Project Closeout Administrative Specifications for Upper Darby Township
This is an administrative specifications document (Section 01700 Project Closeout) applicable to construction contracts for Upper Darby Township, Delaware County, Pennsylvania, specifically relating to the 2026 Resurfacing of Various Streets project. The specifications establish the closeout procedures contractors must follow upon substantial and final completion of work. The document outlines a two-phase completion process: substantial completion requires contractors to submit written notice detailing items requiring completion or correction, followed by engineer observation and verification; final completion requires contractor certification that all work complies with contract documents, equipment and systems are operational, and work is ready for final observation. If work fails to meet completion claims, contractors are subject to re-inspection fees deducted from final payment. The contract requires contractors to submit project record documents per Section 01720, furnish specified spare parts and maintenance materials, and prepare a final accounting statement reflecting all adjustments to the contract sum including change orders, allowances, unit prices, and deductions for uncorrected work.
Contractors must submit a final application for payment following procedures outlined in the contract conditions. The specifications mandate that spare parts and maintenance materials be packaged, labeled, and stored in building areas designated by the engineer. The final accounting statement must itemize the original contract sum, all additions and deductions from change orders and allowances, the total adjusted contract sum, previous payments received, and the remaining sum due. The engineer prepares a final change order reflecting any approved adjustments not previously documented, ensuring a complete accounting reconciliation before project closeout is finalized.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01700-1
SECTION 01700
PROJECT CLOSEOUT
PART 1 GENERAL
1.1 RELATED WORK SPECIFIED ELSEWHERE
A. Project Record Documents - Section 01720.
1.2 SUBSTANTIAL COMPLETION
A. When the work is considered substantially complete, submit a written notice that the work, or a designated portion thereof, is substantially complete. Include a list of all items that require completion or correction.
B. Within a reasonable time after receipt of such notice, an observation will be made to determine the status of completion.
C. If the Work is not considered substantially complete, the Contractor will be notified in writing, giving the reasons therefore.
D. Contractor shall remedy the deficiencies in the Work, and send a second written notice of substantial completion. This notice shall include a statement of action taken on each item noted a requiring correction or completion to achieve "Substantial Completion" status.
E. The Work will be observed a second time.
F. When the Engineer concurs that the Work is substantially complete, he will:
1. Issue a letter accompanied by Contractor's list of items to be completed or corrected, as verified and amended by the Engineer.
1.3 FINAL OBSERVATION
A. When the Work is considered complete, submit written certification that:
1. Contract Documents have been reviewed.
2. Work has been observed and has been completed in compliance with
Contract Documents.
01700-2
3. Equipment and systems have been tested in the presence of the Engineer and are operational.
4. Work is ready for final observation.
B. Observation will be made to verify the status of completion with reasonable promptness after receipt of such certification.
C. If the Work is not considered complete, the Contractor will be notified in writing, listing the incomplete or defective work.
D. Contractor shall take immediate steps to remedy the stated deficiencies and, after correcting deficiencies, he shall send a second written certificate that the work is complete. This certification shall itemize each deficiency noted and a statement of action taken to remedy or complete the Work.
E. The work will be observed a second time.
F. When the Work is acceptable under the Contract Documents, the Contractor shall be required to make closeout submittals.
1.4 SECOND OBSERVATION FEES
A. Should the Engineer perform a second observation due to failure of the work to comply with the claims of status of completion made by the Contractor:
1. Engineer will deduct the amount of such compensation from the final payment to the Contractor.
1.5 CLOSEOUT SUBMITTALS
A. Project Record documents as specified under Section 01720.
1.6 SPARE PARTS AND MAINTENANCE MATERIALS
A. Furnish spare parts and maintenance materials as specified under various Sections of the Specifications.
B. Package and label parts and materials and store in area of the building where directed by the Engineer.
1.7 FINAL ADJUSTMENT OF ACCOUNTS
01700-3
A. Submit a final statement of accounting.
B. Statement shall reflect all adjustments to the Contract Sum:
1. The original Contract Sum.
2. Additions and deductions resulting from:
a. Previous Change Orders.
b. Allowances.
c. Unit Prices.
d. Deductions for uncorrected Work.
e. Deductions for re-inspection payments.
f. Other adjustments.
3. Total Contract Sum, as adjusted.
4. Previous payments.
5. Sum remaining due.
C. The Engineer will prepare a final Change Order, reflecting approved adjustments to the Contract sum which were not previously made by Change Orders.
1.8 FINAL APPLICATION FOR PAYMENT
A. Submit the final Application for Payment in accordance with procedures and requirements stated in the Conditions of the Contracts.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION