This document is a Questions and Answers response from the United States Coast Guard regarding solicitation 70Z03826QS0000014, with answers provided on September 1, 2026.

The document addresses a single question concerning the mandatory site visit requirement for quotation submission. The USCG clarifies that because the site visit is mandatory for a quotation to be considered technically acceptable, verification must be provided that the site visit was attended by an employee of the prime contractor or an authorized agent of the prime contractor. The response does not explicitly state whether a prior documented site visit attended by a proposed subcontractor satisfies the requirement or whether the prime contractor must conduct a new site visit registered under the prime's name. However, the emphasis on verification of prime contractor or authorized agent attendance implies that a prior subcontractor site visit would not satisfy the requirement; the prime contractor or its authorized representative must complete the site visit and visitor request process.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

70Z03826QS0000014

Responses to Questions

Answers provided September 1, 2026

This document provides United States Coast Guard (USCG) responses for questions that have been asked regarding solicitation 70Z03826QS0000014. Question numbers are provided simply as a reference and in no way infer a prioritization of the questions.

Number Question USCG Response

1 Because the solicitation requires a mandatory site visit prior to quotation submission, please clarify whether a prior documented site visit attended by a proposed subcontractor satisfies the mandatory site visit requirement, or whether the prime contractor must have a representative attend a new site visit specifically registered under the prime’s name and complete the visitor request process again.

Because the site visit is mandatory for a quotation to be considered technically acceptable, please confirm whether the U.S.

Coast Guard requires verification that the site visit was attended by an employee of the prime contractor or an authorized agent of the prime contractor.