Attachment D-Preliminary Life-Cycle Cost Analysis LCCA rev 1.pdf
PDF 3 MB Posted
- Attached to
- DESIGN/BUILD CONSTRUCTION FOR CHILD DEVELOPMENT CENTER, USCG BASE ELIZABETH CITY, NORTH CAROLINA
- Solicitation number
- 70Z04726RPCNI0004
About this file
This is an HVAC Life Cycle Cost Analysis Report for the Base Elizabeth City Child Development Center located at Elizabeth City Coast Guard Base, North Carolina, submitted by BCE Engineers (a division of GFT) to the US Coast Guard on October 27, 2025. The analysis covers Contract No. 70Z05018DTRANSY01 and Order No. 70Z05025F43000001.
The report evaluates three HVAC system alternatives for a 24,629 square-foot single-story child development center using a 40-year life cycle cost analysis conducted with BLCC5 software. The proposed system utilizes ground-coupled water source heat pumps (GCHP) with a dedicated outdoor air system (DOAS) and air-to-air heat recovery, paired with an air source heat pump water heater. Alternative 1 consists of a variable air volume (VAV) system with an air source heat pump chiller and hot water reheat, while Alternative 2 features a VAV system with a ground-coupled water-to-water heat pump. All three designs exceed the EPACT requirement of 30% energy savings above the ASHRAE 90.1-2022 baseline, with the proposed system achieving 46.98% savings, Alternative 1 achieving 41.94%, and Alternative 2 achieving 51.86%. The 40-year life cycle costs are $2,081,568 for the Proposed system, $2,307,853 for Alternative 1, and $2,597,810 for Alternative 2. Initial costs, maintenance costs, energy consumption costs, and replacement costs over the 40-year period are detailed for each alternative. The building operates 8 hours per day, 5 days per week, with heating and cooling setpoints of 65°F and 75°F respectively, and includes envelope specifications with roof insulation at R-49 and wall insulation at R-13 with R-10 continuous insulation.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HVAC Life Cycle Cost Analysis Report
Base Elizabeth City Child Development Center Elizabeth City Coast Guard Base, North Carolina
CONTRACT NO 70Z05018DTRANSY01
ORDER NO. 70Z05025F43000001
CLIENT PROJECT NO. 12993422
SUBMITTED BY:
BCE Engineers
A Division of GFT
SUBMITTED TO:
US Coast Guard
DATE:
27 October 2025
Table of Contents
1 Introduction
2 Life Cycle Cost Analysis Inputs
2.1 General Site Description
2.2 Envelope Description
2.3 HVAC Description
2.4 Utility Rates ....................................................................................................................... Error! Bookmark not defined.
2.5 Economic Assumptions
2.6 Installation Cost and Service Life
2.7 Maintenance Cost
2.8 Domestic Hot Water Analysis
2.8 Energy Consumption and Energy Cost
3 Life Cycle Cost Analysis Results
Appendix A .................................................................................................................... A1
BLCC5 LCC Analysis Results ...................................................................................................................................................... A1
NIST BLCC 5.3-20: Summary LCC ............................................................................................................................................. A2
Alternative: Proposed HP Chiller with VAV Reheat ....................................................................... AError! Bookmark not defined.
Alternative: Ground Coupled Water Source Heat Pump .............................................................................................................. A4
Alternative: Ground Couple Heat Pump VAV with Reheat ........................................................................................................... A3
Appendix B .................................................................................................................... B1
Escalation Rates ......................................................................................................................................................................... B1
List of Tables
Table 1 – Proposed, Alternate, And Baseline Building Components
Table 2 – Alternatives And Proposed HVAC Components
Table 3 – Installation Costs And Service Life
Table 4 – Maintenance Costs
Table 5 – Energy Consumption And Cost Summary
Table 6 – Proposed, Alternative 1, And Alternative 2 LCC Results
Table 7 – Performance Cost Index Compliance Path ....................................................................................................................... B2
Table 8 – "Real" Electrical Escalation .............................................................................................................................................. B2
E-CITY CHILD DEVELOPMENT CENTER
HVAC LCCA
1 Introduction
This Life Cycle Cost (LCC) Analysis is an effort to document, plan, and decide this building's energy-related components. The energy analyst and architectural team have listed, discussed, and analyzed the envelope for this building. They have made decisions and assumptions about the roof, walls, floor, glazing, and doors and how these interact with the heating, ventilation, and air conditioning (HVAC) system and lighting systems. Decisions were made about the practicality, budget, and function of all these items, and the components analyzed best fit this facility and its constraints.
