GeoXO Spacecraft Final RFP Questions and Answers Two (002).pdf

PDF 416 KB Posted

Attached to
Geostationary Extended Observations (GeoXO) Spacecraft (SC) Phase B Implementation- Final RFP Federal contract opportunity
Solicitation number
80GSFC23R0010F
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

This document contains questions and answers regarding the final request for proposal for the Geostationary Extended Observations Spacecraft Phase B Implementation opportunity with the National Aeronautics and Space Administration Goddard Space Center. Several questions were asked to clarify requirements for the proposal, including page limits for appendices and the ability to include acronym lists outside of volume page counts. Definitions for verification methods like inspection, test, analysis and demonstration were also provided. One question sought to confirm the number for a small business goal, to which the agency responded with the correct figure of 20.5 percent from the updated source document.

View the file

Other files for this federal contract opportunity

Other files attached to Geostationary Extended Observations (GeoXO) Spacecraft (SC) Phase B Implementation- Final RFP, newest first.
File Type Posted
Amendment 1 Amend Section L.12.pdf PDF
GeoXO Spacecraft Final RFP Questions and Answers 3.pdf PDF
GeoXO Spacecraft SF33.pdf PDF
GeoXO Spacecraft Final RFP Questions and Answers.pdf PDF
GeoXO Spacecraft Final RFP Cover Letter.pdf PDF
Attachment F-1-418-XO-GXIUIID-0023_V_2_4.pdf PDF
Attachment F-5-418-XO-ACXUIID-0072_V_1_6.pdf PDF
Attachment I-418-XO-RPT-0042 Radiation Environment for Electronic Devices final V1_2 RO (1).pdf PDF
Attachment M RESERVED.pdf PDF
Attachment P_GeoXO_TAM_Table Phase B - Final Rev1.pdf PDF
Attachment Q GeoXO MEL_09_28_2023_rev1.pdf PDF
Attachment R_GeoXO Link Budget Templates 09_28_2023.pdf PDF
Attachment AB - Requirements Statements List.pdf PDF
9.29.23 Final GeoXO Spacecraft Implementation Phase B RFP.pdf PDF
Attachment B-418-XO-SCCDRL-0053_V_1_0_final.pdf PDF
Attachment C-418-XO-PSPEC-0051_V_1_5_final.pdf PDF
Attachment F-2-418-XO-LMXUIID-0067 V1_4.pdf PDF
Attachment G-1-418-XO-IRD-0044_V_1_4.pdf PDF
Attachment O-GeoXO SC Engineering Units and Risk.pdf PDF
Attachment V -DEIA Plan DRD.pdf PDF
Attachment X - Small Business Subcontracting Plan.pdf PDF
Enclosure 3 Financial Capability Assessment (SEPT) 2020.pdf PDF
Exhibit 8 - PPQ_9.20.23_FINAL.pdf PDF
Attachment D-418-XO-GIRD-0041_V_2_4.pdf PDF
Attachment E-418-XO-PRAD-0037_V_1_6.pdf PDF
Attachment F-3-418-XO-GXSUIID-0030_V_1_6a.pdf PDF
Attachment F-6-418-XO-PTRUIID-0141_V_1_0.pdf PDF
Attachment G-2-418-XO-IRD-0043_V_1_4.pdf PDF
Attachment H-418-XO-SCMAR-0083_V_2_0-final (003).pdf PDF
Attachment L-GeoXO_ConOps_v1-0-final.pdf PDF
Attachment S - OCI Plan DRD.pdf PDF
Attachment T - Organizational Conflict of Interest Plan.pdf PDF
Attachment W -Diversity-Equity- Inclusion and Accessibility Plan.pdf PDF
Attachment AA- Safety and Health Plan.pdf PDF
Enclosure 2 -418-XO-PLN-0109 GeoXO QASP FINAL V2.0 RO.pdf PDF
Attachment F-4-418-XO-OCXUIID-0062_V_1_7.pdf PDF
Attachment K-418-XO-RPT-0045-FPGA 1.0.pdf PDF
Attachment A-418-XO-SCSOW-0122_V_1_0_final.pdf PDF
Attachment J-418-XO-RPT-0039_V_1_0.pdf PDF
Attachment N-Spacecraft Final RFP WBS dictionary 9-1-23cc.pdf PDF
Attachment U RESERVED.pdf PDF
Attachment Y - IT Security Management Plan.pdf PDF
Attachment Z- Information Technology (IT) Security Applicable Doc List docx.pdf PDF
Attachment AC -Government Furnished Property.pdf PDF
Enclosure 1 GeoXO SC Draft PEP Sept 2023.pdf PDF
GeoXO Spacecraft Cost Exhibits 1-7 September 2023.pdf PDF
Show all 46

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GeoXO Spacecraft Final RFP Questions and Answers #2

Question:

In table of Section A (2), VOSB goals are set at 0.2% and SDVOSB goals are set at

1.5%. SDVOSB goals are a subset of VOSB goals, and therefore cannot be higher than VOSB. Can you confirm these socio-economic goals in FRFP are accurate?

