This document provides an amendment to a solicitation for the USCG National Multiple Award Construction Contract (NMACC III). The amendment makes several changes to the evaluation criteria, including allowing offerors to utilize the experience of a key subcontractor on one construction project, increasing the page limit for the technical approach from ten to sixteen pages, and clarifying the use of design subcontractor experience. Offerors are invited to bid on general construction, marine construction, renovation, alteration and repair projects on an IDIQ basis for the USCG across the United States and its territories. The response due date remains December 5, 2022.

View the file

Other files

File Type Posted
70Z04721RNMACC03 AMEND 0011.pdf PDF
70Z04721RNMACC03 AMEND 0010.pdf PDF
70Z04721RNMACC03 SPECIAL NOTICE.docx DOCX document
70Z04721RNMACC03 AMEND 0009.pdf PDF
70Z04721RNMACC03 AMEND 0008.pdf PDF
70Z04721RNMACC03 AMEND 0007.pdf PDF
70Z04721RNMACC03 AMEND 0006.pdf PDF
70Z04721RNMACC03 AMEND 0005.pdf PDF
70Z04721RNMACC03 AMEND 0004.pdf PDF
ATTACHMENT C NMACC III - PPQ_NoWatermark.docx DOCX document
70Z04721RNMACC03 AMEND 0002.pdf PDF
Attachment B Experience Information Form_Rev1.docx DOCX document
70Z04721RNMACC03 AMEND 0001.pdf PDF
ATTACHMENT C NMACC III - PPQ.docx DOCX document
Attachment B Experience Information Form.docx DOCX document
Attachment A PPI-RFI.xlsx XLSX spreadsheet
70Z04721RNMACC03_SOL.pdf PDF
NMACC III SOURCES SOUGHT NOTICE ADDENDUM11.pdf PDF
NMACCIII_INDUSTRYDAY_REDACTED_PARTICIPANTS.pdf PDF
NMACC3ID2022.pdf PDF
NMACC III SOURCES SOUGHT NOTICE ADDENDUM10.pdf PDF
NMACC III SOURCES SOUGHT NOTICE ADDENDUM09.pdf PDF
DRAFTONLYNMACCIIISOLICITATIONDRAFT06162022.pdf PDF
Attachment A NMACC III DRAFT SOLICIT Pre-Proposal_Inquiry_Form.xlsx XLSX spreadsheet
USCG_NCSUMMITAPRILV12022.pdf PDF
NMACC II Awardees.pdf PDF
SILC BROCHURE_2022.pdf PDF
USCG_SAMEHRMARCH2022.pdf PDF
NMACC III SOURCES SOUGHT NOTICE ADDENDUM06.pdf PDF
NMACC III SOURCES SOUGHT NOTICE ADDENDUM05.pdf PDF
NMACC III SOURCES SOUGHT NOTICE ADDENDUM04.pdf PDF
NMACC III SOURCES SOUGHT ADDENDUM03QANDAS.pdf PDF
NMACC III SOURCES SOUGHT ADDENDUM02.pdf PDF
NMACC III SOURCES SOUGHT ADDENDUM01.pdf PDF
NMACC III SOURCES SOUGHT NOTICE 70Z04721RNMACC03.pdf PDF
ATTACHMENT D NMACC III SOURCES SOUGHT CONTRACTOR SURVEY FORM.pdf PDF
ATTACHMENT B SOURCES SOUGHT CONTRACTING INFO FORM.docx DOCX document
ATTACHMENT C SOURCES SOUGHT PROJECT INFO FORM.docx DOCX document
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

1 5

Facilities Design & Construction Center 5505 Robin Hood Rd, Suite K Norfolk, VA 23513

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

70Z04721RNMACC03

9B. DATED (SEE ITEM 11)

10/27/2022

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

0003 11/14/2022

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended.

is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

DEPARTMENT OF HOMELAND SECURITY/U.S. COAST GUARD NATIONAL MULTIPLE AWARD CONSTRUCTION

CONTRACT (NMACC III)

See Continuation Page. Proposal Due Date remains December 5, 2022.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

70Z04721RNMACC03

Continuation Page

The Solicitation is amended as follows:

I) Page 108, SUBCONTRACTOR – Clarification of Amendment 0001 and 0002

DELETE: SUBCONTRACTORS:

The Offeror may utilize the experience of a proposed key subcontractor to demonstrate construction experience for factor 1.1 - Construction; however, Offeror shall have acted as the prime contractor demonstrating meaningful involvement on submitted projects. In those instances where the Offeror is utilizing the key subcontractor experience, then the Offeror must also provide supporting documentation (such as partnership agreement, teaming agreement, or letter of commitment on the proposed partner/teaming letterhead) with both prime/subcontractor firm authorized signatures which demonstrates agreement by the proposed subcontractor for the entire duration of the NMACC III. If the agreement/letter is not provided or meaningful involvement in the performance of the NMACC III contract is not demonstrated, then the proposed subcontractor submitted project experience will not be considered and will be deemed “Not Relevant”.