The proposed building's estimated energy consumption is less than the ASHRAE 90.1-2022 baseline energy consumption by 19.88% with no process loads included. The proposed building energy model energy cost is less than the ASHRAE 90.1-2022 baseline model energy cost by 46.98% with process loads. Alternate 1's building's energy model cost is less than the ASHRAE 90.1-2022 baseline model energy cost by 41.94% with process loads. Alternate 2’s building's energy model cost is less than the ASHRAE 90.1-2022 baseline model energy cost by 51.86% with process loads. The energy tool used to estimate building energy consumption was Trace700. The Proposed systems and both Alternate 1 and 2 building designs meet the EPACT requirement of 30% or more energy savings above the ASHRAE 90.1-2022 baseline energy model for a new project.
The proposed building design and its alternative building designs were analyzed for a 40-year life cycle using
BLCC5. The BLCC5 outputs were compared to ensure that a cost-efficient building design was selected.
2 Life Cycle Cost Analysis Inputs
2.1 General Site Description
CDC E-City is a single-story building. The child development center is a 24,629 ft2 building comprising mostly of early-childhood classrooms as well as office space, reception areas, a faculty break area, storage spaces, a comms room, a kitchen, a laundry room, and building utility rooms. The building is occupied during the day, 8 hours per day, five days a week. The minimum outside air requirement has been calculated per ASHRAE
62.1-2022. The building has a heating setpoint of 65 °F, with a cooling setpoint of 75 °F. During unoccupied hours, the HVAC systems revert to a "setback" mode wherein the heating and cooling setpoints are reset to conserve energy when that portion of the building is not being used.
2.2 Envelope Description
The child development center proposed building envelope consists of the following: Roof R-49 continuous insulation with a calculated U value of 0.02. Walls R-13 batt with R-10 continuous insulation with a calculated
U value of 0.076. Vertical glazing was modeled as fixed, nonmetal framed, double pane with a U value of 0.4 and an SHGC value of 0.32. Standard opaque swinging doors were modeled with a U-value of 0.352.
Alternative 1's and Alternative 2's envelopes are the same as the proposed envelope. Table 1 compares the
Proposed, Alternative 1 and Alternative 2 building envelope components and their overall U values. ASHRAE
90.1-2022 Baseline envelope values are also listed in the table below for comparison.
E-City Child Development Center
Table 1 – Proposed, Alternate, and Baseline Building Components
Component Proposed: Ground
Coupled WSHP
Alternative 1: HP Chiller
VAV w/Reheat
Alternative 2: GCHP
VAV w/Reheat
ASHRAE 90.1 -
2022 Baseline
Walls U=0.076 U=0.076 U=0.076 U=0.071
Roof U=0.02 U=0.02 U=0.02 U= 0.028
Vertical Glazing
(Windows)
U=0.4 fixed
SHGC=0.32
U=0.4 fixed
SHGC=0.32
U-0.4 fixed
SHGC=0.32
U=0.29 fixed
SHGC=0.4
Doors
(Swinging) U=0.352 U=0.352 U=0.352 U=0.370
Concrete Floor F=0.48 F=0.48 F=0.48 F=0.51
2.3 HVAC Description
The proposed HVAC system consists of a ground coupled heat pump (GCHP) and a dedicated outdoor air system (DOAS). Each space will have a ground-coupled water source heat pump located in the ceiling or closet space. These GCHP’s will recirculate zone air to provide heating and cooling for the space. The GCHP will allow for unoccupied, after hours heating and cooling without the need of the DOAS. The DOAS will provide ventilation air and collect return and exhaust air from the building. The return air will be pulled across an air-to-air heat exchanger to temper the ventilation air before being provided to the building. An electric hydronic boiler will be provided to back up the ground coupled heat pump during extremely cold weather.
An under floor radiant heating system will be provided in infant and pre-toddler care rooms and coupled with the GCHP and hydronic boiler.
Alternate 1’s HVAC system consists of a variable air volume (VAV) system with a full air-side economizer.
Each space or zone will have a VAV terminal recirculating the air to heat or cool the space. The VAV terminal will have a hot water reheat coil on the discharge to provide heating and will provide unoccupied, after hours heating without the use of the main air handler. The main air handler provides ventilation air that is heated/cooled/dehumidified and delivered to each space through the VAV terminals. Supply air temperature will continually be reset based on VAV terminal air volume feedback. Heating water will be generated by a high-efficiency, air to water heat pump. Heating water will be circulated to each VAV terminal, the under-floor radiant heat system, and the main air handler. Chilled water will be generated by the same high-efficiency, air to water heat pump and circulated to the main air handler for the purpose of cooling and dehumidification of the ventilation air.
