPORTING INFORMATION:
13. Met established project schedules. SUPPORTING INFORMATION:
14. Provided timely resolution of warranty defects. SUPPORTING INFORMATION:
15. Was responsive to contract changes. SUPPORTING INFORMATION:
16. Provided adequate project supervision. SUPPORTING INFORMATION:
17. Obtained consent of surety for increases in bonding as work-in-progress increased.
When completed, this document is Source Selection Information IAW RFO 2.101 and 3.104. Past Performance Reference
| E |
| V |
| S |
| M |
| U |
| N/A |
18. Paid subcontractors/suppliers in a timely manner. SUPPORTING INFORMATION:
19. Provided accurate and complete line item cost proposals including all aspects of work required for each task.
20. Cooperated with Government personnel after award. SUPPORTING INFORMATION:
21. Met or exceeded small business and small disadvantaged business goals set forth in the approved subcontracting plan.
22. How would you rate the contractor's overall performance on this contract? SUPPORTING INFORMATION:
23. Was the contractor ever issued a cure or show cause notice under the referenced contract? If yes, explain.
EXPLANATION:
· Yes
· No
| 24. Would you award another contract to this contractor? If not, explain. EXPLANATION: |
| · Yes |
· No