This is a Questions and Answers document for the federal contract opportunity CO FTNP ROMO 407(1) Holzwarth Culvert, issued across three dates in October 2026. The document addresses clarifications from contractors regarding project requirements, site conditions, and specifications for a bridge culvert construction project located in Rocky Mountain National Park.

Key project clarifications include: material disposal from grubbing and road widening must follow FP-24 section 201.06 and SCR section 650.07 respectively; no water from the river is available for dust control or road conditioning, and no water sources exist within the park for contractor use; contractors will receive park passes waiving entrance fees and timed-entry reservations but cannot stay in campers on site or use park bathrooms during construction. Technical specifications address anchor bolt installation methods (cast-in-place or drilled and epoxied with submittal approval), superstructure load ratings per SCR section 555.03, and micropile testing requirements referencing FP-24 sections 567.06. The prefabricated modular steel vehicular bridge (10' wide × 48' long) is typically delivered fully assembled minus railings and may arrive in multiple longitudinal modules requiring field connection. Dewatering is subsidiary and not separately paid. Bid schedule includes 20 hours of survey services per FP-24 section 152. The bid date was extended one week per Amendment A001. Ground-disturbing activities cannot begin before August 2, 2027, with details in Amendment A001 clarifying which preparatory work (material delivery, fabrication, surveying, mobilization, traffic control) may occur prior to that date. The Geotechnical Report dated April 2026 is available on sam.gov.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for

CO FTNP ROMO 407(1) HOLZWARTH CULVERT

October 9, 2026

Questions Answers 1 Can the material grubbed from the project remain on site or will it need to be hauled off?

Refer to FP-24 section 201.06 for clearing and grubbing disposal.

2 Can the material used for the road widening be left, or will it need to be reclaimed?

Refer to SCR section 650.07 for roadway widening removal requirements.

3 Is there a power supply near by for the office trailer? Refer to the plans and SCR section 107-2 for utility information near the project.

4 Will a lab trailer be required? Refer to SCR section 154.04B for laboratory requirements.

5 Can you provide more detail or description of what is needed for the remove and reset of the diversion structure? Is this reset as more of a monument structure?

Refer to plan sheets S12 and S13 in the plans and section 203 of the FP-24 and SCRs for diversion structure information.

6 What permits, if any, is the contractor responsible for obtaining? Refer to SCR and FP-24 section 107 for permit requirements.

7 Is a certified steel erector going to be required for this project? Refer to SCR and FP-24 section 555.18 for steel structure erection requirements.

October 12, 2026

Questions Answers 8 Can the contractor use water from the river for dust control, and road conditioning?

No

9 If water from the river is not available, is there a water source nearby?

There are no water sources within Rocky Mountain National Park that are available for use.

10 Will the contractors be permitted to stay in campers at the site? No 11 Will the bathrooms remain open during construction? No 12 How will the reservation into the park effect construction? Will the contractor be required to purchase permits to enter the park?

Contractors working on the project will receive a pass from Rocky Mountain National Park, waiving standard entrance fees and timed-entry reservation requirements.

October 13, 2026

13 Page 20 States government to provide electrical and telephone conduit. Does this include hangers bolted to structural steel?

This does not include hangers.

14 Is there a source for power for the Field Office on site? Refer to the plans and SCR section 107-2 for utility information near the project.

15 Salvage items in removed diversion box what address items to be delivered to?

Refer to plan sheets S12 and S13 in the plans and section 203 of the FP-24 and SCRs for diversion structure information.

16 Extend the bid date one (1) week per sub-contractors and suppliers request?

See Amendment A001.

17 Diverting the Colorado River around the existing channel, or must the diverting have to stay within the existing channel?

Refer to SCR and FP-24 section 628 for temporary stream diversion requirements.

18 New anchor bolts (ps 20) in abutment have to be placed or embedded in concrete or can they be drilled and epoxy grouted after concrete placement.

Anchor bolts may be either cast in place or drilled and epoxied. For epoxied installations a submittal with calculations verifying embedment and material certs will be required for approval.

19 What is the load rating for the Superstructure? Refer to SCR section 555.03 for required superstructure load rating.

20 Is the Owner open to any Value Engineering for the

Superstructure for an alternate design?

No. Bid as specified within the plans and specifications.

21 What is the desired seed mix? Refer to SCR section 105.02(a).

22 Is dewatering included with the Temporary Stream Diversion item and how will dewatering be paid for?

Dewatering will not be paid for directly and is subsidiary.

23 What is the anticipated start date for the project and if the start time frame is this year when will a winter shut down be considered (what timeframe will the winter shut down be considered).

Refer to SCR section 105.02(a) for restrictions on work and completion date.

24 The bid schedule includes one verification test and two proof load tests. Please confirm whether these tests are to be performed on the six production micropiles or whether additional sacrificial/test micropiles are required.

Refer to FP-24 sections 567.06 for testing requirements.

25 The foundation plans and Specs Sheet E-1, reference the Final Geotechnical Report, Holzwarth Bridge, dated April 2026, prepared by CFLHD Geotechnical Services. Can you provide this Geotech report. If it isn’t available, are there any assumptions we should be making in our estimate?

The Geotech Report is available on project solicitation on sam.gov

26 The bid schedule identifies a 10' wide × 48' long prefabricated modular steel vehicular bridge. Please confirm whether the contractor may have the bridge delivered to the site fully assembled, or whether field assembly at the project site is anticipated/required

Typically these prefabricated bridges are delivered to the site fully assembled (minus railings) and may come in 2 or more longitudinal modules which are field connected. This is usually determined by hauling limits and site access limitations.

27 May the designated temporary truck turnaround area (Plan Sheet D-1) also be used for crane setup, bridge assembly, material staging, temporary stockpiling, office trailers and bridge erection?

Refer to SCR and FP-24 section 104 for control of work, 105 for control of material, section 555 for steel structure, and section 637 for office trailer requirements.

28 The bid schedule carries 20 hours of survey services. Is there a survey tabulation that shows contractor required survey elements?

Refer to FP-24 section 152 for construction survey and staking requirements.

29 Are there any items of the existing removed features that must be provided to the owner or are all removals the contractors responsibility?

Refer to the SCRs removal salvage or storage requirements.

30 Please confirm what items would be considered ground-disturbing activities that may only begin after August 2, 2027 per the specs.

For instance, can material delivery, bridge fabrication, surveying, mobilization, traffic-control setup, or prefabrication occur before that date?

Refer to Amendment A001.