Attachment J25 - Buildings 5 and 6 Asbestos Survey.pdf

PDF 847 KB Posted

Attached to
PIMC Maintenance & Improvements (M&I) Renovations
Solicitation number
75H701-23-R-00001
Issued by

About this file

This document is an asbestos survey report for Buildings 5 and 6 at the Phoenix Indian Medical Center campus. The report identifies various asbestos-containing materials found throughout the buildings including floor tiles and mastics, wall textures, drywall joint compounds, and window putty. Laboratory testing confirmed the presence of asbestos in these materials. The report provides the locations and quantities of the asbestos-containing materials and notes most are in good condition. It includes an abatement cost estimate and liability limitations. Appendices include sampling logs, laboratory results, and inspector certifications.

The related federal contract opportunity is a solicitation for maintenance and improvement renovations at the Phoenix Indian Medical Center. The work includes abatement of asbestos materials identified in the survey report along with other projects like mechanical HVAC improvements, interior and exterior painting, roof replacement, fire alarm and sprinkler work. The performance period is 300 days with anticipated value between $1 million to $5 million. The solicitation will use LPTA evaluation and result in a firm fixed price contract with the Indian Health Service.

View the file

Other files

File Type Posted
B04 Pre-Proposal Inquiries (23R00001) (85-87).pdf PDF
B05 75H70123R00001 Amendment A000008.pdf PDF
B05 75H70123R00001 Amendment A000007.pdf PDF
Attachment J17 - WD AZ20230031 2023.01.06.pdf PDF
B05 75H70123R00001 Amendment A000006.pdf PDF
B04 Pre-Proposal Inquiries (23R00001) (1-84).pdf PDF
Attachment J01 R2 - SOW - PIMC MI Renovations (CHANGES IN RED) 2022.12.05.pdf PDF
Attachment J01 R2 - SOW - PIMC MI Renovations FINAL 2022.12.05.pdf PDF
B05 75H70123R00001 Amendment A000005.pdf PDF
Attachment J12 R1 - Micro Lab Renovation Schematics.pdf PDF
Attachment J01 R1 - SOW - PIMC MI Renovations (changes in red) 2022.11.28.docx DOCX document
Attachment J02 R1 - PIMC Campus Map.pdf PDF
B04 Pre-Proposal Inquiries (23R00001) 1-29.pdf PDF
Attachment J04 R1 - Behavioral Health Schematics.pdf PDF
Attachment J03 R1 - 3rd Floor Nurse Station Replacement.pdf PDF
B05 75H70123R00001 Amendment A000004.pdf PDF
Attachment J06 R1 - Main Tower Maintenance Areas.pdf PDF
Attachment J26 - Asbestos Abatement Specification.pdf PDF
Attachment J01 R1 - SOW - PIMC MI Renovations FINAL 2022.11.28.pdf PDF
Attachment J24 - Hospital Exterior Painting.pdf PDF
Attachment J10 R1 - Fire Sprinkler Replacement and Testing.pdf PDF
Attachment J05 R1 - Outpatient Floor Plans.pdf PDF
B05 75H70123R00001 Amendment A000003.pdf PDF
B05 75H70123R00001 Amendment A000002.pdf PDF
B04 Pre-Proposal Inquiries (23R00001).pdf PDF
Attachment J19 - Self Performed Calculation Sheet (Amend A00002).pdf PDF
B03 Site Visit Agenda and Sign-in (23R00001).pdf PDF
B05 75H70123R00001 Amendment A000001.pdf PDF
Attachment J17 - WD AZ20220031 Mod 8 2022.10.28.pdf PDF
B01 RFP 75H701-23-R-00001.pdf PDF
Attachment J04 - Behavioral Health Schematics.pdf PDF
Attachment J03 - 3rd Floor Nurse Station Replacement.pdf PDF
Attachment J19 - Self Performed Calculation Sheet (Construction).docx DOCX document
Attachment J12 - Micro Lab Renovation Schematics.pdf PDF
Attachment J17 - WD AZ20220031 Mod 7 2022.10.07.pdf PDF
Attachment J06 - Main Tower Maintenance Areas.pdf PDF
Attachment J09 - ED Waiting Room Ventilation.pdf PDF
Attachment J23 - Financial Institution Reference Sheet.docx DOCX document
Attachment J08 - CSR Schematics.pdf PDF
Attachment J21 - Past Performance Questionnaire.docx DOCX document
Attachment J10 - Fire Sprinkler Replacement and Testing.pdf PDF
Attachment J20 - Company Specialized Experience Form.docx DOCX document
Attachment J01 - SOW - PIMC MI Renovations 2022.10.25.pdf PDF
Attachment J15 - ICRA Permit.pdf PDF
Attachment J22 - Key Personnel Resume Form.docx DOCX document
Attachment J14 - Phoenix Solid Waste Access and Enclosure Standard Details.pdf PDF
Attachment J07 - PIMC Asbestos Survey Feb 2003.pdf PDF
Attachment J13 - Trash Enclosure Location.pdf PDF
Attachment J18 - 2022 Exemption Letter for a Qualifying Hospital.pdf PDF
Attachment J11 - PIMC 2021 Fire Alarm Testing Report.pdf PDF
Show 40 more

