Attachment J25 - Buildings 5 and 6 Asbestos Survey.pdf
PDF 847 KB Posted
- Solicitation number
- 75H701-23-R-00001
About this file
This document is an asbestos survey report for Buildings 5 and 6 at the Phoenix Indian Medical Center campus. The report identifies various asbestos-containing materials found throughout the buildings including floor tiles and mastics, wall textures, drywall joint compounds, and window putty. Laboratory testing confirmed the presence of asbestos in these materials. The report provides the locations and quantities of the asbestos-containing materials and notes most are in good condition. It includes an abatement cost estimate and liability limitations. Appendices include sampling logs, laboratory results, and inspector certifications.
The related federal contract opportunity is a solicitation for maintenance and improvement renovations at the Phoenix Indian Medical Center. The work includes abatement of asbestos materials identified in the survey report along with other projects like mechanical HVAC improvements, interior and exterior painting, roof replacement, fire alarm and sprinkler work. The performance period is 300 days with anticipated value between $1 million to $5 million. The solicitation will use LPTA evaluation and result in a firm fixed price contract with the Indian Health Service.
View the file
Other files
Show 40 more
Latest 50 of 53 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ASBESTOS SURVEY
At
PHOENIX INDIAN MEDICAL CENTER
Building #5 & 6 – Office
For
Phoenix Area Indian Health Service Two Renaissance Square
40 N. Central Avenue Phoenix, AZ 85004
By
U.S. Public Health Service Federal Occupational Health
2201 Sixth Avenue, M/S Rx-21 Seattle, Washington 98121-2500
(206) 615-2441
February 2003
Attachment J25 - Buildings 5 & 6 Asbestos Survey
TABLE OF CONTENTS
Section Title Page No.
1.0 Introduction
2.0 Description of Inspected Area
3.0 Survey Procedures
4.0 Findings
5.0 Abatement Cost Estimate
6.0 Liability Limitations
Appendices
1 Bulk Sample Log and Location of Functional Spaces
2 Laboratory Results
3 Certifications
Area Wide Asbestos Building Inspection Indian Health Service Facilities
Phoenix Indian Medical Center Campus Building #5 & 6 – Office
Phoenix, Arizona
1.0 INTRODUCTION
As requested by the Phoenix Area Indian Health Services, bulk sampling of suspect asbestos-containing building materials was conducted in Building #5 & 6, Office, at the Phoenix Indian Medical Center (PIMC) at 4212 North 16th Street in Phoenix, Arizona, on August 1, 2002. Bulk samples of suspect asbestos-containing materials (ACMs) were collected throughout the interior and exterior of the building.
Messrs. Mark Updike and James Marshall, representing Federal Occupational Health (FOH), performed the asbestos inspection of the subject property. Messrs. Updike and Marshall both hold current Asbestos Hazard Emergency Response Act (AHERA) accreditation as Asbestos Building Inspectors. Sampling of suspect asbestos-containing materials was conducted using procedures similar to the Environmental Protection Agency (EPA) AHERA regulations, 40 CFR 763. The Federal Occupational Health EH Environmental Laboratory in Denver, Colorado, performed the laboratory analysis of the asbestos samples.
Laboratory analysis indicates that floor tiles, floor tile mastics, wall texture, drywall joint compound, and window putty in Buildings #5 & 6, Office, contain asbestos.
2.0 DESCRIPTION OF INSPECTED AREA
This inspection focused on the entire interior and exterior of the building. The building is single story with a stucco exterior built slab-on grade. The roof consists of both a composite shingle and ceramic shingle roofing system.
Suspect building materials identified and sampled in the subject property included the following: Various floor tiles and associated mastics, various gypsum drywall materials, plaster wall materials, leveling compounds, cove base mastic, acoustical ceiling tiles and associated mastic, exterior stucco, window putty, and roofing materials.
3.0 SURVEY PROCEDURES
Each room was assigned unique functional space numbers. Each functional space was visually inspected for suspect asbestos-containing materials. Materials were mapped and quantified on maps provided by the IHS or on hand made maps of the existing floor plan.
Each suspect ACM was designated as a distinct homogeneous area, which is a single material, uniform in texture and appearance, installed at one time, and unlikely to consist of more than one type or formulation of material. The inspectors touched each suspect material in order to determine friability.
A sufficient number of samples were collected of each material to satisfy the Occupational Safety and Health Administration (OSHA) and the National Emission Standard for Hazardous Air Pollutants (NESHAP) regulations for the determination of asbestos content. A total of 84 samples were collected from Buildings #5 & 6.
Each sample was assigned a unique sample identification number and assessed for damage and friability classifications. The samples, with Chain of Custody documentation were delivered to FOH EH
Environmental Laboratory for analysis. The FOH EH Environmental Laboratory is accredited under the National Voluntary Laboratory Accreditation Program (NVLAP) for bulk-asbestos sample analysis conducted by the National Institute of Standards and Technology.
