4-2.4 ADMIN SPECIFICATIONS 01340 Shop Drawings Samples.pdf

PDF 75 KB Posted

Attached to
COMMUNITY CENTER ARCHITECTURAL DESIGN SERVICES
Solicitation number
Not on record
Issued by
Delaware County, Pennsylvania

About this file

This is an administrative specification document for shop drawings, product data, and samples submitted by contractors to Upper Darby Township, Delaware County, Pennsylvania, for infrastructure projects including the 2026 Resurfacing of Various Streets. The specification establishes mandatory submittal procedures requiring contractors to present shop drawings, product data, and instruction manuals in a clear and thorough manner with details identified by reference to contract drawings. Submittals must be made electronically and promptly according to an approved schedule to prevent delays in work execution. Each submittal requires specific documentation including submission dates, project title, contract number, contractor and supplier names, product identification with specification section numbers, applicable standards such as ASTM or Federal Specification numbers, identification of any deviations from contract documents, and an 8-inch by 3-inch blank space for contractor and engineer stamps. The contractor must certify review of the submittal, verification of products, field measurements, field construction criteria, and coordination with all work requirements and contract documents through an initialed or signed stamp.

Resubmission requirements mandate that contractors make any corrections or changes identified by the engineer and resubmit revised drawings or data until approval is obtained, with all revisions clearly indicated on subsequent submissions. This specification applies to all contractors bidding on Upper Darby Township projects valued at $100,000 or more, who must demonstrate competency and responsibility under the Township's Responsible Contractors Ordinance. The specification establishes uniform documentation standards across multiple township infrastructure projects to ensure quality control, coordination among contractors, and compliance with prevailing wage requirements and bond obligations.

View the file

Other files

File Type Posted
1-FINAL UDT Community Ctr RFP Arch Dgn Svcs Rev1 (sent 07.08.26).pdf PDF
8-2.3 ADMIN SPECS 01201 PRECONSTRUCTION CONFERENCE.pdf PDF
3-2.2 ADMIN SPECS 01025 MEASUREMENT PAYMENT.pdf PDF
13-1.3 APPENDIX K - DCNR.pdf PDF
15-5.0 UDT RCO ORD NO 3107.pdf PDF
14-1.0 FRONT END SPECS (OBSERVATORY HILL REBID).pdf PDF
18-2.2 (UPDATED) ADMIN SPECS 01025 MEASUREMENT PAYMENT.pdf PDF
19-2.2 (UPDATED) ADMIN SPECS 01025 MEASUREMENT PAYMENT.pdf PDF
4-4.0 - PUBLIC WORKS EMPLOYMENT VERIFICATION FORM.pdf PDF
10-2.4 ADMIN SPECS 01340 SHOP DRAWINGS SAMPLES.pdf PDF
7-1.1 ADVERTISEMENT - OBSERVATORY HILL REBID.pdf PDF
12-2.6 ADMIN SPECS 01720 PROJECT RECORD DOCUMENTS.pdf PDF
16-1.2 PGS D CONTRACT FORMS.pdf PDF
9-3.0 PA PREVAILING WAGES.pdf PDF
2-1.5 APPENDIX K - DCNR NONDISCRIMINATION - SEXUAL HARRASSMENT CLAUSE.pdf PDF
15-9.0 BID DOCUMENTS PAGES D-1 THRU D-9.pdf PDF
17-6.0 PENNDOT 944 PROPOSAL FORM.pdf PDF
13-7.0 PREVAILING WAGE RATES.pdf PDF
2-2.3 ADMIN SPECIFICATIONS 01201 Preconstruction Conference.pdf PDF
18-8.0 UDT RCO ORDINANCE.pdf PDF
1-1.0 FRONT END DOCS.pdf PDF
5-2.1 ADMIN SPECIFICATIONS 01010 Contractors Work.pdf PDF
6-2.2 ADMIN SPECIFICATIONS 01025 Measurement Payment.pdf PDF
11-5.0 PENNDOT FORMS.pdf PDF
7-4.1 PADOT SPECIFICATIONS PADOT SECTION 409.pdf PDF
12-2.5 ADMIN SPECIFICATIONS 01700 Project Closeout.pdf PDF
8-1.1 ADVERTISEMENT.pdf PDF
10-4.0 PADOT SPECIFICATIONS PADOT SECTION 350.pdf PDF
19-10.0 UDT 2026 Streets Resurfacing Map FINAL.pdf PDF
9-2.6 ADMIN SPECIFICATIONS 01720 Project Record Documents.pdf PDF
2-Specifications.pdf PDF
1-Golf Road Parking Lot.pdf PDF
12-pages D-1 thru D-9.pdf PDF
4-01340 Shop Drawings Samples.pdf PDF
9-02930 Lawns Grasses.pdf PDF
14-Public Works Verification Form.pdf PDF
10-Naylors Run Trail Section 5A advertisement.pdf PDF
11-Nondiscrimination - Sexual Harassment Clause (3).pdf PDF
13-01010 Contractors Work.pdf PDF
16-Prevailing Wages.pdf PDF
17-Naylors Run Trail 5A - Bid Docs Complete 08.18.25.pdf PDF
18-Naylors Run Trail 5A Plans (Signed 08.12.25 r1).pdf PDF
2-01025 Measurement Payment.pdf PDF
5-02210 Rough Grading.pdf PDF
6-01001 Special Provisions.pdf PDF
7-01201 Preconstruction Conference.pdf PDF
1-01720 Project Record Documents.pdf PDF
15-UDT RCO Ord. no. 3107.pdf PDF
3-01700 Project Closeout.pdf PDF
8-02260 Finish Grading.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01340-1

SECTION 01340

SHOP DRAWINGS, PRODUCT DATA AND SAMPLES

PART 1 GENERAL

1.1 WORK INCLUDED

A. Submit Shop Drawings, Product Data, and Instruction Manuals required by Contract

Documents.

1.2 RELATED REQUIREMENTS

A. Definitions, and Additional Responsibilities of Parties: Conditions of the Contract.

1.3 SHOP DRAWINGS

A. Drawings shall be presented in a clear and thorough manner.

1. Details shall be identified by reference to sheet and detail, shown on

Contract Drawings.

1.4 PRODUCT DATA

A. Preparation

1. Clearly mark each copy to identify pertinent products or models.

2. Show performance characteristics and capacities.

3. Show dimensions and clearances required.

1.5 SUBMISSION REQUIREMENTS

A. Make submittals promptly in accordance with approved schedule, and in such sequence as to cause no delay in the Work or in the work of any other contractor.

B. Number of Submittals Required:

1. Shop Drawings: Submit electronically.

2. Product Data: Submit electronically.

C. Submittals Shall Contain:

01340-2

1. The date of submission and the dates of any previous submissions.

2. The Project title and contract number.

3. The names of:

a. Contractor.

b. Supplier.

c. Manufacturer.

4. Identification of the product, with the specification section number.

5. Applicable standards, such as ASTM or Federal Specification numbers.

6. Identification of deviations from Contract Documents.

7. Identification of revisions on resubmittals.

8. An 8 in. x 3 in. blank space for Contractor and Engineer stamps.

9. Contractor's stamp, initialed or signed, certifying to review of submittal, verification of products, field measurements and field construction criteria, and coordination of the information within the submittal with requirements of the Work and of Contract Documents.

1.6 RESUBMISSION REQUIREMENTS

A. Make any corrections or changes in the submittals required by the Engineer and resubmit until approved.

B. Shop Drawings and Product Data:

1. Revise initial drawings or data, and resubmit as specified for the initial submittal.

2. Indicate any changes which have been made other than those previously noted by the Engineer.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION