This document is a contract amendment (Amendment 0003) for a transportation services contract with the Federal Law Enforcement Training Centers (FLETC) in Artesia, New Mexico. The amendment covers a five-year period from 07/01/2025 to 09/30/2029, with a base year and four option years, and includes multiple fixed-price line items for services such as project management, dispatch, vehicle cleaning, transportation hours (routine, recreation, and tours), vehicle maintenance, and fuel support.
Key dates include a question deadline of 3/14/2025 at 2 PM ET, questions answered by 3/20/2025, and Phase One due date of 3/24/2025 at 2 PM ET. Transportation services will prioritize Government Furnished Property (GFP) buses as the primary transportation method, with contractor-provided transportation supporting remaining requirements. The contract includes not-to-exceed amounts for SCWR and Emergency Fuel, with reimbursement at invoiced cost and no markup for overhead or profit. Each option year has an anticipated exercise date of the first of the month preceding the new performance period, with consistent service categories across all years.
View the file
Other files
Show 40 more
Latest 50 of 70 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
70LART25RPFB00007
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
70LART
ARTESIA NM 88210
1300 W RICHEY AVE
FEDERAL LAW ENFORCEMENT TRAINING CENTERS
DEPARTMENT OF HOMELAND SECURITY
02/13/20250003
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
02/14/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is for updates in FAR via executive orders. Prospective offerors should reread the requirement document “clauses and provisions”, with an emphasis
Performance Work Statement, period of performance date changes (due to fiscal availability of funds), and technical evaluation. Question Deadline 3/14/2025 2PM ET, Questions Answered
3/20/2025, and Phase One due date 3/24/2025 2PM ET.
07/01/2025-09/30/2025
OY 1 10/01/2025-09/30/2026,
OY 2, 10/01/2026-09/30/2027
OY 3, 10/01/2027-09/30/2028
OY 4 10/01/2028-09/30/2029
Period of Performance: 07/01/2025 to 09/30/2026
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Nicholas J. Antal
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
70LART25RPFB00007/0003
Change Item 0001 to read as follows(amount shown is the total amount):
0001 Fixed Price Project Management
Base Year 07/01/2025-09/30/2025
PWS REFERENCE: PARAGRAPH C.1, C.1.7
Period of Performance: 07/01/2025 to 09/30/2025
Change Item 0002 to read as follows(amount shown is the total amount):
0002 Fixed Price Dispatch
Base Year 07/01/2025-09/30/2025
PWS REFERENCE: PARAGRAPH C.2.2
Period of Performance: 07/01/2025 to 09/30/2025
Change Item 0003 to read as follows(amount shown is the total amount):
0003 Fixed Price Vehicle Cleaning
Base Year 07/01/2025-09/30/2025
Period of Performance: 07/01/2025 to 09/30/2025
Change Item 0004 to read as follows(amount shown is the total amount):
0004 Fixed Price Transportation Hours-Routine
Base Year 07/01/2025-09/30/2025
GFP buses will be the primary method of transportation, contractor provided transports will support all remaining requirements.
Priority:
1st GFP buses
2nd Contractor provided transportation
Period of Performance: 07/01/2025 to 09/30/2025
Change Item 0005 to read as follows(amount shown is the total amount):
0005 Fixed Price Transportation Hours-Recreation
Base Year 07/01/2025-09/30/2025
GFP buses will be the primary method of
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
3 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
70LART25RPFB00007/0003
transportation, contractor provided transports will support all remaining requirements.
Priority:
1st GFP buses
2nd Contractor provided transportation
Period of Performance: 07/01/2025 to 09/30/2025
Change Item 0006 to read as follows(amount shown is the total amount):
0006 Fixed Price Transportation Hours-Tours
Base Year 07/01/2025-09/30/2025
GFP buses will be the primary method of transportation, contractor provided transports will support all remaining requirements.
Priority:
1st GFP buses
2nd Contractor provided transportation
Period of Performance: 07/01/2025 to 09/30/2025
Change Item 0007 to read as follows(amount shown is the total amount):
0007 Firm Fixed Price Vehicles, Maintenance and
Supplies
Base Year 07/01/2025-09/30/2025
Period of Performance: 07/01/2025 to 09/30/2025
Change Item 0008 to read as follows(amount shown is the total amount):
0008 SCWR and ER Fuel
Base Year 07/01/2025-09/30/2025
Not to exceed $20,000.00 SCWR
SCWR
Not to exceed $8,000.00 Emergency Fuel
Clin is for misc. supplies and services in support of the various functional areas and reimbursed at invoiced cost with no markup for overhead, G&A or profit. Vendor invoices are to be submitted with the monthly invoice.
Period of Performance: 07/01/2025 to 09/30/2025
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
4 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
70LART25RPFB00007/0003
Change Item 1001 to read as follows(amount shown is the total amount):
1001 Fixed Price Project Management
Option Year 10/01/2025-09/30/2026
PWS REFERENCE: PARAGRAPH C.1, C.1.7
(Option Line Item)
Anticipated Option Exercise Date 09/01/2025
Period of Performance: 10/01/2025 to 09/30/2026
Change Item 1002 to read as follows(amount shown is the total amount):
1002 Fixed Price Dispatch
Option Year One 10/01/2025-09/30/2026
PWS REFERENCE: PARAGRAPH C.2.2
(Option Line Item)
Anticipated Option Exercise Date 09/01/2025
Period of Performance: 10/01/2025 to 09/30/2026
Change Item 1003 to read as follows(amount shown is the total amount):
1003 Fixed Price Vehicle Cleaning
Option Year One 10/01/2025-09/30/2026
(Option Line Item)
Anticipated Option Exercise Date 09/01/2025
Period of Performance: 10/01/2025 to 09/30/2026
Change Item 1004 to read as follows(amount shown is the total amount):
1004 Fixed Price Transportation Hours-Routine
Option Year One 10/01/2025-09/30/2026
GFP buses will be the primary method of transportation, contractor provided transports will support all remaining requirements.
Priority:
1st GFP buses
2nd Contractor provided transportation
(Option Line Item)
Anticipated Option Exercise Date 09/01/2025
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
5 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
70LART25RPFB00007/0003
Period of Performance: 10/01/2025 to 09/30/2026
Change Item 1005 to read as follows(amount shown is the total amount):
1005 Fixed Price Transportation Hours-Recreation
Option Year One 10/01/2025-09/30/2026
GFP buses will be the primary method of transportation, contractor provided transports will support all remaining requirements.
Priority:
1st GFP buses
2nd Contractor provided transportation
(Option Line Item)
Anticipated Option Exercise Date 09/01/2025
Period of Performance: 10/01/2025 to 09/30/2026
Change Item 1006 to read as follows(amount shown is the total amount):
1006 Fixed Price Transportation Hours-Tours
Option Year One 10/01/2025-09/30/2026
GFP buses will be the primary method of transportation, contractor provided transports will support all remaining requirements.
Priority:
1st GFP buses
2nd Contractor provided transportation
(Option Line Item)
Anticipated Option Exercise Date 09/01/2025
Period of Performance: 10/01/2025 to 09/30/2026
Change Item 1007 to read as follows(amount shown is the total amount):
1007 Firm Fixed Price Vehicles, Maintenance and
Supplies
Option Year One 10/01/2025-09/30/2026
(Option Line Item)
Anticipated Option Exercise Date 09/01/2025
Period of Performance: 10/01/2025 to 09/30/2026
Change Item 1008 to read as follows(amount shown is the total amount):
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
6 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
70LART25RPFB00007/0003
1008 SCWR and ER Fuel
Option Year One 10/01/2025-09/30/2026
Not to exceed $20,000.00 SCWR
SCWR
Not to exceed $8,000.00 Emergency Fuel
Clin is for misc. supplies and services in support of the various functional areas and reimbursed at invoiced cost with no markup for overhead, G&A or profit. Vendor invoices are to be submitted with the monthly invoice.
(Option Line Item)
Anticipated Option Exercise Date 09/01/2025
Period of Performance: 10/01/2025 to 09/30/2026
Change Item 2001 to read as follows(amount shown is the total amount):
2001 Fixed Price Project Management
Option Year Two 10/01/2026-09/30/2027
PWS REFERENCE: PARAGRAPH C.1, C.1.7
(Option Line Item)
Anticipated Option Exercise Date 09/01/2026
Period of Performance: 10/01/2026 to 09/30/2027
Change Item 2002 to read as follows(amount shown is the total amount):
2002 Fixed Price Dispatch
Option Year Two 10/01/2026-09/30/2027
PWS REFERENCE: PARAGRAPH C.2.2
(Option Line Item)
Anticipated Option Exercise Date 09/01/2026
Period of Performance: 10/01/2026 to 09/30/2027
Change Item 2003 to read as follows(amount shown is the total amount):
2003 Fixed Price Vehicle Cleaning
Option Year Two 10/01/2026-09/30/2027
(Option Line Item)
Anticipated Option Exercise Date 09/01/2026
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
7 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
70LART25RPFB00007/0003
Period of Performance: 10/01/2026 to 09/30/2027
Change Item 2004 to read as follows(amount shown is the total amount):
2004 Fixed Price Transportation Hours-Routine
Option Year Two 10/01/2026-09/30/2027
GFP buses will be the primary method of transportation, contractor provided transports will support all remaining requirements.
