06 SEAM E-15 SOW DETAIL ISS Power Supply.pdf

PDF 22 KB Posted

Attached to
Specialized, Engineering, Aeronautics, and Manufacturing (SEAM) II Solicitation
Solicitation number
80JSC020R0045
Issued by

View the file

Other files

File Type Posted
SEAM II SF-30 Amendment 4.pdf PDF
LFT_User_Guide.pdf PDF
SEAM II SF-30 Amendment 3.pdf PDF
LFT_Quick_Start_Guide.pdf PDF
80JSC020R0045 SEAM II SF-33.pdf PDF
SF-30 SEAM II Amendment 2.pdf PDF
Attachment IV L.32.6 Price Templates.xlsx XLSX spreadsheet
SF-30 SEAM II.pdf PDF
Attachment 2 SEAM II RFP 80JSC020R0045.pdf PDF
Amendment 1 SEAM II Final RFP Questions and Responses.pdf PDF
Attachment III L.32.2 Past Performance Reference Table.xlsx XLSX spreadsheet
Attachment 1 Signed SEAM II Cover Letter.pdf PDF
Attachment V 80JSC020R0045 Track Changes.docx DOCX document
Modification 3 SEAM II Final RFP Questions and Responses.pdf PDF
Modification 2 Final RFP Questions and Responses.pdf PDF
07 Price Breakout SEAM E-15.xlsx XLSX spreadsheet
02 SEAM D04 Emergency Mask Trainers.pdf PDF
04 Mask Measurements.pdf PDF
03 D-04 Emer Mask requirements.pdf PDF
SEAM II Pre-proposal Conference Charts.pdf PDF
05 SEAM RFP Coversheet E-15.pdf PDF
01 Fidelity Classification Matrix.pdf PDF
SEAM Sec L - L_32_1 Relevant Past Performance Matrix.xlsx XLSX spreadsheet
80JSC020R0045 SEAM II Final RFP.pdf PDF
SEAM Sec L - L_32_2 Past Performance Reference Table.xlsx XLSX spreadsheet
SEAM Sec L - L_32_6 Price Templates.xlsx XLSX spreadsheet
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Task NO.: E-15 SEAM Proposal Request

TASK TITLE: Power Supply Assembly 120VDC

REQUIREMENTS/REFERENCES:

1.0 Build to print the following hardware to IIA fidelity(with redlines)

1.1 Twenty (20) ea Power Cable Assembly part number SEZ39129260 IIA Fidelity

1.1.1 Sixteen (16) ea SEZ39129260-309

1.1.2 Four (4) ea SEZ39129260-311

1.2 Twenty (20) ea ISS ZBOOK Power Cables part number SEG33125099-302 IIA Fidelity

1.2.1 Nine (9) ea HP ZBook power supplies will be provided.(GSE)

1.2.2 The remaining 11 power supplies will need to be provided as part of the project.

1.3 Twenty (20) ea Power Supply Assembly 120 VDC part number 25-040-20-0005

1.3.1 Use the provided Mockup drawings for design, manufacture and assembly

1.3.2 Upgrade the DC to DC converter to VICOR VI-L5N-IU, see provided data sheet

1.3.2.1 This will replace item 15 on the 25-040-20-0005 drawing provided.

1.3.3 Power Supply Assembly enclosure shall be cobalt blue, this is the -802 version in drawing 25-040-20-0002

1.4 All hardware shall have labels install

1.5 All connectors shall have caps and plugs with lanyards installed

Testing requirements:

Load test of the power supply with a 80% load to verify the exterior case does not exceed the 113F touch temperature limit.

Verify the output voltage between 16.4 and 17.5 volts Verify cable connections to the power supply assembly Provide a copy of the test results for each unit.

Provide one unit with one of each of the cables for evaluation before starting production run of the remaining units.

Reference Material Provided:

Drawings:

25-040-20-0002 25-040-20-0003 25-040-20-0004 25-040-20-0005 25-040-20-0006 25-040-30-0002A

SEG33125099-302

SEZ39129260-303

Documents:

VICOR VI-L5N-IU data sheet Fidelity definitions

ACCEPTANCE CRITERIA/DELIVERABLES DEFINITION:

All requirements met. Functional check of at least one set Utility Outlet Panel (UOP) cable to power supply assembly and power supply assembly to zbook cable all connected to a UOP and zbook in the SVMF.

SCHEDULE MILESTONES: (complete or reference separate project plan)

BASIS OF ESTIMATE

Include and identify significant assumptions: (complete or reference separate project plan)

RISK ASSESSMENT

Include risk associated with facility cost for maintenance in out years: (complete or reference separate project plan)

MAJOR COST AND SCHEDULE DRIVERS: (complete or reference separate project plan)

DELIVERABLES:

Materials List Proof Loading Drawing Package (Paper and Electronic) Lift Plan Stress Analysis/Stress Models Mass Properties Welding Report Tip Over Analysis Project Design Review. PDR CDR General Design Review Hazard Analysis Operation/maintenance instructions Assembly/Installation instructions Status Reports (DRD XXX) Weekly Bi-weekly Monthly None Test Readiness Review Package Flight Readiness Review Package

File details come from the government source that posted it. Updated .