REPLACE WITH: SUBCONTRACTORS:

The Offeror may utilize the experience of a proposed key subcontractor to demonstrate construction experience, on one (1) project submitted for factor 1.1 - Construction; however, the Key Subcontractor shall have acted as the prime contractor demonstrating meaningful involvement on submitted project. In those instances where the Offeror is utilizing the key subcontractor experience, then the Offeror shall also provide supporting documentation (such as partnership agreement, teaming agreement, or letter of commitment on the proposed partner/teaming letterhead) with both prime/subcontractor firm authorized signatures which demonstrates agreement by the proposed subcontractor for the entire duration of the NMACC III. If the agreement/letter is not provided or meaningful involvement in the performance of the NMACC III contract is not demonstrated, then the proposed subcontractor submitted project experience will not be considered and will be deemed “Not Relevant”.

II) Factor 1, Subfactor 1.2 Design Experience

DELETE: The Offeror may utilize experience of a design subcontractor as the DOR in order to demonstrate design experience under this evaluation factor. The Offer must provide a supporting documentation (such as: JV agreement, partnership agreement, teaming agreement, or letter of commitment on official letter head and signed by the proposed design firm(s) with an explanation of the meaningful involvement for the design subcontractor. If the agreement/letter is not provided or meaningful involvement is not demonstrated, experience of the proposed designer will not be considered.

REPLACE WITH: The Offeror may utilize experience of a design subcontractor as the DOR in order to demonstrate design experience under this evaluation factor. The Offer shall provide a supporting documentation (such as: JV agreement, partnership agreement, teaming agreement, or letter of commitment on official letter head and signed by the proposed design firm(s) with an explanation of the meaningful involvement for the design subcontractor. If the agreement/letter is not provided or meaningful involvement is not demonstrated, experience of the proposed designer will not be considered.

III) Page 111, Factor 2 Technical Approach, Paragraph a.

DELETE: The narrative plan shall not exceed ten (10) single-sided pages or five (5) double sided pages.

Information beyond the ten (10) page limit will not be considered with the exception of the organizational chart.

REPLACE WITH: The narrative plan shall not exceed sixteen (16) single-sided pages or eight (8) double sided pages. Information beyond the sixteen (16) single-sided pages or eight (8) double sided pages limit will not be considered with the exception of the organizational chart.

END OF AMENDMENT

QUESTIONS AND ANSWERS (numbering continued from Amendment 0002)

32. Factor 1: With Amendment 0002, Relevant design projects are now described as "Projects submitted for the Offeror shall have been completed within eight (8) years of the date of issuances of this RFP; however, ongoing projects within the same dollar range may be submitted, provided that design is 100% complete and construction duration to date has exceeded one year." [Amendment 0002] and "Design projects submitted for the DOR(s) shall have been completed within the previous eight (8) years prior to the date of issuance of this RFP. For design-build projects, the design portion of the contract shall have been completed in the previous eight (8) years prior to the date of issuance of this RFP." [Remaining in original RFP]. Can you please confirm that Design-Build projects will be acceptable if the design portion is complete whether or not the project is in construction or has a minimum construction duration of one year?

Answer: Per Amendment 0002, Experience with design-build (at least four (4) projects). Projects submitted for the Offeror shall have been completed within eight (8) years of the date of issuances of this RFP; however, ongoing projects within the same dollar range may be submitted, provided that design is 100% complete and construction duration to date has exceeded one year.

33. Factor 1: If construction of a submitted design project has not received a bid and/or is not in construction, can the cost estimate be used to satisfy the project size requirement (i.e cost estimate >$25M or >$50M but has not received bids)?

Answer: For Design-Bid-Build projects, with a completed design but bid has not been received the estimated cost may be used to satisfy the project size

34. Seeking clarification on RFI responses included in Amendment 1 and Amendment 2. Both RFI’s are related to Offerors utilizing experience of proposed key subcontractors to demonstrate construction experience in Factor

1.1. It is clear an agreement, in writing, is required for proposed Key Subcontractors. What is not clear in the RFI responses is the acceptable capacity in which the Key Subcontractor’s experience was contracted. Please confirm an Offeror may use the experience of a Key Subcontractor in the NMACC III proposal if the Key Subcontractor’s experience was performed as a Prime Contractor.

Answer: See Amendment Language

35. Attachment B.2: The Attachment B.2 Experience Information Form section 15 requests us to list the construction trades, subcontractor and brief work description. Some projects can have over 20 – 30 trades resulting in 2-3 pages just to answer section 15. Please increase the Experience Information Form page count from 4 pages to 6 pages to cover section 15.