Alternative 2’s HVAC system consists of a variable air volume (VAV) system with a full air-side economizer.
Each space or zone will have a VAV terminal recirculating the air to heat or cool the space. The VAV terminal will have a hot water reheat coil on the discharge to provide heating and will provide unoccupied, after hours heating without the use of the main air handler. The main air handler provides ventilation air that is heated/cooled/dehumidified and delivered to each space through the VAV terminals. Supply air temperature will continually be reset based on VAV terminal air volume feedback. Heating water will be generated from a high-efficiency ground-coupled water to water heat pump (GCHP). Heating water will be circulated to each
VAV terminal, the main air handler, and the under-floor radiant heat system. Chilled water will be generated by the same GCHP and circulated to the main air handler for the purpose of cooling and dehumidification of the ventilation air. Chilled water will also be circulated to the VAV terminals for the purpose of cooling the space.
Per ASHRAE 90.1-2022 G.1.2.2, "Neither the proposed building performance nor the baseline building performance are predictions of actual energy consumption or costs for the proposed design after construction. Actual experience will differ from these calculations due to variations such as occupancy, building operation and maintenance, weather, energy use not covered by this procedure, changes in energy rates between the design of the building and occupancy, and the precision of the calculation tool."
The proposed system, alternative 1, and alternative 2 HVAC definitions and efficiencies are listed below in
Table 2. ASHRAE 90.1-2022 baseline HVAC definitions and efficiencies are also listed for comparison.
Table 2 – Alternatives and Proposed HVAC Components
Component
Proposed: Ground
Coupled WSHP
Alternative 1: Chiller
VAV w/Reheat
Alternative 2: GCHP
VAV w/Reheat
ASHRAE 90.1 -
2022 Baseline –
System 5
Heating
Water Source Heat Pump –
3.7 COP
Air Source Heat Pump – 2.52
COP
Water Source Heat Pump – 3.7
COP
Gas Fired Furnace – 75%
EFF
Cooling WSHP – 18 EER ASHP – 9.3 EER WSHP – 18 EER PSZ – 10.57 EER
Economizer No No No Yes, @75ºF
Heat
Recovery* 0.76 sensible/0.74 latent 0.76 sensible/0.74 latent 0.76 sensible/0.74 latent None
Supply Fan
(kw/cfm) WSHP=0.0008 ASHP SF=0.0008 WSHP=0.0008
Packaged Rooftop VAV
SF=0.00113988
Safety Factor
1.0 Heating
1.0 Cooling
1.0 Heating
1.0 Cooling
1.0 Heating
1.0 Cooling
1.25 Heating
1.15 Cooling
Equipment
Schedule 8 Hrs/day, 5 days/week 8 Hrs/day, 5 days/week 8 Hrs/day, 5 days/week 8 Hrs/day, 5 days/week
2.4 Utility Rates
The electric energy rate used for the economic analysis is $0.0933 per kWh. The natural gas rate used for the economic analysis is $1.20 per therm. Utility rates for both electricity and natural gas were current rates received from the US Coast Guard and US Government for the area of Elizabeth City, North Carolina in 2025.
2.5 Economic Assumptions
The economic assumptions made in this analysis are based on the values in the current version of BLCC5_3-
24. The current BLCC5 economic assumptions extend to 2065. Years beyond 2065 included in this analysis are assigned the "Remaining" Escalation Rate. "Real" escalation rates are as noted in Appendix B.
2.6 Installation Cost and Service Life
The HVAC equipment costs shown below were provided by “CostWorks 2021”. The equipment service life data was estimated from the "Energy Life-Cycle Cost Analysis, Guidelines for Public Agencies." A summary of the installation costs and service life for the proposed building system and the alternative building systems is listed below in Table 3.
Table 3 – Installation Costs and Service Life
Category Service Life Proposed: Ground
Coupled WSHP
Alternative 1: Chiller VAV w/Reheat
Alternative 2: GCHP VAV w/Reheat
Ductwork 50 $184,718 $184,718 $184,718
WSHP 19 $254,150 $0 $0
Hydronic Piping 50 $73,887 $147,774 $147,774
Hydronic Circ. Pump 25 $41,950 $49,900 $41,950
Electric Hydronic Boiler 15 $35,000 $44,000 $35,000
4-Pipe VAV AHU 20 $96,600 $285,000 $285,000
Controls 15 $67,730 $67,730 $67,730
Enthalpy Wheel Heat
Exchanger 20 $29,700 $0 $0
Ground Loop Heat
Exchanger 50 $394,064 $0 $394,064
VRF Condensing Unit –
1.5 Ton 20 $2,475 $2,475 $2,475
VRF Indoor Unit – 1 Ton 20 $8,025 $8,025 $8,025
Radiant Floor Piping 50 $69,563 $69,563 $69,563
Fan Powered VAV
Terminal 20 $0 $155,670 $166,790
Air Cooled Chiller 20 $0 $245,000 $0
Water Cooled Chiller 20 $0 $0 $210,000
Totals $1,257,862 $1,259,855 $1,603,089
2.7 Maintenance Cost
A summary of the proposed and two alternate system's maintenance costs are listed below in Table 4. The maintenance costs for each system alternate are estimated from "RS Means Facilities Maintenance and
Repair 2021".
