This is Amendment A00007 to Solicitation 75H701-25-R-00002 for the Parker Duplex Quarters project issued by the Indian Health Service Division of Engineering Services in Seattle. The amendment provides responses to two pre-proposal inquiries dated December 20, 2024.
The amendment clarifies specifications for bedroom closet installations, requiring 3/4" particle board shelves with bullnose edges, solid wood cleats and dowels, and specific hardware requirements including KV Pro BC-0037 White rod sockets and KV 1195 White shelf/rod brackets. It also provides guidance regarding Factor 4 (Indian Economic Enterprise Representation), directing offerors to demonstrate how the prime firm will receive the majority of earnings from the contract. The amendment does not extend the proposal due date of 11/18/2024.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
A00007
N/A
KELLY J. BRITTON
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Project PH21CR03Q3, Parker Duplex Quarters
Amendment A00007 is issued to provide a response to pre-proposal inquiries #37 - #38.
SEE CONTINUATION PAGES
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
Indian Health Service Division of Engineering Services (DES) - Seattle 701 5th Ave, Suite 1600 Seattle, WA 98104
See Block 6
75H701-25-R-00002
PH21CR02Q3
1 2
12/20/2024
11/18/2024
Amendment of Solicitation Amendment A00007 under Solicitation 75H701-25-R-00002 Project PH21CR03Q3, Parker Duplex Quarters
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-25-R-00002
PROJECT: Parker Duplex Quarters LOCATION: Parker AZ
PROJECT NO: PH21CR03Q3
DOCUMENT
OWNER: Kelly Britton PHONE: 602-364-5081 DOCUMENTS:
DATE: 12/20/2024 DEPARTMENT: IHS/PAO/DFE
Item No.
Reference Drawing, Spec, Page COMMENTS POC IHS Approved Response
Amendment A00007 dated 12/20/2024
37. A2.0
Keynote
Keynote 110 calls for rod & shelf in closets and to refer to spec on A2.0. I could not locate the spec for rod & shelf.
− Is the shelf to be ¾” Particle board w/ bullnose edge to match the linen shelves?
− Is shelf to be installed on cleat or in wall mounting?
− Is the rod to be metal or wood?
− Is rod to be hung within end cap or have supports?
− If supports are used how many? Please provide a spec and detail for closet install.
COR/
BWS
At each bedroom closet, furnish and install ¾” particle board shelf with bullnose edge, full width, 14” deep, at 6’-0”AFF. Provide continuous solid wood cleat at sides and back, continuous solid wood dowel 1 3/8” D, with rod socket (KV Pro BC-0037 White or equal) at each end, and intermediate shelf/rod bracket (KV 1195 White or equal) equally spaced at 3’-0”OC maximum.
38. It is not clear what information you would like us to provide for Volume 1, FACTOR 4: Indian Economic Enterprise Representation, Part 2. Can you please provide clarification around what you are looking for?
CO Provide supporting information that demonstrates how the prime firm will receive the majority of the earnings (profit or net income) from the contract.
| B04 Pre-Proposal Inquiries 37-38 (25R00002).pdf |
| Solicitation 75H701-25-R-00002 does not include the liquidated damages clause at FAR 52.211-12 Liquidated Damages-Construction. |
| Contractor may use utility water by connecting to the existing 4” water line running along the street. |
| Note that a “hot tap” using a tapping sleeve and gate valve will be required, as there are no shutoff valves in the immediate area. Contractor must also install a backflow prevention valve to prevent contaminated water from flowing back into the main water supply. |
| Notify local utility (BIA) and adhere to any guidance they may issue regarding water use and metering. As the Indian Health Service is paying for the water, it is likely that BIA will only charge a connection fee. |
| The BIA point of contact is Steve McVeigh at (928) 916-2186. |