Specification 32 01 17.61 Sealing Cracks in Asphalt Paving.pdf

PDF 21 KB Posted

Attached to
Wallops Airfield Repair Project, Field Carrier Landing Practice (FCLP) Phase 9
Solicitation number
80GSFC22B0004
Issued by

About this file

This document outlines a federal contract opportunity for repair work at Wallops Airfield. NASA intends to award a firm fixed price construction contract for repairs to Portland cement concrete and asphalt surfaces at runways, taxiways, and aircraft parking ramps at Wallops Flight Facility. The scope of work includes spall repairs, full depth repairs, slab replacements, crack sealing, joint sealing and asphalt seal coating. A site visit is scheduled for August 11th, with attendees requiring badge access to be submitted by August 5th. Electronic bids are due by August 30th at 12:00 PM Eastern with bid opening taking place via Microsoft Teams at 2:00 PM Eastern on the same day. Questions regarding the solicitation must be submitted in writing by August 12th.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FCLP Phase 9 - Wallops Flight Facility 1696789

SECTION 32 01 17.61

SEALING CRACKS IN ASPHALT PAVING

05/17

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C509 (2006; R 2021) Standard Specifiaction for Elastomeric Cellular Preformed Gasket and Sealing Material

ASTM D789 (2015) Determination of Relative Viscosity and Moisture Content of Polyamide (PA)

ASTM D6690 (2015) Standard Specification for Joint and Crack Sealants, Hot Applied, for Concrete and Asphalt Pavements

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Installation of Sealant

SD-04 Samples

SD-06 Test Reports

Laboratory Tests

1.3 QUALITY ASSURANCE

Test the crack sealant and backup material, when required, for conformance with the referenced applicable material specification. Perform testing of the materials in an approved, independent laboratory; submit certified copies of the test reports for approval 60 days prior to the use of the materials at the job site. Costs of the tests will be borne by the Contractor. Submit reports of all tests. Samples will be retained by the Government for possible future testing, should the materials appear defective during or after application. Furnish samples of materials, in sufficient quantity to be tested upon request. Conformance with the test requirements of the laboratory tests specified will not constitute final

SECTION 32 01 17.61 Page 1 acceptance of the materials. Final acceptance will be based on the performance of materials that have been satisfactorily installed.

1.4 DELIVERY, STORAGE, AND HANDLING

Inspect materials delivered to the job site for defects; unload, and store them with a minimum of handling to avoid damage. Provide storage facilities at the job site to protect materials from weather and maintain them at the temperatures recommended by the manufacturer.

1.5 EQUIPMENT, TOOLS, AND MACHINES

Equipment, tools, and machines used in performance of the work are subject to approval by the Contracting Officer. Maintain in a satisfactory working condition at all times.

1.5.1 Routing Equipment

Provide routing equipment which is a self-powered machine operating a power driven tool or bit specifically designed for routing bituminous pavements.

Use a bit rotating about a vertical axis at sufficient speed to cut a smooth vertical-walled reservoir in the pavement surface and maintain accurate cutting without damaging the sides or top edges of the reservoir.

Provide a router capable of following the trace of the crack without deviation. The use of rotary impact routing devices may be permitted if vertical-sided carbide tipped bits are used.

1.5.2 Concrete Saw

Provide a self-propelled power saw with small diameter ( 6 inches or less) water-cooled diamond or abrasive saw blades for cutting cracks to the depths and widths specified and for removing filler that is embedded in the cracks or adhered to the crack faces. Use a saw blade with a diameter small enough to allow the saw to closely follow the trace of the crack.

1.5.3 Waterblasting Equipment

Include with the waterblasting equipment a trailer-mounted water tank, pumps, high-pressure hose, wand with safety release cutoff control, nozzle, and auxiliary water resupply equipment. Use water tank and auxiliary resupply equipment with sufficient capacity to permit continuous operations. Use hoses, wands, and nozzles capable of cleaning the crack faces and the pavement surface on both sides of the crack for a width of at least 1/2 inch beyong the crack. Use pump with a mounted pressure gauge that shows the pressure in psi at which the equipment is operating at all times. Limit the pressure so that the sides of the crack are not damaged during the cleaning operation.