Answer:

Section L.12 is Electronic Submission of Proposals and (C) is the submittal address.

Assuming you are referring to L.13. The information provided is incorrect. The table at A.2 will be updated as follows:

Small Businesses (SB) 15.4%

Small Disadvantaged Business (SDB) Concerns 1.8%

Women-Owned Small Business (WOSB) Concerns 1.2%

HUBzone 0.2%

Veteran-Owned Small Business (VOSB) Concerns 1.5%

Service-Disabled Veteran-Owned Small Business (SDVOSB) Concerns 0.2%"

Question:

The Proposal Content and Page Limitations table in L.10(b) indicates that

Appendix A for block diagrams for the Spacecraft Design is limited to 20 pages.

Please confirm that the 20-page Appendix A is outside of the 150 pages for the

Mission Suitability volume.

Answer:

The 20 pages for Appendix A for block diagrams for the Spacecraft Design are outside of the 150 pages for Mission Suitability.

Question:

The Proposal Content and Page Limitations table in L.10(b) requests an Acronym

List in the Past Performance volume that is excluded from page limit/page count.

1) Would the government permit acronym lists to be included with the other volumes to support evaluation and context for the material?

2) Would the government permit these acronym lists for the other volumes to be similarly excluded from page limit/page count?

Answer:

Yes, the Government agrees with providing acronym lists in each volume and yes, the acronym lists are excluded from the page count.

Question:

SCSOW809 is showing 3 Dual Sided testbeds while also stating which SHS require decryption and intermediate frequency capabilities. This is in contrast to

SCFPS500, SCFPS806, and SCFPS563 in the functional performance spec that intimate that only a single SHS requires these capabilities. Recommend removing

SCFPS500, 806, and 563 as they are non-functional requirements that are in conflict with the SOW.

Answer:

The F&PS requirement state "an instantiation" which is equivalent to configuration. In this case, instantiation in the F&PS does not dictate the quantity. The quantity of each instantiation is dictated in the SOW.

Question:

In the latest MEL template, the % New Design Column is highlighted. Is the column to be removed? If it does remain, can additional guidance be provided on the expected content?

Answer:

No, this column should not be removed - this column should be filled out for the proposal. There is no significance to the highlight. The entry in this column should reflect the percentage of the hardware and software that is a "New" design. A

"New" design requires Non-Recurring Engineering or has not been flown before.

Please provide percentages for the amount of new hardware and new software

(only if applicable) separately.

Question:

Within Appendix C Mission Assurance Compliance Matrix, directions state to

“Indicate the method used to verify compliance (Inspection, Test, Analysis, Demonstration)”. Would it be possible to get definitions of those verification methods? Many Mission Assurance requirements are verified or setup through procedure documentation and it is not entirely clear which selection one would use for that option.

Answer:

Per the NASA Systems Engineering Handbook:

1. Inspection: The visual examination of a realized end product. Inspection is generally used to verify physical design features or specific manufacturer identification. For example, if there is a requirement that the safety arming pin has a red flag with the words “Remove Before Flight” stenciled on the flag in black letters, a visual inspection of the arming pin flag can be used to determine if this requirement was met.

2. Test: The use of a realized end product to obtain detailed data to verify or validate performance or to provide sufficient information to verify or validate performance through further analysis.

3. Analysis: Use of mathematical modeling and analytical techniques to predict the compliance of a design to its requirements based on calculated data or data derived from lower system structure end product validations.

4. Demonstration: Showing that the use of an end product achieves the individual specified requirement (verification) or stakeholder expectation (validation). It is generally a basic confirmation of performance capability, differentiated from testing by the lack of detailed data gathering. Demonstrations can involve the use of physical models or mock-ups; for example, a requirement that all controls shall be reachable by the pilot could be verified by having a pilot perform flight-related tasks in a cockpit mock-up or simulator. A demonstration could also be the actual operation of the end product by highly qualified personnel, such as test pilots, who perform a one-time event that demonstrates a capability to operate at extreme limits of system performance.

Answer:

The spreadsheet is correct as written. The correct number is 20.5. The vendor may be looking at old version of C3SIRD. The document has been updated.

SAM.gov has the correct version posted. The version on SAM.gov matches the spreadsheet as follows:

End Questions and Answers #2