Priority:
1st GFP buses
2nd Contractor provided transportation
(Option Line Item)
Anticipated Option Exercise Date 09/01/2026
Period of Performance: 10/01/2026 to 09/30/2027
Change Item 2005 to read as follows(amount shown is the total amount):
2005 Fixed Price Transportation Hours-Recreation
Option Year Two 10/01/2026-09/30/2027
GFP buses will be the primary method of transportation, contractor provided transports will support all remaining requirements.
Priority:
1st GFP buses
2nd Contractor provided transportation
(Option Line Item)
Anticipated Option Exercise Date 09/01/2026
Period of Performance: 10/01/2026 to 09/30/2027
Change Item 2006 to read as follows(amount shown is the total amount):
2006 Fixed Price Transportation Hours-Tours
Option Year Two 10/01/2026-09/30/2027
GFP buses will be the primary method of transportation, contractor provided transports will support all remaining requirements.
Priority:
1st GFP buses
2nd Contractor provided transportation
(Option Line Item)
Anticipated Option Exercise Date 09/01/2026
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
8 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
70LART25RPFB00007/0003
Period of Performance: 10/01/2026 to 09/30/2027
Change Item 2007 to read as follows(amount shown is the total amount):
2007 Firm Fixed Price Vehicles, Maintenance and
Supplies
Option Year Two 10/01/2026-09/30/2027
(Option Line Item)
Anticipated Option Exercise Date 09/01/2026
Period of Performance: 10/01/2026 to 09/30/2027
Change Item 2008 to read as follows(amount shown is the total amount):
2008 SCWR and ER Fuel
Option Year Two 10/01/2026-09/30/2027
Not to exceed $20,000.00 SCWR
SCWR
Not to exceed $8,000.00 Emergency Fuel
Clin is for misc. supplies and services in support of the various functional areas and reimbursed at invoiced cost with no markup for overhead, G&A or profit. Vendor invoices are to be submitted with the monthly invoice.
(Option Line Item)
Anticipated Option Exercise Date 09/01/2026
Period of Performance: 10/01/2026 to 09/30/2027
Change Item 3001 to read as follows(amount shown is the total amount):
3001 Fixed Price Project Management
Option Year Three 10/01/2027-09/30/2028
PWS REFERENCE: PARAGRAPH C.1, C.1.7
(Option Line Item)
Anticipated Option Exercise Date 09/01/2027
Period of Performance: 10/01/2027 to 09/30/2028
Change Item 3002 to read as follows(amount shown is the total amount):
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
9 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
70LART25RPFB00007/0003
3002 Fixed Price Dispatch
Option Year Three 10/01/2027-09/30/2028
PWS REFERENCE: PARAGRAPH C.2.2
(Option Line Item)
Anticipated Option Exercise Date 09/01/2027
Period of Performance: 10/01/2027 to 09/30/2028
Change Item 3003 to read as follows(amount shown is the total amount):
3003 Fixed Price Vehicle Cleaning
Option Year Three 10/01/2027-09/30/2028
(Option Line Item)
Anticipated Option Exercise Date 09/01/2027
Period of Performance: 10/01/2027 to 09/30/2028
Change Item 3004 to read as follows(amount shown is the total amount):
3004 Fixed Price Transportation Hours-Routine
Option Year Three 10/01/2027-09/30/2028
GFP buses will be the primary method of transportation, contractor provided transports will support all remaining requirements.
Priority:
1st GFP buses
2nd Contractor provided transportation
(Option Line Item)
Anticipated Option Exercise Date 09/01/2027
Period of Performance: 10/01/2027 to 09/30/2028
Change Item 3005 to read as follows(amount shown is the total amount):
3005 Fixed Price Transportation Hours-Recreation
Option Year Three 10/01/2027-09/30/2028
GFP buses will be the primary method of transportation, contractor provided transports will support all remaining requirements.
Priority:
1st GFP buses
2nd Contractor provided transportation
(Option Line Item)
Anticipated Option Exercise Date 09/01/2027
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
10 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
70LART25RPFB00007/0003
Period of Performance: 10/01/2027 to 09/30/2028
Change Item 3006 to read as follows(amount shown is the total amount):
3006 Fixed Price Transportation Hours-Tours
Option Year Three 10/01/2027-09/30/2028
GFP buses will be the primary method of transportation, contractor provided transports will support all remaining requirements.