1.5.4 Hand Tools

Hand tools may be used, when approved, for removing defective sealant from cracks and repairing or cleaning the crack faces.

1.5.5 Crack Sealing Equipment

Provide unit applicators, used for heating and installing the hot-poured crack sealant materials, that are mobile and equipped with a double-boiler, agitator-type kettle with an oil medium in the outer space for heat transfer; a direct-connected pressure-type extruding device with a nozzle

SECTION 32 01 17.61 Page 2 shaped for inserting in the crack to be filled; positive temperature devices for controlling the temperature of the transfer oil and sealant;

and a recording type thermometer for indicating the temperature of the sealant. Allow the sealant to circulate through the delivery hose and return to the inner kettle when not in use, due to the applicator unit design.

1.6 ENVIRONMENTAL REQUIREMENTS

Apply the materials only when the ambient air temperature and the pavement temperature within the joint wall are at least 50 degrees F and rising.

Do not apply sealant if moisture is observed in the crack.

PART 2 PRODUCTS

2.1 SEALANTS

Provide sealants conforming to ASTM D6690, Type II or ASTM D6690, Type I.

2.2 BACKER ROD MATERIALS

Provide backer rod material that is a compressible, nonshrinking, nonstaining, nonabsorptive material and nonreactive with the crack sealant. Use backer rod with a melting point temperature of at least 5 degrees F greater than the maximum pouring temperature of the sealant being used, when tested in accordance with ASTM D789. Use material that has a water absorption of not more than 5 percent by weight when tested in accordance with ASTM C509. Use backer rod material that is 25 percent (plus or minus 5 percent) larger in diameter than the nominal width of the crack.

PART 3 EXECUTION

3.1 PREPARATION OF CRACKS

Immediately before the installation of the crack sealant, thoroughly dry and clean the cracks to remove oxidized pavement, loose aggregate and foreign debris. Prepare cracks as follows:

3.1.1 Cracks

3.1.1.1 Hairline Cracks

Cracks that are less than 1/4 inch wide do not need to be sealed.

3.1.1.2 Small Cracks

Route cracks that are 1/4 to 3/4 inch wide to a nominal width 1/8 inch greater than the existing nominal width and to a depth not less than 3/4 inch, waterblasted and cleaned and dried using compressed air.

3.1.1.3 Medium Cracks

Waterblast cracks that are 3/4 to 2 inches wide and clean and dry using compressed air.

SECTION 32 01 17.61 Page 3

3.1.1.4 Large Cracks

Repair cracks that are greater than 2 inches wide shall be milled and patched.

3.1.2 Existing Sealant Removal

3.1.3 Routing

Perform routing of the cracks using a rotary router with a bit that is at least 1/8 inch wider than the nominal width of the crack to remove all residual old sealant (resealing), oxidized pavement and any loose aggregate in the crack wall.

3.1.4 Sawing

Perform sawing of the cracks using a power-driving concrete saw as specified in paragraph EQUIPMENT, TOOLS, AND MACHINES. Stiffen the blade as necessary with suitable dummy (or used) blades or washers. Immediately following the sawing operation, clean the crack opening using a water jet to remove all saw cuttings and debris.

3.1.5

Waterblast clean the crack faces and the pavement surfaces extending a minimum of 1/2 inch from the crack edges. Use a multiple-pass technique until the surfaces are free of dust, dirt, old sealant residue, or foreign debris that might prevent the sealant material from bonding to the asphalt pavement. After final cleaning and immediately prior to sealing, blow out the cracks with compressed air and leave them completely free of debris and water. Ensure that waterblasting does not damage the pavement.