Latest 50 of 53 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ASBESTOS SURVEY

At

PHOENIX INDIAN MEDICAL CENTER

Building #5 & 6 – Office

For

Phoenix Area Indian Health Service Two Renaissance Square

40 N. Central Avenue Phoenix, AZ 85004

By

U.S. Public Health Service Federal Occupational Health

2201 Sixth Avenue, M/S Rx-21 Seattle, Washington 98121-2500

(206) 615-2441

February 2003

Attachment J25 - Buildings 5 & 6 Asbestos Survey

TABLE OF CONTENTS

Section Title Page No.

1.0 Introduction

2.0 Description of Inspected Area

3.0 Survey Procedures

4.0 Findings

5.0 Abatement Cost Estimate

6.0 Liability Limitations

Appendices

1 Bulk Sample Log and Location of Functional Spaces

2 Laboratory Results

3 Certifications

Area Wide Asbestos Building Inspection Indian Health Service Facilities

Phoenix Indian Medical Center Campus Building #5 & 6 – Office

Phoenix, Arizona

1.0 INTRODUCTION

As requested by the Phoenix Area Indian Health Services, bulk sampling of suspect asbestos-containing building materials was conducted in Building #5 & 6, Office, at the Phoenix Indian Medical Center (PIMC) at 4212 North 16th Street in Phoenix, Arizona, on August 1, 2002. Bulk samples of suspect asbestos-containing materials (ACMs) were collected throughout the interior and exterior of the building.

Messrs. Mark Updike and James Marshall, representing Federal Occupational Health (FOH), performed the asbestos inspection of the subject property. Messrs. Updike and Marshall both hold current Asbestos Hazard Emergency Response Act (AHERA) accreditation as Asbestos Building Inspectors. Sampling of suspect asbestos-containing materials was conducted using procedures similar to the Environmental Protection Agency (EPA) AHERA regulations, 40 CFR 763. The Federal Occupational Health EH Environmental Laboratory in Denver, Colorado, performed the laboratory analysis of the asbestos samples.

Laboratory analysis indicates that floor tiles, floor tile mastics, wall texture, drywall joint compound, and window putty in Buildings #5 & 6, Office, contain asbestos.

2.0 DESCRIPTION OF INSPECTED AREA

This inspection focused on the entire interior and exterior of the building. The building is single story with a stucco exterior built slab-on grade. The roof consists of both a composite shingle and ceramic shingle roofing system.

Suspect building materials identified and sampled in the subject property included the following: Various floor tiles and associated mastics, various gypsum drywall materials, plaster wall materials, leveling compounds, cove base mastic, acoustical ceiling tiles and associated mastic, exterior stucco, window putty, and roofing materials.

3.0 SURVEY PROCEDURES

Each room was assigned unique functional space numbers. Each functional space was visually inspected for suspect asbestos-containing materials. Materials were mapped and quantified on maps provided by the IHS or on hand made maps of the existing floor plan.

Each suspect ACM was designated as a distinct homogeneous area, which is a single material, uniform in texture and appearance, installed at one time, and unlikely to consist of more than one type or formulation of material. The inspectors touched each suspect material in order to determine friability.

A sufficient number of samples were collected of each material to satisfy the Occupational Safety and Health Administration (OSHA) and the National Emission Standard for Hazardous Air Pollutants (NESHAP) regulations for the determination of asbestos content. A total of 84 samples were collected from Buildings #5 & 6.

Each sample was assigned a unique sample identification number and assessed for damage and friability classifications. The samples, with Chain of Custody documentation were delivered to FOH EH

Environmental Laboratory for analysis. The FOH EH Environmental Laboratory is accredited under the National Voluntary Laboratory Accreditation Program (NVLAP) for bulk-asbestos sample analysis conducted by the National Institute of Standards and Technology.

A description of the samples taken, location, and summary of laboratory results are located in Appendix 1.