Table 4 – Maintenance Costs
Category Proposed: Ground
Coupled WSHP
Alternative 1: Chiller
VAV w/Reheat
Alternative 2: GCHP VAV w/Reheat
WSHP $9,775 $0 $0
Hydronic Circ. Pump $246 $246 $246
Electric Hydronic Boiler $435 $435 $435
4-Pipe VAV AHU $645 $1,290 $1,290
Controls $290 $290 $290
VRF Condensing Unit – 1.5 Ton $370 $370 $370
VRF Indoor Unit – 1 Ton $880 $880 $880
Fan Powered VAV Terminal $0 $7,056 $7,560
Air Cooled Chiller $0 $1,475 $0
Water Cooled Chiller $0 $0 $1,175
Annual Totals $12,641 $12,042 $12,246
2.8 Domestic Hot Water Analysis
The design team evaluated two electric water heating systems and compared them to the ASHRAE 90.1 2022
Appendix G Baseline. The proposed system utilizes an air source heat pump water heater that would operate in a single pass lift to meet the storage temperature of 140F, with a back-up electric boiler for usage in extreme cold weather. Alternative 2 is an air source heat pump system that operates in the same manner as the proposed system to meet the 140F storage temperature. A PV array is supplied to work as a supplemental renewable energy for the air source heat pump and an electric boiler is provided to aid in heating water in extreme cold weather. Each alternative was run under the assumption that the child development center uses 1980.6 gallons of water per day, calculated at 2.4 gallons/meal for 352 people a day, plus an additional
264 gallons/day for lavatory water usage and an additional 27 gallons/day for sink water usage. Details and costs for each system are shown in Table 5 below.
Table 5 – Domestic Hot Water Generation Alternatives
Since the proposed system showed the lowest life cycle cost, this system was paired with all of the HVAC alternatives in the full LCC analysis. The Appendix G baseline case included the gas-fired DHW system.
Alternative 1:
ASHP Alternative 2: ASHP w/30% PV
ASHRAE 90.1 2022 Appendix
G Baseline (Gas-Fired Water
Heater)
Daily Hot Water Use (gal/day) 1980.6 1980.6 1980.6
Incoming Cold-Water Temp 50 50 50
Hot Water Storage Temp 140 140 140
Building HW Energy
Requirement (kWh/year) 52,451.6 36,716.1 6,713 therms
Thermal Efficiency of DHW
System 3.0 COP (47F) 3.0 COP (47F) .8 Et
Cost of Fuel $0.0933/kWh $0.0933/kWh $1.20 / therm
Annual Energy Cost $4,894 $3,425 $8,056
Equipment Spec
400 MBH ASHP
60 kW Electric Swing
Tank
500-gallon storage
400 MBH ASHP
60 kW Electric Swing Tank
11 kW PV Array
500-gallon storage
(1) 500 Gallon 750MBH Gas-Fired
Water Heaters
Equipment First Cost $90,300 $117,800 $47,800
Annual O&M Cost $1,910 $2,100 $1,925
40 Year LCC $315,781 $328,368 $246,505
2.9 Energy Consumption and Energy Cost
Table 6 below summarizes the baseline, proposed, and alternative building designs' energy consumption and costs. The electric and natural gas utility rates were provided by the US Coast Guard for the area of Elizabeth
City. This analysis's electric utility rate is $0.0933 per kWh, while the natural gas was taken from an average commercial rate of $1.20 per therm. These energy model results and costs are used in the BLCC5 40-year life cycle cost analysis.
