- Solicitation number
- RFP 2026-03-03
- Issued by
- Franklin County, Ohio
About this file
This is a procurement specification document for a County government contract involving the installation and commissioning of an air compressor system. The vendor is required to furnish and install a complete compressor system by August 17, 2026, including mechanical assembly, connection to the existing compressed air distribution header, condensate drain line connections, and verification of all safety devices and controls. The scope encompasses factory-authorized startup and commissioning with documented commissioning data submitted within five business days of completion, as well as mandatory on-site operator and maintenance training lasting a minimum of two hours. All components must be capable of passing through a 46-inch doorframe without structural modification, and delivery shall be via lift-gate equipped truck with vendor offloading and staging at the installation site. The vendor must coordinate delivery access at least five business days in advance and provide disassembly documentation and reassembly instructions if required for transport.
The contract includes a 24-month warranty on the compressor pump from acceptance and a 12-month parts and labor warranty on the system, with optional extended warranty coverage available on an annual basis for years one through five. All costs for the system, installation, training, and standard warranty are included in the total contract price. The County is responsible for electrical rough-in work, compressed air distribution piping beyond the system outlet, and site readiness including a level, reinforced concrete or structural floor. The vendor must provide certified weight data at least ten business days before delivery and is responsible for all required permits, licenses, and calibration certificates at vendor expense. Pricing is presented as a single line item with all costs included, though optional extended warranty rates are also specified.
View the file
Other files
Show 40 more
Latest 50 of 146 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Item Quantity Units Description Cost
1 1 Each
Installation by August 17, 2026 (Must be installed by date.) Vendor shall furnish all labor, tools, rigging, and incidental materials required to set, assemble, level, anchor, and connect the compressor system at the designated installation location. Installation shall include: mechanical assembly and re-connection of any components disassembled for transport; connection to the existing compressed air distribution header at the point of connection identified by the County; connection of condensate drain lines to the nearest available floor drain; and verification that all safety devices, gauges, and controls are properly mounted and functional. Electrical rough-in (conduit, disconnect, and branch circuit wiring to the single power connection point on the unit) is the responsibility of the County and shall be completed prior to the Vendor’s installation visit.
Installation to be completed by:
Included
2 1 System
Model Type and Number:
BRAND NAME(s) OR EQUAL PURCHASE
DESCRIPTION:
3 1 System
SITE READINESS: The County shall provide a level, reinforced concrete or structural floor adequate for the unit weight prior to the scheduled installation date. Vendor shall provide certified weight data to the County not less than ten
(10) business days in advance of delivery to allow floor-loading verification. Included
ELECTRICAL ROUGH-IN (COUNTY-FURNISHED):
Electrical conduit, disconnect switch, and branch circuit wiring from the County facility panel to the single power connection point on the compressor unit is the responsibility of the County and shall be completed and inspected before the Vendor’s startup visit. County
COMPRESSED AIR DISTRIBUTION PIPING
(COUNTY-FURNISHED): Compressed air distribution piping beyond the system outlet connection point to the laboratory header is the responsibility of the County and shall be completed prior to the startup and commissioning visit. County
FACTORY-AUTHORIZED STARTUP AND
COMMISSIONING: Documentation of all commissioning data on a startup report to be submitted to the County within five (5) business days of completion. Included
6 1 System Training
OPERATOR AND MAINTENANCE TRAINING: The Vendor’s factory-authorized technician shall conduct on-site operator and maintenance training at the time of startup and commissioning. O&M manual is provided. Training shall be a minimum of two (2) hours in duration.
Included
7 24 Months Warranty – compressor pump ≥ 24 months from acceptance
Included
8 12 Months Warranty – system ≥ 12 months parts and labor
Included
CRITICAL:
All components and sub-assemblies of the air compressor package, whether shipped assembled or knocked down, must be capable of passing through a 46-inch (46") wide doorframe without structural modification to the building.
Included
DELIVERY:
F.O.B. – Destination: System shall be delivered via lift-gate equipped truck to the designated delivery point at the County facility. The Vendor shall offload and stage the equipment at the installation site. Any disassembly required for transport through the 46-inch doorframe shall be documented, and re-assembly instructions shall be provided. Vendor shall coordinate delivery access with the County not less than five
(5) business days before the scheduled delivery date.
Any required permits or licenses are the responsibility and cost of Vendor. Any calibration will have a certificate provided to the County at the responsibility and cost of Vendor. Included
12 All Costs Included
Total Costs with System, Installation, Training, and Warranty $
13 1-5 Annual Rate Optional Extended Warranty Coverage $
Vendor Name
Completed By
Date