This is a Scope of Work document for a County procurement involving the installation and commissioning of an air compressor system. The vendor shall furnish and install a compressor system at a designated County facility with installation completion required by August 17, 2026. The scope includes mechanical assembly, connection to the existing compressed air distribution header, condensate drain line connections, and verification of all safety devices and controls. The vendor is responsible for delivery via lift-gate equipped truck with offloading and staging at the installation site, and must ensure all components can pass through a 46-inch wide doorframe without structural modification. Additionally, the vendor shall provide factory-authorized startup and commissioning with documented commissioning data submitted within five business days of completion, conduct a minimum of two hours of on-site operator and maintenance training, and provide an Operations and Maintenance manual.
The pricing structure consolidates all costs—including the compressor system, installation, training, and warranty—into a single line item with the total cost to be specified by the vendor. The warranty package includes 24 months coverage for the compressor pump from acceptance and 12 months of parts and labor coverage for the system. The County is responsible for site readiness (providing a level, reinforced concrete floor adequate for unit weight), electrical rough-in (conduit, disconnect switch, and branch circuit wiring), and compressed air distribution piping beyond the system outlet. The vendor must provide certified weight data at least ten business days in advance of delivery and coordinate delivery access with the County at least five business days before the scheduled delivery date. An optional extended warranty coverage for years one through five is available at an additional cost to be specified by the vendor. All required permits, licenses, and calibration certificates are the vendor's responsibility and expense.
View the file
Other files
Show 40 more
Latest 50 of 148 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Item Quantity Units Description Cost
1 1 Each
Installation by August 17, 2026 (Must be installed by date.) Vendor shall furnish all labor, tools, rigging, and incidental materials required to set, assemble, level, anchor, and connect the compressor system at the designated installation location. Installation shall include: mechanical assembly and re-connection of any components disassembled for transport; connection to the existing compressed air distribution header at the point of connection identified by the County; connection of condensate drain lines to the nearest available floor drain; and verification that all safety devices, gauges, and controls are properly mounted and functional. Electrical rough-in (conduit, disconnect, and branch circuit wiring to the single power connection point on the unit) is the responsibility of the County and shall be completed prior to the Vendor’s installation visit.
Installation to be completed by:
Included
2 1 System
Model Type and Number:
BRAND NAME(s) OR EQUAL PURCHASE
DESCRIPTION:
3 1 System
SITE READINESS: The County shall provide a level, reinforced concrete or structural floor adequate for the unit weight prior to the scheduled installation date. Vendor shall provide certified weight data to the County not less than ten
(10) business days in advance of delivery to allow floor-loading verification. Included
ELECTRICAL ROUGH-IN (COUNTY-FURNISHED):
Electrical conduit, disconnect switch, and branch circuit wiring from the County facility panel to the single power connection point on the compressor unit is the responsibility of the County and shall be completed and inspected before the Vendor’s startup visit. County
COMPRESSED AIR DISTRIBUTION PIPING
(COUNTY-FURNISHED): Compressed air distribution piping beyond the system outlet connection point to the laboratory header is the responsibility of the County and shall be completed prior to the startup and commissioning visit. County
FACTORY-AUTHORIZED STARTUP AND
COMMISSIONING: Documentation of all commissioning data on a startup report to be submitted to the County within five (5) business days of completion. Included
6 1 System Training
OPERATOR AND MAINTENANCE TRAINING: The Vendor’s factory-authorized technician shall conduct on-site operator and maintenance training at the time of startup and commissioning. O&M manual is provided. Training shall be a minimum of two (2) hours in duration.
Included
7 24 Months Warranty – compressor pump ≥ 24 months from acceptance
Included
8 12 Months Warranty – system ≥ 12 months parts and labor
Included
CRITICAL:
All components and sub-assemblies of the air compressor package, whether shipped assembled or knocked down, must be capable of passing through a 46-inch (46") wide doorframe without structural modification to the building.
Included
DELIVERY:
F.O.B. – Destination: System shall be delivered via lift-gate equipped truck to the designated delivery point at the County facility. The Vendor shall offload and stage the equipment at the installation site. Any disassembly required for transport through the 46-inch doorframe shall be documented, and re-assembly instructions shall be provided. Vendor shall coordinate delivery access with the County not less than five
(5) business days before the scheduled delivery date.
Any required permits or licenses are the responsibility and cost of Vendor. Any calibration will have a certificate provided to the County at the responsibility and cost of Vendor. Included
12 All Costs Included
Total Costs with System, Installation, Training, and Warranty $