Answer: The Government does not anticipate a change in page limit at this time

36. Factor 3 Past Performance: Factor 3: Past Performance. CCASS or CPARS are not available to a design firm of a design-build project since they are issued to the design-build contractor whom the Government had the contract with. If the Offeror’s design firm proposes a design-build project in Factor 1, should the design firm get a PPQ from the design-build contractor with whom they had the contract with? Confirm this will satisfy the design firm Factor 3: Past Performance requirements?

Answer: Confirmed. If a CPARS/CCASS/ACASS is not available, a PPQ for the Design firm will satisfy the design firms past performance requirement.

37. Please confirm that teaming agreements, table of contents, tabs, cover letter, cover sheet, Reps and Certs, SF 1442, SF 30, and surety bonding letter are not part of the proposal page count?

Answer: Confirmed, teaming agreements, table of contents, tabs, cover letter, cover sheet, Reps and Certs, SF 1442, SF 30, and surety bonding letter are not part of the proposal page count

38. Factor 2 Technical Approach: Factor 2 Technical Approach requests an abundance of information but is restricted to a 10 page count limit. For us to detail our Management Approach and commitment to the NMAC III adequately responding to all the listed minimal requirements, 10 pages is not sufficient. Please consider increasing the page count to 20 pages for us to provide the Government our best technical approach.

39. Amendment 0002, Factor 1: Amendment 0002 replaced portion of Factor 1, Subfactor 1.2 Design Experience specifically d) stating design projects need to have construction duration exceeding one year. The following paragraph states for DB projects, only the design needs to be completed within 8 years. Please correct section d) to reflect that only the design needs to be complete within 8 years for Designer design-build projects.

Answer: Per Amendment 0002, Experience with design-build (at least four (4) projects). Projects submitted for the Offeror shall have been completed within eight (8) years of the date of issuances of this RFP; however, ongoing projects within the same dollar range may be submitted, provided that design is 100% complete and construction duration to date has exceeded one year.

40. Attachment B: For construction experience, please confirm Prime should leave box 13 (on Attachment B Experience Information Form) on design disciplines blank for design-bid-build projects where there was no design.

Answer: Prime should list the firm developing the design in Box 13

41. Factor 2: The previous NMACC II solicitation gave NMACC II Offerors a total of 14-pages combined to discuss the elements "Organizational Structure," "Capacity," and "D/B Management" as three separate factors. In this NMACC III solicitation, the CG is asking Bidders to address the elements "Organizational Structure," "Capacity," and "D/B Management" as one Factor within a total of 10-pages only. Please consider allowing NMACC III Offerors a total of 15-pages to comprehensively address the required elements of the Factor 2 Technical Approach narrative.

42. Factor 1: Please confirm offerors can include projects by key construction subcontractors as long as we include a Letter of Commitment signed by both firms.

43. Page 108: Page 108 of the RFP states in the SUBCONTRACTORS paragraph, "The Offeror may utilize the experience of a proposed key subcontractor to demonstrate construction experience for factor 1.1 - Construction;

however, Offerors shall have acted as the prime contractor..." Please confirm that this should state, "SUBCONTRACTORS shall have acted as the prime contractor on submitted subcontractor projects."

44. Can the Government please confirm we can alter the “Attachment B Experience Information Form” with headers, footers, and page numbers.

Answer: Offeror may alter Attachment B with headers, footers, and page numbers as long as page limit is adhered.

45. If an offeror is providing a letter of commitment for design firms who will be utilized as the DOR, does the government have a Letter of Commitment Template they would like us to use?

Answer: The Government does not have a Letter of Commitment Template. Offeror may use their own template.

46. Box 6 on Attachment B.2 - Experience Information Form requests the contract duration. Please advise if this duration should be in date format (award to completion date) or if it should state the duration as the total number of days.

Answer: Contract Duration shall be in date format.

47. The submission requirements for Factor 2 Technical Approach are significant. The stated limit of 10 pages appears to be insufficient for a thorough response. Would the Government consider increasing the page limit to 15 pages, inclusive of the organizational chart?

48. The Factor 2 Technical Approach requires a significant amount of information to be described between the Organizational Structure, Capacity, and Design-Build Management sections. The Design-Build Management section itself is specifically broken down into several parts which require a large amount of space to respond to.

Would the USCG please consider extending the page limit for this Factor from 10 to 20 single sided pages to allow necessary space to properly respond to each section?

49. Can the government please confirm if a Bid Bond is required for the Phase I submittal?

Answer: A Bid Bond is not required for Phase I

50. The government requires a "formal letter from its bonding company". Does this count to the page count for Factor 2? If so, can that be changed so that it does not take away from our Technical Approach page count?

Answer: As the letter from the bonding company is to be provided with the Cover Letter, SF1442, etc, as outlined in L.2, the letter does not count against the page count under Factor 2.