3-2.2 ADMIN SPECS 01025 MEASUREMENT PAYMENT.pdf
PDF 102 KB Posted
- Attached to
- COMMUNITY CENTER ARCHITECTURAL DESIGN SERVICES
- Solicitation number
- Not on record
- Issued by
- Delaware County, Pennsylvania
About this file
This is an administrative specifications document from Upper Darby Township in Delaware County, Pennsylvania, detailing measurement and payment methodologies for construction work performed under unit price and stipulated lump sum payment methods. The document establishes that the Contractor is responsible for taking all measurements and computing quantities, which the Engineer will verify. Quantities indicated in the Form of Proposal are for bidding purposes only, and actual work quantities placed and verified by the Engineer determine final payment. The Contractor must provide all required quantities at contracted unit or lump sum prices, regardless of whether actual quantities exceed or fall short of estimated amounts. Measurement methods specified include by number of completed items, volume using cubic dimensions, area using square dimensions, linear dimension at item centerline, or by weight, volume, area, or linear means as appropriate to the completed work unit.
Payment includes full compensation for all supervision, labor, products, tools, equipment, plant, transportation, services, and incidental work, with specific notation that replacement of existing pavement markings with thermoplastic markings matching existing sizes shall be included under the 11.5-inch Superpave wearing bid item. Final payment for unit price work is calculated by multiplying actual measurements and quantities accepted by the Engineer by the contracted unit price, with replacement of line stripe for lanes, stop bars, and crosswalks included in unit pricing. The document explicitly prohibits payment for products wasted or disposed of improperly, products deemed unacceptable before or after placement, products placed beyond required lines and levels, products remaining after completion, and costs associated with loading, hauling, and disposing of rejected products. No additional compensation is authorized except through written order of the Owner.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01025-1
SECTION 01025
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Measurement and payment criteria applicable to the Work performed under a Unit
Price payment method and stipulated Lump Sum method.
B. Defect assessment and non-payment for rejected work.
1.2 AUTHORITY
A. Measurement methods delineated in the individual specification sections, if any, are intended to complement the criteria of this section.
B. The Contractor shall take all measurements and compute quantities. The Engineer will verify measurements and quantities.
1.3 UNIT QUANTITIES SPECIFIED
A. Quantities and measurements indicated in the Form of Proposal are for bidding and contract purposes only. Quantities and measurements supplied or placed in the Work and verified by the Engineer shall determine payment.
B. If the actual Work requires more or fewer quantities than those quantities indicated, provide the required quantities at the unit or lump sum prices contracted.
1.4 MEASUREMENT OF QUANTITIES
A. Measurement by Number: Will be measured by the actual number of completed items installed.
B. Measurement by Volume: Measured by cubic dimension using mean length, width and height or thickness.
C. Measurement by Area: Measured by square dimension using mean length and width or radius.
01025-2
D. Linear Measurement: Measured by linear dimension, at the item centerline or mean chord.
E. Stipulated Lump Sum or Unit Price Measurement: Items measured by weight, volume, area, or linear means or combination, as appropriate, as a completed item or unit of the Work.
1.5 PAYMENT
A. Payment Includes: Full compensation for all required supervision, labor, products, tools, equipment, plant, transportation, services, replacement of existing pavement markings with Thermo Plastic markings matching existing pavement marking sizes and to be included under the 11/2” Superpave wearing bid item, and all incidental work; erection, application or installation of an item of the Work; overhead and profit.
B. Final payment for Work governed by unit prices will be made on the basis of the actual measurements and quantities accepted by the Engineer multiplied by the unit price for Work which is incorporated in or made necessary by the Work.
Replacement of existing line stripe for lane, stop bars and crosswalks are to be included in unit pricing.
1.6 DEFECT ASSESSMENT
A. Replace the Work, or portions of the Work, not conforming to specified requirements.
1.7 NON-PAYMENT FOR REJECTED PRODUCTS
A. Payment will not be made for any of the following:
1. Products wasted or disposed of in a manner that is not acceptable.
2. Products determined as unacceptable before or after placement.
3. Products placed beyond the lines and levels of the required Work.
4. Products remaining on hand after completion of the Work.
5. Loading, hauling, and disposing of rejected Products.
01025-3
PART 2 GENERAL
2.1 GENERAL
A. Payment for materials furnished and work done under this contract will be made as hereinafter stipulated for the amount of materials furnished and work performed under authorization of Engineers, or their authorized representative, and in accordance with their measurements. Contractor shall not be entitled to receive additional compensation for any work or materials except as shall be authorized by written order of the Owner.
B. The following items, classifying the various kinds of work, refer to respective items bid in the "Form of Proposal".
C. Items 1.1 thru 1.53:
END OF SECTION