PRICE PROPOSAL FORM
PROJECT 15182879_Pier Papa ReCAP, Charleston, SC
TASK ORDER ANNOUNCEMENT #:
Base Item: This project will construct new waterfront, shore structures and utility/supporting facilities required to homeport and berth 4 NSCs at Pier November (4 dedicated berths at Pier November). The scope of work includes, but is not limited to: demolition and replacement of the existing Pier November and of damaged bulkhead, removal and backfill of contaminated soils and removal of uncontaminated underwater released aggregate. Dredging will include spoils from between Piers Mike and Papa for constructing the new Pier November as well as the removal 3 pieces of submerged equipment in the area of the collapsed bulkhead. The construction includes a new Pier November, support facilities, site/groundwork and all associated utilities. New Shore Tie service requirements for electrical, potable water, fire protection, sewer, bilge water, and compressed air services will be provided for 4 NSCs at Pier November and bulkhead mooring. In addition, a new duct bank will be installed to provide C5IT connectivity between pier Papa and Pier Mike. The new work for this project will also involve additional paving of the ground surface to provide an access road to Pier November.
All future parking, buoy storage, and MAT Cutter Support Team (CST) requirements will be addressed by an on-going IDP/Master Plan. Provide all labor, material, equipment, mobilization, demobilization, permitting, construction support, quality control services, and ancillary items required for site development and construction, excluding items identified in Option Items.
Design (General): $ ______________
Design (Dredging): $ ______________
Design (Dredging plus $ ______________
(Equipment removal) $ ______________
Total Design Price: $ _____________________
Construction (General): $ ______________
Construction (Dredging): $ _____________
Construction (Dredging plus Equipment removal): $______________
Total Construction Price: $__________________
Contaminated Soil and Materials for Disposal: $__________________
Electrical Utility Connection Allowance: $ 100,000.00___
TOTAL BASE: $ _________________
The TOTAL BASE ITEMS shall be deemed to include all costs required for the specified work to be completed in accordance with the plans and specifications.
Option Item 0001: This option will construct one (1) NSC nested birth. The scope of work includes, but is not limited to: additional electrical shore tie, additional fenders to support double berthing,.
Bollards and cleat to support double berthing. Additional electrical, sanitary potable water and telecommunication runs. Provide all labor, material, equipment, mobilization, demobilization, permitting, construction support, quality control services, and ancillary items required to construct items identified in Option 0001.
Design Price: $ ______________
Construction Price: $ ______________
TOTAL OPTION 0001: $ ______________
Option Item 0002: This option will construct an additional 80 linear feet of pier at Pier November.
Provide all labor, material, equipment, mobilization, demobilization, permitting, construction support, quality control services, and ancillary items required to construct items identified in Option 0002.
Design Price: $ ______________
Construction Price: $ ______________
TOTAL PRICE
(Base Line Item 0001 plus Option Line Items 0001and 002): $ ______________