A description of the samples taken, location, and summary of laboratory results are located in Appendix 1.
The asbestos laboratory reports are included as Appendix 2.
4.0 FINDINGS
Results of the asbestos inspection are as follows:
Phoenix Indian Medical Center Building #5 & 6 – Office
HA # Material Functional Space ACM Condition Quantity 1A 12”x12” Floor
Tile & Mastic 1-34 Yes: 10-12%
Chrysotile Black Mastic
Good 5,241 sf
1B 12”x12” Floor Tile & Mastic
17-29 Yes: 10-12% Chrysotile
Good 2,011 sf
1C 12”x12” Floor Tile & Mastic
17-29 Yes: 12-15% Chrysotile
Good 2,011 sf
1D 12”x12” Floor Tile & Mastic
31, 32, 34 Yes: 8-10% Chrysotile
Good 853 sf
1E 12”x12” Floor Tile & Mastic
31, 34 Yes: 12-14% Chrysotile
Good 772 sf
1F 12”x12” Floor Tile & Mastic
32, 33 Yes: 8-10% Chrysotile
Good 139 sf
1G Plaster 2, 3, 8-13, 15, 16 No Good 1,953 sf 1H Cement Floor
& Mastic 7, 14 Yes: 8-10%
Chrysotile Black Mastic
Good 342 sf
1J 12”x12” Floor Tile & Mastic
4, 6 Yes: 8-10% Chrysotile
Good 75 sf
1K Floor Compound &
Mastic
9 Yes: 10-12% Chrysotile
Black Mastic
Good 208 sf
2A Drywall Texture
2, 3, 7-28, 32, 33 Yes: 2-3% Chrysotile
Good 6,700 sf
2B Gypsum Drywall
2,3, 7-28, 32, 33 No Good 6,700 sf
2C Plaster 1-7, 10, 11, 13-22, 24-31, 33, 34
No Good 6,500 sf
2E Stucco Exterior Entire Exterior Of Building
No Good 5,027 sf
2F Drywall Compound
2, 3, 7-28, 32, 33 Yes: 2-3% Chrysotile
Good 6,700 sf
3A 1’x1’ Random 27-29 No Good 911 sf
Ceiling Tile & Mastic
3B 1’x1’ Fissured Ceiling Tile &
Mastic
31-34 No Good 434 sf
3C 2’x4’ Ceiling Tile & Mastic
1-3, 7, 8, 10-29 No Good 4,330 sf
7A Cove Base Mastic
17-34 No Good 468 sf
7B Window Putty On Exterior Windows Yes: 1-2% Chrysotile
Good 31 sf
7C Leveling Compound
2, 3, 8-13, 15, 16 No Good 130 sf
8A Roofing Shingles
Roof No Good 1,200 sf
8B Roofing Felt Roof No Good 1,200 sf 8C Ceramic
Roofing Felt Roof No Good 5,750 sf
Laboratory analysis of the bulk samples collected from the Phoenix Indian Medical Center Buildings #5 & 6, Office, indicates that floor tiles, floor tile mastics, wall texture, drywall joint compound, and window putty contain asbestos.
Floor tile and mastics are non-friable NESHAP Category I materials. The materials occur in multiple layers and are in good condition and pose minimum health threat. Removal or disturbance to this material should be performed by appropriately trained and certified personnel. Removed flooring material may be disposed at a landfill that accepts non-friable asbestos waste. Landfills should be checked for acceptance of this material prior to the disposal of asbestos waste materials.
Drywall joint compound and wall texture are classified as NESHAP Category I materials assuming that no disturbance will be caused to them by either renovation or demolition. If disturbance to the material is required, they must be treated as friable NESHAP RACM. Removal of this material should be performed by appropriately trained and certified personnel. Friable materials must be disposed of at a regulated landfill, approved by the EPA for disposal of friable asbestos waste.
Window putty is a non-friable NESHAP Category I material. The material is in good condition and poses little health threat. Removal or disturbance to this material should be performed by appropriately trained and certified personnel. Removed window putty may be disposed at a landfill that accepts non-friable asbestos waste. Landfills should be checked for acceptance of this material prior to the disposal of waste materials.
5.0 ABATEMENT COST ESTIMATE
Following is the programming cost estimate for the removal of asbestos-containing materials.
Identified asbestos-containing materials (ACMs) consist of floor tile & mastics (5,241 sf), gypsum drywall materials (6,700 sf), window putty (31 sf).
APPENDIX 1
Bulk Sample Log
Location of Functional Spaces
APPENDIX 2
Laboratory Results
APPENDIX 3
Certifications