Amendment_0002_70Z08525RLREP0013 HEALY FY26 Solicitation.pdf
PDF 848 KB Posted
- Solicitation number
- 70Z08525RLREP0013
About this file
This document is an Amendment of Solicitation/Modification of Contract for the USCG Surface Forces Logistics Center, specifically for the HEALY DD FY26 project (Solicitation No. 70Z08525RLREP0013). The amendment includes several key modifications: replacement of multiple attachments including the Specifications Statement of Work, Pricing Sheet, and Consolidated List of References, with new versions marked as A0002. Line Item 45 for Propeller Hubs and Blades, Removal and Reinstallation was added to Tab 1 Task Order 1, and answers to Request for Clarification Questions were attached.
The amendment notably changes the proposal close date from 05 NOV 2025 to 12 NOV 2025. The Request for Clarification questions address technical details such as pit measurements during stern tube inspection, valve information in Table 2, and propeller hub removal and reinstallation requirements. The U.S. Coast Guard confirmed that the 200 pit measurements can be handled as a Condition Found Report after visual inspection, no valves are required for certain items, and propeller hub removal specifications are now included in Work Item 45.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A0002
USCG Surface Forces Logistics Center Attn: Kyra May 1519 Alaska Way South Seattle, WA 98134 E-mail: kyra.l.may@uscg.mil
70Z08525RLREP0013
X
10/22/20025
HEALY DD FY26
See next page.
10/242025
X
X X mailto:kyra.l.may@uscg.mil
CONTINUATION OF SF 30 – BLOCK 14
70Z08525RLREP0013 is hereby amended (70Z08525RLREP0013A0002) as follows:
1. The document titled: 70Z08525RLREP0013 Attachment 2 Specifications Statement of Work is hereby replaced in its entirety with 70Z08525RLREP0013 Attachment 2 Specifications Statement of Work A0002.
2. The document titled: 70Z08525RELP0013 Attachment 1 Pricing Sheet is hereby replaced in its entirety with 70Z08525RLREP0013 Attachment 1 Pricing Sheet A0002. Line Item 45 - Propeller Hubs and Blades, Removal and Reinstallation was added to Tab 1 Task Order 1.
3. The document titled: 70Z08525RLREP0013 HEALY DD FY26 Solicitation 21OCT25 A0001 is hereby replaced in its entirety with 70Z08525RLREP0013 HEALY DD FY26 Solicitation 21OCT25 A0002. A revision is marked with REV2 in the document.
4. The document titles: 70Z08525RLREP0013 Attachment 3 Consolidated List of Referencesv2 is hereby replaced in its entirety with 70Z08525RLREP0013 Attachment 3 Consolidated List of Referencesv2 A0002.
5. Attached are answers to the Request for Clarification Questions received as of 24 OCT 2025.
6. The proposal close date is hereby changed from 05 NOV 2025 to 12 NOV 2025.
7. No other changes are made or implied.
mailto:(Wayne.m.gutman@uscg.mil mailto:Amy.A.Kelm@uscg.mil
Request for Clarification
Offeror’s Name:
Solicitation No. 70Z08525RLREP0013
Question Submitted Number: 001 Section/Work Item Number: 14 Paragraph Number, if applicable: 3.8.1.1
Question: Can the 200 measurements of the pits be handled as a CFR after the visual inspection of the cleaned stern tube?
Answer: Yes. Upon review the 200 measurements of pits can be handled as part of the Condition Found Report (CFR) after the visual inspection of the cleaning and removal of the existing coating system. As outlined in section 3.8.1, the Contractor must visually inspect all exposed substrates for signs of pits, corrosion, and erosion.
Perform all inspections in the presence of the Coast Guard Inspector and in accordance with SFLC Std Spec 0740 and submit a CFR.
Question Submitted Number: 002 Section/Work Item Number: 22 Paragraph Number, if applicable: Table 2
Question: Table 2 shows Item No 1B and 2B but is missing the Valve Type, Size, Description, Valve No. and Location. Please provide the missing information for Items 1B and 2B.
Answer: Upon review, we confirm that no valves are required for Items 1B and 2B in Table 2. Additionally, the contractor incorrectly cited WI-22, which pertains to Internal Hoists. WI-23 is the correct reference that covers the valves. Therefore, the fields for Valve Type, Size, Description, Valve No., and Location in Table 2 are intentionally left blank.
Question Submitted Number: 003 Section/Work Item Number: 14 Paragraph Number, if applicable: 3.3.1
Question: Paragraph 3.3.1 states Coordinate with Definite Items, “Propeller Hubs, Removal and Reinstallation”.
Propeller Hubs, Removal and Reinstallation has not been included in the package. Please advise if the propeller hubs are to be removed and reinstalled and provide a detailed explanation and associated drawings.
Answer: Upon review, Paragraph 3.3.1 references coordination with "Definite Items, Propeller Hubs, Removal and Reinstallation." The specification has been updated, and the requirements for the removal and installation of the propeller hubs and blades are now included in Work Item 45.
Request for Clarification Attachment (5) Solicitation No.: 70Z08525RLREP0013
Question Submitted Number:
Section/Work Item Number:
Paragraph Number, if applicable:
Question:
…”Respectfully requests USCG reconsider this Amendment and revert to adding one additional week to the original Bid Due date from 12 November to 19 November allowing [deleted] and other bidders an opportunity to give this proposal the attention it deserves. Even this is a very short period to put all of this together”.
Answer: USCG has extended the close date to 12 Nov 25.