This document provides an amendment to a federal sources sought notice for the United States Coast Guard's National Multiple Award Construction Contract III. The USCG seeks small businesses capable of performing general construction, marine construction, renovation, alteration and repair projects on an IDIQ or DB/DBB basis for facilities in the 50 US states, Puerto Rico, Guam and the US Virgin Islands. The amendment answers questions from potential offerors to clarify that designers should indicate total fees received, that disciplines performed by subconsultants should be included, and that general contractors managed construction trades. It also confirms the proposal due date remains January 5, 2023.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
1 2
Facilities Design & Construction Center 5505 Robin Hood Rd, Suite K Norfolk, VA 23513
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
70Z04721RNMACC03
9B. DATED (SEE ITEM 11)
10/27/2022
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
0005 12/7/2022
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended.
is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
DEPARTMENT OF HOMELAND SECURITY/U.S. COAST GUARD NATIONAL MULTIPLE AWARD CONSTRUCTION
CONTRACT (NMACC III)
See Continuation Page. Proposal Due Date remains January 5, 2023.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
70Z04721RNMACC03
Continuation Page
This amendment provides answers to the following questions received.
END OF AMENDMENT
Questions and Answers (Numbering continued from Amendment 0004)
68. The Experience Information Form, B.2, item 16 states to attach copies or photos of awards/special recognition, etc.
(max of one page). Please confirm this page can be used for project photos?
Answer: Item 16 remains unchanged at this time.
69. Provide some clarification for what you are looking for on Question 11 of form B.2 of the USG NMACCIII project?
The question is shown as “If Design-Build, what percentage of the total design was provided by you”?
Answer: Block 11 actually states, If Design-Build, what percentage of the total design was provided to you.
If project being submitted to demonstrate experience is Design-Build, the Offeror shall indicate the percentage of total design provided in the project's solicitation.
70. Please see Tab 1 Factor 1, corporate Experience, Attachment A - Experience Overview Sheet. Please clarify the Offeror's share of responsibility for the total construction contract. For Designers is the intent to show the total fee received?
Answer: Correct, Designers shall indicate the total fee received.
71. Please see Tab 1 Factor 1, corporate Experience, Attachment B - Experience Information Form. Item #13, Should the designer also include disciplines that were not performed as the DOR but were completed by subconsultatnts who designed their portion of the work. For example if the permitting portion of the project was performed by a subconsultant should this work also be included in the Disciplines section?
Answer: Yes, include the disciplines performed by subconsultants. However, the offer shall indicate the disciples were through a subconsultant.
72. Please see Tab 1 Factor 1, corporate Experience, Attachment B - Experience Information Form. Item #15, As a designer of record on these projects in many cases the prime handled the subcontracts with the trades, should this section be filled out by the DOR submitted projects or is it adequate to say that the GC managed the trades?
Answer: This block is for Construction Trades. The designer of record may indicate the GC managed the trades.