This is Amendment A00001 to solicitation 75H701-25-R-00002 for the Parker Duplex Quarters construction project in Parker, Arizona. The amendment extends the period of performance from 150 to 240 calendar days after notice to proceed, provides responses to three pre-proposal inquiries, and includes an updated SF1442 form reflecting the revised timeline.
Key details from the amendment include: clarification that appliances and FFE Package items will be procured outside this solicitation; confirmation that Joint Venture partners do not need shared past performance experience but must submit relevant experience for all JV partners; and maintenance of the original proposal due date of January 7, 2025 at 2:00pm MST. The project remains a 100% Indian Small Business Economic Enterprise (ISBEE) set-aside under NAICS code 236116 with a size standard of $45 million. The construction magnitude is estimated between $1-5 million. The Indian Health Service Division of Engineering Services in Seattle is the issuing agency, with Kelly Britton serving as the point of contact.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
A00001
N/A
KELLY J. BRITTON
Project PH21CR03Q3, Parker Duplex Quarters
Amendment A00001 is issued to provide responses to pre-proposal inquiries #1-3, extend the period of performance FROM "150" TO "240" calendar days and to revise clause F.2. FAR 52.211-10 Commencement, Prosecution And Completion Of Work Included in this amendment is an updated SF1442, updating Block 11.
SEE CONTINUATION PAGES
Indian Health Service Division of Engineering Services (DES) - Seattle 701 5th Ave, Suite 1600 Seattle, WA 98104
See Block 6
75H701-25-R-00002
PH21CR02Q3
1 5
12/01/2024
11/18/2024
Amendment of Solicitation Amendment A00001 under Solicitation 75H701-25-R-00002 Project PH21CR03Q3, Parker Duplex Quarters
SUMMARY OF CHANGES
1. The purpose of Amendment A00001 is to provide responses to pre-proposal inquiries #1-3, extend the period of performance FROM “150” TO “240” calendar days and to revise clause F.2. FAR 52.211-10 Commencement, Prosecution And Completion Of Work as follows:
a. The responses to pre-proposal inquiries #1-3 are attached. Additional inquiries will be provided in a forthcoming amendment.
b. SF 1442, Block 11 is hereby changed FROM “150” TO “240” calendar days. Included in this amendment is an updated SF1442, updating Block 11.
c. Section F – Deliveries Or Performance, clause F.2. FAR 52.211-10 Commencement, Prosecution And Completion Of Work is changed to read as follows (changes in red):
F.2. FAR 52.211-10 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than *240 calendar days after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
* The period of performance above includes pre-construction activities (i.e., submittals, ordering long lead materials, etc).
(End of clause)
2. The proposal due date of January 7, 2025 remains unchanged.
END OF SUMMARY OF CHANGES
Amendment of Solicitation Amendment A00001 under Solicitation 75H701-25-R-00002 Project PH21CR03Q3, Parker Duplex Quarters
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-25-R-00002
PROJECT: Parker Duplex Quarters LOCATION: Parker AZ
PROJECT NO: PH21CR03Q3
DOCUMENT
OWNER: Kelly Britton PHONE: 602-364-5081 DOCUMENTS:
DATE: 12/1/2024 DEPARTMENT: IHS/PAO/DFE
Item No.
Reference Drawing, Spec, Page COMMENTS POC IHS Approved Response
Amendment A00001 dated 12/01/2024
1. Within the specs is list Division 11 as “Not Used” and the interior elevations call out appliances but refer me to the “FFE Package” which I can not find in any of the documentation provided. Are the appliances to be furnished and installed by the owner?
COR Yes, all work pertaining to the FFE Package will be procured outside of this solicitation and resulting contract.
2. The 150 day performance period is extremely short for a project of this magnitude. A project of this size will take at a minimum 6 months (180 days) to complete onsite. That time does not include the time it will take for pre construction submittals. We’d like to request an extension to the performance period to at least 240 days. If that is not an option, when does the IHS anticipate issuing NTP for this project? Could we request a delayed NTP to ensure that this project is completed within the performance period? For example, we have had Federal Customers issue partial NTP’s to get the pre construction submittals completed, then an NTP right before construction begins.
COR/
CO
Amendment A00001 extends the period of performance from 150 to 240 calendar days.
3. Is it a requirement for a Joint Venture company to have completed past projects together, or is it acceptable to have one member of the Joint Venture to have the past performance history to meet the requirements for the project’s bid?
CO Reference L.12, (1) VOLUME I - TECHNICAL PROPOSAL, FACTOR 1: Specialized Experience, (c) “If the Offeror is a Joint Venture (JV), relevant experience should be submitted by that JV entity. If the JV does not have shared experience, projects shall be submitted for each JV partner relevant to their overall JV partnership.
Offerors who fail to submit experience for all JV partners may be evaluated as “UNACCEPTABLE.”
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR
INFORMATION CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF PAGES
75H701-25-R-00002
Indian Health Service Division of Engineering Services (DES) - Seattle 701 5th Ave, Suite 1600 Seattle, WA 98104
Project: PH21CR03Q3, Parker Duplex Quarters
Location: Parker Indian Health Center, 12033 Agency Road, Parker, AZ 85344
See Section L for Proposal Submittal Instructions and Site Visit Information.
This project will be procured as a 100% Indian Small Business Economic Enterprise (ISBEE) set-aside under North American Industry Classification System (NAICS) code 236116, New Multifamily Housing Construction (except For-Sale Builders). The associated size standard for this procurement is $45 million.
CONSTRUCTION MAGNITUDE: The magnitude of this construction project is anticipated to be between $1,000,000 and $5,000,000, in accordance with FAR 36.204(f).
Indian Health Service, Phoenix Area OEHE Attn: Kelly Britton 40 N. Central Ave., Suite 720 Phoenix, AZ 85004-4424
Kelly Britton (602) 364-5081 or kelly.britton@ihs.gov
PH21CR03Q3
1 5611/18/2024
1/7/2025
2:00pm MST
10 days after award
F.2. FAR 52.211-10
AWARD (To be completed by Government)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES
CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
B.3.
Indian Health Service, DES - Seattle 701 5th Ave, Suite 1600 Seattle, WA 98104
Indian Health Service Attn: Financial Management 40 N Central Avenue, Suite 512 Phoenix, AZ 85004
KELLY J. BRITTON
LUMP SUM TOTAL $________________