Priority:
1st GFP buses
2nd Contractor provided transportation
(Option Line Item)
Anticipated Option Exercise Date 09/01/2027
Period of Performance: 10/01/2027 to 09/30/2028
Change Item 3007 to read as follows(amount shown is the total amount):
3007 Firm Fixed Price Vehicles, Maintenance and
Supplies
Option Year Three 10/01/2027-09/30/2028
(Option Line Item)
Anticipated Option Exercise Date 09/01/2027
Period of Performance: 10/01/2027 to 09/30/2028
Change Item 3008 to read as follows(amount shown is the total amount):
3008 SCWR and ER Fuel
Option Year Three 10/01/2027-09/30/2028
Not to exceed $20,000.00 SCWR
SCWR
Not to exceed $8,000.00 Emergency Fuel
Clin is for misc. supplies and services in support of the various functional areas and reimbursed at invoiced cost with no markup for overhead, G&A or profit. Vendor invoices are to be submitted with the monthly invoice.
(Option Line Item)
Anticipated Option Exercise Date 09/01/2027
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
11 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
70LART25RPFB00007/0003
Period of Performance: 10/01/2027 to 09/30/2028
Change Item 4001 to read as follows(amount shown is the total amount):
4001 Fixed Price Project Management
Option Year Four 10/01/2028-09/30/2029
PWS REFERENCE: PARAGRAPH C.1, C.1.7
(Option Line Item)
Anticipated Option Exercise Date 09/01/2028
Period of Performance: 10/01/2028 to 09/30/2029
Change Item 4002 to read as follows(amount shown is the total amount):
4002 Fixed Price Dispatch
Option Year Four 10/01/2028-09/30/2029
PWS REFERENCE: PARAGRAPH C.2.2
(Option Line Item)
Anticipated Option Exercise Date 09/01/2028
Period of Performance: 10/01/2028 to 09/30/2029
Change Item 4003 to read as follows(amount shown is the total amount):
4003 Fixed Price Vehicle Cleaning
Option Year Four 10/01/2028-09/30/2029
(Option Line Item)
Anticipated Option Exercise Date 09/01/2028
Period of Performance: 10/01/2028 to 09/30/2029
Change Item 4004 to read as follows(amount shown is the total amount):
4004 Fixed Price Transportation Hours-Routine
Option Year Four 10/01/2028-09/30/2029
GFP buses will be the primary method of transportation, contractor provided transports will support all remaining requirements.
Priority:
1st GFP buses
2nd Contractor provided transportation
(Option Line Item)
Anticipated Option Exercise Date 09/01/2028
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
12 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
70LART25RPFB00007/0003
Period of Performance: 10/01/2028 to 09/30/2029
Change Item 4005 to read as follows(amount shown is the total amount):
4005 Fixed Price Transportation Hours-Recreation
Option Year Four 10/01/2028-09/30/2029
GFP buses will be the primary method of transportation, contractor provided transports will support all remaining requirements.
Priority:
1st GFP buses
2nd Contractor provided transportation
(Option Line Item)
Anticipated Option Exercise Date 09/01/2028
Period of Performance: 10/01/2028 to 09/30/2029
Change Item 4006 to read as follows(amount shown is the total amount):
4006 Fixed Price Transportation Hours-Tours
Option Year Four 10/01/2028-09/30/2029
GFP buses will be the primary method of transportation, contractor provided transports will support all remaining requirements.
Priority:
1st GFP buses
2nd Contractor provided transportation
(Option Line Item)
Anticipated Option Exercise Date 09/01/2028
Period of Performance: 10/01/2028 to 09/30/2029
Change Item 4007 to read as follows(amount shown is the total amount):
4007 Firm Fixed Price Vehicles, Maintenance and
Supplies
Option Year Four 10/01/2028-09/30/2029
(Option Line Item)
Anticipated Option Exercise Date 09/01/2028
Period of Performance: 10/01/2028 to 09/30/2029
Change Item 4008 to read as follows(amount shown is the total amount):
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
13 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
70LART25RPFB00007/0003
4008 SCWR and ER Fuel
Option Year Four 10/01/2028-09/30/2029
Not to exceed $20,000.00 SCWR
SCWR
Not to exceed $8,000.00 Emergency Fuel
Clin is for misc. supplies and services in support of the various functional areas and reimbursed at invoiced cost with no markup for overhead, G&A or profit. Vendor invoices are to be submitted with the monthly invoice.
(Option Line Item)
Anticipated Option Exercise Date 09/01/2028
Period of Performance: 10/01/2028 to 09/30/2029
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
File details come from the government source that posted it. Updated .