The asbestos laboratory reports are included as Appendix 2.

4.0 FINDINGS

Results of the asbestos inspection are as follows:

Phoenix Indian Medical Center Building #5 & 6 – Office

HA # Material Functional Space ACM Condition Quantity 1A 12”x12” Floor

Tile & Mastic 1-34 Yes: 10-12%

Chrysotile Black Mastic

Good 5,241 sf

1B 12”x12” Floor Tile & Mastic

17-29 Yes: 10-12% Chrysotile

Good 2,011 sf

1C 12”x12” Floor Tile & Mastic

17-29 Yes: 12-15% Chrysotile

Good 2,011 sf

1D 12”x12” Floor Tile & Mastic

31, 32, 34 Yes: 8-10% Chrysotile

Good 853 sf

1E 12”x12” Floor Tile & Mastic

31, 34 Yes: 12-14% Chrysotile

Good 772 sf

1F 12”x12” Floor Tile & Mastic

32, 33 Yes: 8-10% Chrysotile

Good 139 sf

1G Plaster 2, 3, 8-13, 15, 16 No Good 1,953 sf 1H Cement Floor

& Mastic 7, 14 Yes: 8-10%

Chrysotile Black Mastic

Good 342 sf

1J 12”x12” Floor Tile & Mastic

4, 6 Yes: 8-10% Chrysotile

Good 75 sf

1K Floor Compound &

Mastic

9 Yes: 10-12% Chrysotile

Black Mastic

Good 208 sf

2A Drywall Texture

2, 3, 7-28, 32, 33 Yes: 2-3% Chrysotile

Good 6,700 sf

2B Gypsum Drywall

2,3, 7-28, 32, 33 No Good 6,700 sf

2C Plaster 1-7, 10, 11, 13-22, 24-31, 33, 34

No Good 6,500 sf

2E Stucco Exterior Entire Exterior Of Building

No Good 5,027 sf

2F Drywall Compound

2, 3, 7-28, 32, 33 Yes: 2-3% Chrysotile

Good 6,700 sf

3A 1’x1’ Random 27-29 No Good 911 sf

Ceiling Tile & Mastic

3B 1’x1’ Fissured Ceiling Tile &

Mastic

31-34 No Good 434 sf

3C 2’x4’ Ceiling Tile & Mastic

1-3, 7, 8, 10-29 No Good 4,330 sf

7A Cove Base Mastic

17-34 No Good 468 sf

7B Window Putty On Exterior Windows Yes: 1-2% Chrysotile

Good 31 sf

7C Leveling Compound

2, 3, 8-13, 15, 16 No Good 130 sf

8A Roofing Shingles

Roof No Good 1,200 sf

8B Roofing Felt Roof No Good 1,200 sf 8C Ceramic

Roofing Felt Roof No Good 5,750 sf

Laboratory analysis of the bulk samples collected from the Phoenix Indian Medical Center Buildings #5 & 6, Office, indicates that floor tiles, floor tile mastics, wall texture, drywall joint compound, and window putty contain asbestos.

Floor tile and mastics are non-friable NESHAP Category I materials. The materials occur in multiple layers and are in good condition and pose minimum health threat. Removal or disturbance to this material should be performed by appropriately trained and certified personnel. Removed flooring material may be disposed at a landfill that accepts non-friable asbestos waste. Landfills should be checked for acceptance of this material prior to the disposal of asbestos waste materials.

Drywall joint compound and wall texture are classified as NESHAP Category I materials assuming that no disturbance will be caused to them by either renovation or demolition. If disturbance to the material is required, they must be treated as friable NESHAP RACM. Removal of this material should be performed by appropriately trained and certified personnel. Friable materials must be disposed of at a regulated landfill, approved by the EPA for disposal of friable asbestos waste.

Window putty is a non-friable NESHAP Category I material. The material is in good condition and poses little health threat. Removal or disturbance to this material should be performed by appropriately trained and certified personnel. Removed window putty may be disposed at a landfill that accepts non-friable asbestos waste. Landfills should be checked for acceptance of this material prior to the disposal of waste materials.

5.0 ABATEMENT COST ESTIMATE

Following is the programming cost estimate for the removal of asbestos-containing materials.

Identified asbestos-containing materials (ACMs) consist of floor tile & mastics (5,241 sf), gypsum drywall materials (6,700 sf), window putty (31 sf).

APPENDIX 1

Bulk Sample Log

Location of Functional Spaces

APPENDIX 2

Laboratory Results

APPENDIX 3

Certifications