9-2.6 ADMIN SPECIFICATIONS 01720 Project Record Documents.pdf

PDF 75 KB Posted

Attached to
COMMUNITY CENTER ARCHITECTURAL DESIGN SERVICES
Solicitation number
Not on record
Issued by
Delaware County, Pennsylvania

About this file

This is an Administrative Specifications document detailing Project Record Documents requirements for Upper Darby Township in Delaware County, Pennsylvania, applicable to the 2026 Resurfacing of Various Streets project. The document establishes mandatory procedures for contractors to maintain, record, and submit comprehensive project documentation throughout the construction phase and upon project completion. Contractors must maintain one copy each of all contract drawings, specifications, amendments, change orders, modifications, shop drawings, and product data at the job site in a clean, dry, legible condition using Construction Specifications Institute filing standards. Documentation must be recorded concurrently with construction progress, with drawings legibly marked to show actual construction including horizontal and vertical locations of utilities, field changes, supplemental instructions, and change orders. Specifications must identify the manufacturer, trade name, catalog number, and supplier of each installed product and equipment, along with any modifications made during construction.

Upon project completion, contractors must submit one set of marked drawings showing all construction notations, two copies of annotated shop drawings or product data sheets requiring post-approval modifications, and one complete set of contract drawings (with Design Professional drawing reimbursement required if applicable). All final submittals must be accompanied by a transmittal letter containing project data, the contractor's name and address, document titles and numbers, certification of completeness and accuracy, and the authorized contractor representative's signature. These record documents serve as permanent documentation of the actual work performed and constitute a critical deliverable for project closeout and future reference by Upper Darby Township.

View the file

Other files

File Type Posted
1-FINAL UDT Community Ctr RFP Arch Dgn Svcs Rev1 (sent 07.08.26).pdf PDF
8-2.3 ADMIN SPECS 01201 PRECONSTRUCTION CONFERENCE.pdf PDF
3-2.2 ADMIN SPECS 01025 MEASUREMENT PAYMENT.pdf PDF
13-1.3 APPENDIX K - DCNR.pdf PDF
15-5.0 UDT RCO ORD NO 3107.pdf PDF
14-1.0 FRONT END SPECS (OBSERVATORY HILL REBID).pdf PDF
18-2.2 (UPDATED) ADMIN SPECS 01025 MEASUREMENT PAYMENT.pdf PDF
19-2.2 (UPDATED) ADMIN SPECS 01025 MEASUREMENT PAYMENT.pdf PDF
4-4.0 - PUBLIC WORKS EMPLOYMENT VERIFICATION FORM.pdf PDF
10-2.4 ADMIN SPECS 01340 SHOP DRAWINGS SAMPLES.pdf PDF
7-1.1 ADVERTISEMENT - OBSERVATORY HILL REBID.pdf PDF
12-2.6 ADMIN SPECS 01720 PROJECT RECORD DOCUMENTS.pdf PDF
16-1.2 PGS D CONTRACT FORMS.pdf PDF
9-3.0 PA PREVAILING WAGES.pdf PDF
2-1.5 APPENDIX K - DCNR NONDISCRIMINATION - SEXUAL HARRASSMENT CLAUSE.pdf PDF
15-9.0 BID DOCUMENTS PAGES D-1 THRU D-9.pdf PDF
4-2.4 ADMIN SPECIFICATIONS 01340 Shop Drawings Samples.pdf PDF
17-6.0 PENNDOT 944 PROPOSAL FORM.pdf PDF
13-7.0 PREVAILING WAGE RATES.pdf PDF
2-2.3 ADMIN SPECIFICATIONS 01201 Preconstruction Conference.pdf PDF
18-8.0 UDT RCO ORDINANCE.pdf PDF
1-1.0 FRONT END DOCS.pdf PDF
5-2.1 ADMIN SPECIFICATIONS 01010 Contractors Work.pdf PDF
6-2.2 ADMIN SPECIFICATIONS 01025 Measurement Payment.pdf PDF
11-5.0 PENNDOT FORMS.pdf PDF
7-4.1 PADOT SPECIFICATIONS PADOT SECTION 409.pdf PDF
12-2.5 ADMIN SPECIFICATIONS 01700 Project Closeout.pdf PDF
8-1.1 ADVERTISEMENT.pdf PDF
10-4.0 PADOT SPECIFICATIONS PADOT SECTION 350.pdf PDF
19-10.0 UDT 2026 Streets Resurfacing Map FINAL.pdf PDF
2-Specifications.pdf PDF
1-Golf Road Parking Lot.pdf PDF
12-pages D-1 thru D-9.pdf PDF
4-01340 Shop Drawings Samples.pdf PDF
9-02930 Lawns Grasses.pdf PDF
14-Public Works Verification Form.pdf PDF
10-Naylors Run Trail Section 5A advertisement.pdf PDF
11-Nondiscrimination - Sexual Harassment Clause (3).pdf PDF
13-01010 Contractors Work.pdf PDF
16-Prevailing Wages.pdf PDF
17-Naylors Run Trail 5A - Bid Docs Complete 08.18.25.pdf PDF
18-Naylors Run Trail 5A Plans (Signed 08.12.25 r1).pdf PDF
2-01025 Measurement Payment.pdf PDF
5-02210 Rough Grading.pdf PDF
6-01001 Special Provisions.pdf PDF
7-01201 Preconstruction Conference.pdf PDF
1-01720 Project Record Documents.pdf PDF
15-UDT RCO Ord. no. 3107.pdf PDF
3-01700 Project Closeout.pdf PDF
8-02260 Finish Grading.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01720-1

SECTION 01720

PROJECT RECORD DOCUMENTS

PART 1 GENERAL

1.1 MAINTENANCE OF DOCUMENTS

A. Maintain at job site, one copy of record documents including Drawings, Specification, Amendments, Change Orders and other modifications, Shop Drawings, product date and samples.

B. In addition, maintain one copy of field orders or written instructions and field test records.

C. Provide files and racks for storage documents.

D. File documents and samples in accordance with Data Filing Format of the

Construction Specifications Institute (C.S.I).

E. Maintain documents in a clean, dry, legible condition and in good order. Do not use record documents for construction purposes.

F. Make Documents and samples available at all times for inspection.

1.2 RECORDING

A. Label each document "Project Record" in neat large letters.

B. Record information concurrently with construction progress.

C. Do not conceal any work until required information is recorded.

D. Drawings - Legibly mark to record actual construction:

1. Horizontal and vertical locations of laterals, underground utilities and appurtenances, referenced to permanent surface improvements.

2. Field changes of dimension and detail.

3. Changes made by Supplemental Instruction or by Change Order.

4. Details not on original Contract Drawings.

E. Specifications and Amendments - Legibly mark each Section to record

01720-2

1. Manufacturer, trade name, catalog number, and Supplier of each Product and item of equipment actually installed.

2. Changes made by Supplemental Instructions or by Change Order.

F. Shop Drawings - Maintain as record documents. Legibly annotate any changes made after review.

1.3 SUBMITTALS

A. At completion of the Work, furnish one set of drawings showing all notations specified above. A copy of the Design Professional's drawings may be used for this purpose upon reimbursement of the printing costs to the Design Professional. In addition, furnish two copies of any shop drawings or product data sheet which required annotation after approval.

B. After inclusion of additional data, if any, furnish:

1. One set of contract drawings as specified under 1.3, A. above.

2. Two sets of all other Project Record Documents.

C. Accompany this final submittal with transmittal letter containing data, project title and number, Contractor's name and address, title and number of each Record Document, certification that each document as submitted as complete and accurate, signature of Contractor or his authorized representative.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION