This document provides details for a solicitation to award a firm fixed price construction contract for repairs at Wallops Airfield in Virginia. The scope of work includes Portland cement concrete spall repairs, full depth repairs, full slab replacements, crack sealing, joint sealing, and asphalt concrete seal coating. The repairs focus on routine maintenance recommendations from a 2018 airfield pavement condition survey. Work will be performed on runways, taxiways, and an east ramp area and includes furnishing equipment, labor, materials, and services. A site visit is scheduled for August 11th with a bid submission deadline of August 30th. Questions are due by August 12th and bidders must monitor the system for any amendments. The contract will be awarded by the National Aeronautics and Space Administration Goddard Space Center.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Continuation Page SF-30 Amendment 002
80GSFC22B004
A. Invitation for Bid (IFB), Section J, Clause J.1 GSFC 52.211-101 LIST OF ATTACHMENTS (FEB 2016) is hereby revised to incorporate Attachment G, entitled, “Wallops Airfield Repair Project FCLP Phase 9 Sketch 1 & Sketch 2” dated 8/11/2022. ‘
Clause J.1 is hereby modified as follows (change in BOLD):
Attachments Description Date No. of Pages
A Wallops Airfield Repair Project, FCLP, Phase 9 Statement of Work
7/1/2022 5
B Wallops Airfield Repair Project, FCLP Phase 9 Specifications
5/26/2022 333
C Wallops Airfield Repair Project, FLCP, Phase 9Drawings for Runway 10-28, D-1 Apron
5/26/2022 25
D Davis Bacon Wage Determination General Decision No. VA220095
02/25/2022 6
E Contractor’s Daily Report, Form WI 452
Not Dated 3
F Safety and Health Plan TBS* TBS*
G Wallops Airfield Repair Project FCLP Phase 9 Sketch 1 & Sketch 2
8/11/2022 2
TBS* = To Be Submitted within 30 days after award. Once approved, will be incorporated by separate modification.
(End of clause)
Continuation Page SF-30 Amendment 002
80GSFC22B004
B. Attachment B, entitled, “Wallops Airfield Repair Project, FCLP Phase 9 Specifications”, is hereby revised to incorporate the following Specifications:
1. Specification 32 01 17.61 “Sealing Cracks in Pavement”
2. Specification 32 13 14.14 “Concrete Paving for Small Airfield Projects”
3. Specification 34 73 13 “Aircraft Tiedowns”
4. Specification 34 73 16 “Airfield Grounding”
5. Submitted Register
C. Attachment G, entitled, “Wallops Airfield Repair Project FCLP Phase 9 Sketch 1 & 2”, is hereby incorporated.
D. The Government responses to questions are provided under Amendment 002, ATTACHMENT 1: Wallops Airfield Repair Project, FCLP Phase 9, Invitation for Bid (IFB) 80GSFC22B0004, Pre-Bid Questions and Responses.
E. A copy of the Site Visit Agenda and List of Participants are hereby provided.
--End of Amendment 002--