Specification 34 73 13 Aircraft Tiedowns.pdf
PDF 12 KB Posted
- Solicitation number
- 80GSFC22B0004
About this file
This solicitation is for a firm fixed price construction contract to perform repairs at Wallops Airfield in Virginia. The scope of work includes Portland cement concrete spall repairs, full depth repairs, full slab replacements, crack sealing, joint sealing, and asphalt concrete seal coating. A site visit is scheduled for August 11th where attendees must RSVP by August 5th. Electronic bids are due by August 30th and will be opened publicly via Microsoft Teams on the same date. Questions about the solicitation are due by August 12th. The solicitation is being conducted by the National Aeronautics and Space Administration Goddard Space Center to focus on routine maintenance recommendations from a 2018 airfield pavement condition report.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FCLP Phase 9 - Wallops Flight Facility 1696789
SECTION 34 73 13
AIRCRAFT TIEDOWNS
11/19
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN WELDING SOCIETY (AWS)
AWS D1.4/D1.4M (2011) Structural Welding Code - Reinforcing Steel
ASTM INTERNATIONAL (ASTM)
ASTM A615/A615M (2020) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
NATIONAL INSTITUTE FOR OCCUPATIONAL SAFETY AND HEALTH (NIOSH)
NIOSH 81-123 (1981) Occupational Health Guideline for Chemical Hazards, (Vols. I, II, and III)
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
As-Built Drawings; G
SD-06 Test Reports
Concrete; G
SD-07 Certificates
Mooring Devices
Reinforcing Steel
1.3 AS-BUILT DRAWINGS
Submit as-built drawings that provide current factual information, including deviations from and amendments to the drawings and changes in the work, concealed and visible.
SECTION 34 73 13 Page 1
FCLP Phase 9 - Wallops Flight Facility 1696789
PART 2 PRODUCTS
2.1 MATERIALS
Do not use a combination of materials that forms an electrolytic couple, which accelerates corrosion in the presence of moisture, unless moisture is permanently excluded from the junction of such metals.
2.2 MOORING DEVICES
2.3 CONCRETE
Submit complete concrete mix design including all cement, aggregate, and concrete tests and compliance certificates. Use concrete in accordance with Section 32 13 14.4 CONCRETE PAVING FOR SMALL AIRFIELD PROJECTS.
2.4 REINFORCING STEEL
Use reinforcing steel in accordance with ASTM A615/A615M Grade 40 or 60 for #4 tie bars and Grade 60 for #6 vertical bars. Weld steel into cages in accordance with AWS D1.4/D1.4M and insert securely in the piers, in position and alignment, as shown in the drawings, prior to concrete placement. Submit certificates of compliance stating that the reinforcing steel meets the specified requirements.
PART 3 EXECUTION
3.1 MOORING POINTS IN NEW RIGID PAVEMENTS OR CONCRETE PADS
Install the mooring device within plus or minus 4 in of the location in existing slab to be demolished. Set the top of the mooring device within 1/4 in of the plan pavement surface elevation, but not higher than the pavement surface. Install the mooring device prior to placement of the concrete pavement. . Keep hand finishing of the concrete around the mooring devices to a minimum.
3.2 SAFETY
In addition to Safety Requirements contained in the Contract Clauses;
prevent employee respiratory, eye or skin contact with Portland cement.
Provide and require employees to use and dispose or clean the following in accordance with the provisions of the National Institute for Occupational Safety and Health NIOSH 81-123:
a. Impervious clothing, boots, and gloves.
b. Splash-proof safety goggles and face shields.
c. Respiratory protection equipment.
-- End of Section --
SECTION 34 73 13 Page 2
File details come from the government source that posted it. Updated .