Table 6 – Energy Consumption and Cost Summary
Component Proposed: Ground
Coupled WSHP
Alternative 1: HP
Chiller VAV w/Reheat
Alternative 2:
GCHP VAV
w/Reheat
ASHRAE 90.1 -
2022 Baseline
Fan energy 100.9 26.6 22.5 33.7
Heating Energy 120.3 132.9 124.6 536.5
Cooling Energy 26.2 113.3 66.9 71.4
Interior Lighting Energy 83.9 83.9 83.9 143.8
Pump & Aux Energy 4.8 2.4 13.3 5.5
Exterior Lighting 19.6 19.6 19.6 19.6
Total Energy Consumption (MBTU) 355.7 389.6 322.9 820.3
Electrical Energy Cost $9,724 $10,649 $8,828 $8,680
Natural Gas Energy Cost $0 $0 $0 $6,033
Total Energy Cost $9,724 $10,649 $8,828 $14,713
Energy Consumption
Average (kbtu/sqft-yr)
14.44 15.82 13.11 33.29
Maximum Unmet Hours 0 heating
0 cooling
0 heating
0 cooling
0 heating
0 cooling
0 heating, 0 cooling
* All energy values shown in Table 5 are in MBTU (millions of BTU).
3 Life Cycle Cost Analysis Results
The BLCC5 40-year life cycle detailed LCC report for the proposed building design and the alternative building designs is provided in Appendix A. The 40-year life cycle costs are summarized in Table 7 below.
Table 7 – Proposed, Alternative 1 and Alternative 2 LCC Results
System LCCA 40-year Costs
Proposed: Ground Coupled WSHP $2,081,568
Alternative 1: HP Chiller VAV w/Reheat $2,307,853
Alternative 2: GCHP VAV w/Reheat $2,597,810
Table 8 – Performance Cost Index Compliance Path
Components
Proposed: Ground
Coupled WSHP
Alt 1: HP
Chiller VAV w/Reheat
Alt 2: GCHP
VAV w/Reheat
ASHRAE 90.1-2022
Appendix G System 5
BBP (Baseline Building
Performance) - - - $14,713
BBUEC (Baseline Building
Unregulated Energy Cost) - - - $22,430
BBREC (Baseline Building
Regulated Energy Cost) - - - $7,717
BPF (Building Performance
Factor) - - - 0.53 (Other)
PBP (Proposed Building
Performance) $9,724 $10,649 $8,828 -
PCI (Performance Cost Index) 0.66 0.72 0.60 -
PCIt (Performance Cost Index target) - - - 1.25
PI (Percentage Improvement
+30% = EPAct Compliance) 46.98% 41.94% 51.86% -
Page A1
Appendix A
BLCC5 LCC Analysis Results
Page A2
NIST BLCC 5.3-24: Summary LCC
Consistent with Federal Life Cycle Cost Methodology and Procedures, 10 CFR, Part 436, Subpart A
Page A3
Alternative: Proposed Ground Coupled WSHP
LCC Summary
Page A4
Alternative: HP Chiller VAV w/Reheat
Page A5
Alternative: GCHP VAV w/Reheat
Page B1
Appendix B
Escalation Rates
TABLE 9 – "REAL" ELECTRICAL ESCALATION
RATES
*"Real" Analysis does not include inflation.
From Date Duration Escalation
April 1, 2024 1 year 0 months -1.96%
April 1, 2025 1 year 0 months -2.06%
April 1, 2026 1 year 0 months -2.13%
April 1, 2027 1 year 0 months -1.70%
April 1, 2028 1 year 0 months -0.85%
April 1, 2029 1 year 0 months -0.40%
April 1, 2030 1 year 0 months 0.40%
April 1, 2031 1 year 0 months 0.20%
April 1, 2032 1 year 0 months 2.17%
April 1, 2033 1 year 0 months 1.37%
April 1, 2034 1 year 0 months -0.14%
April 1, 2035 1 year 0 months 0.47%
April 1, 2036 1 year 0 months 1.34%
April 1, 2037 1 year 0 months 1.65%
April 1, 2038 1 year 0 months 0.61%
April 1, 2039 1 year 0 months 0.53%
April 1, 2040 1 year 0 months -0.21%
April 1, 2041 1 year 0 months -0.26%
April 1, 2042 1 year 0 months -0.29%
April 1, 2043 1 year 0 months 0.11%
April 1, 2044 1 year 0 months 0.53%
April 1, 2045 1 year 0 months 0.08%
April 1, 2046 1 year 0 months -0.05%
April 1, 2047 1 year 0 months -0.45%
April 1, 2048 1 year 0 months -0.50%
April 1, 2049 1 year 0 months -0.90%
April 1, 2050 1 year 0 months -0.48%
April 1, 2051 1 year 0 months -0.49%
April 1, 2052 1 year 0 months -0.49%
April 1, 2053 1 year 0 months -0.46%
April 1, 2054 Remaining -0.57%
File details come from the government source that posted it. Updated .