3.1.6 Backer Rod Material

When required, use backer rod material in all cracks that otherwise would require excessive sealant. Insert the backer rod material into the lower portion of the crack as shown on the drawings. Place the backer rod so that the top of the backer rod is at least 3/4 inch below the top of the pavement. Ensure that the backer rod material is placed at the specified depth and is not stretched or twisted during installation.

3.1.7 Rate of Progress of Crack Preparation

Limit the stages of crack preparation, which include routing, sandblasting of the crack faces, air pressure cleaning and placing of the backer rod material, to only that linear footage that can be sealed during the same day.

3.2 PREPARATION OF SEALANT

Do not heat hot-poured sealants in excess of the safe heating temperature recommended by the manufacturer, as shown on the sealant containers.

Withdraw and waste sealant that has been overheated or subjected to application temperatures for over 4 hours or that has remained in the applicator at the end of the day's operation.

SECTION 32 01 17.61 Page 4

3.3 INSTALLATION OF SEALANT

Submit manufacturer's instructions 10 days prior to the use of the material on the project. Installation of the material will not be allowed until the instructions are received.

3.3.1 Time of Application

Seal cracks immediately following final cleaning and drying of the crack walls and following the placement of the backer rod material (when required). Place sealant only when cracks are dry. Reclean cracks that cannot be sealed under the conditions specified, or when rain interrupts sealing operations, and allow to dry or dry by machanical means prior to installing the sealant.

3.3.2 Sealing the Crack

Immediately preceding, but not more than 50 feet ahead of the crack sealing operations, perform a final cleaning and drying with compressed air. Fill the cracks from the bottom of reservoir formed by the routing or the top of the backer rod up to 1/8 inch below the pavement surface. Remove excess or spilled sealant from the pavement by approved methods and discard it.

Install the sealant in a manner which prevents the formation of voids and entrapped air. Several passes with the applicator wand may be necessary to obtain the specified sealant depth from the pavement surface. Do not use gravity methods or pouring pots to install the sealant material. Do not permit traffic over newly sealed pavement until authorized by the Contracting Officer. Check cracks frequently to ensure that the newly installed sealant is cured to a tack-free condition within 3 hours.

Immediately notify the Contracting Officer of the location of any sealant that has not cured to a tack-free condition within 3 hours.

3.4 CRACK SEALANT INSTALLATION TEST SECTION

Prior to the cleaning and sealing of the cracks for the entire project, construct a test section at least 200 feet long using the specified materials and approved equipment to demonstrate the proposed sealing of all cracks of the project. Following the completion of the test section and before any other crack is sealed, inspect the test section to determine that the materials and installation meet the requirements specified. If materials or installation do not meet requirements, remove the materials and reclean and reseal the cracks at no cost to the Government. When the test section meets the requirements, it may be incorporated into the permanent work and paid for at the contract unit price per linear foot for sealing items scheduled. Seal all other cracks in the manner approved and sucessfully completed for sealing the test section.

3.5 CLEANUP

Upon completion of the project, remove unused materials from the site and leave the pavement in a clean condition.

3.6 QUALITY CONTROL PROVISIONS

3.6.1 Crack Cleaning

Provide quality control provisions during the crack cleaning process to correct improper equipment and cleaning techniques that damage the bituminous pavement in any manner. Cleaned cracks must be approved by the

SECTION 32 01 17.61 Page 5

Contracting Officer prior to installation of the crack sealant.

3.6.2 Crack Seal Application Equipment

Inspect the application equipment to ensure conformance to temperature requirements and proper installation. Evidences of bubbling, improper installing, and failing to cure or set will cause to suspend operations until causes of the deficiencies are determined and corrected.

3.6.3 Crack Sealant

Inspect the crack sealant for proper cure and set rating, tack free surface, bonding to the bituminous pavement, cohesive separation within the sealant, reversion to liquid, and entrapped air and voids. Remove sealants exhibiting any of these deficiencies, at any time prior to the final acceptance of the project, and replace as specified herein at no additional cost to the Government.

-- End of Section --