This document is an Amendment to Solicitation 697DCK-24-R-00596 issued by the Department of Transportation Federal Aviation Administration Southwestern Region. The purpose of Amendment 02 is to update several key dates related to the solicitation:

  1. The site visit date has been changed to October 29, 2024 at 0900ET. Interested parties must submit attendance information by October 25, 2024.
  2. The deadline for submitting questions has been updated to November 06, 2024 by 1200ET.
  3. The proposal due date has been changed to November 29, 2024 at 1200ET. Proposals received after this time will be deemed non-responsive.

All other terms and conditions of the solicitation remain unchanged. The solicitation is for an Upgraded HVAC and Fire Life Safety Project at the Air Traffic Control Tower in Portland, ME, which includes replacing chillers, boilers, pumps, air handling units, and building automation controls, as well as roof and other related work.

View the file

Other files

File Type Posted
697DCK-24-R-00596_Amendment 07.pdf PDF
697DCK-24-R-00596_Amendment 06.pdf PDF
J-8_UPDATED QA for PWM HVAC and Fire Alarm_12_16_2024.pdf PDF
J-13_20241213_102801.jpg JPG image
J-14_20241213_102844.jpg JPG image
J-9_20241213_101951.jpg JPG image
J-11_20241213_102043.jpg JPG image
J-17_20241213_103520.jpg JPG image
697DCK-24-R-00596_Amendment 05.pdf PDF
J-18_20241213_104733.jpg JPG image
J-10_20241213_102014.jpg JPG image
J-19_PWM Plot layout with staging area and offices shown.pdf PDF
J-20_Utility Site Plan pwm-d-atct-c110-bl.pdf PDF
J-12_20241213_102514.jpg JPG image
J-16_20241213_103308.jpg JPG image
J-15_20241213_103246.jpg JPG image
J-6_PWM HVAC ADENDUM NOTES LIST.pdf PDF
J-5_Mobile_Office_PS1.pdf PDF
697DCK-24-R-00596_Amendment 04.pdf PDF
J-8_QA for PWM HVAC and Fire Alarm December 02 2024.pdf PDF
J-7_Restroom Trailer Spec Sheet.pdf PDF
697DCK-24-R-00596_Amendment 03.pdf PDF
PWM PreBid Walkthru 2024-10-29.pdf PDF
697DCK-24-R-00596_Amendment 01.pdf PDF
J-1_PWM HVAC FINAL SPECIFICATIONS 9.25.2024.pdf PDF
J-1 FINAL SPECIFICATIONS PWM HVAC 1302899.pdf PDF
J-1aFAA PWM HVAC REHAB FINAL DRAWINGS SIGNED.pdf PDF
J-1b Bid Alternate PWM ATCT FLS Upgrade F101 JLSB Signed.pdf PDF
697DCK-24-R-00596.pdf PDF
J-4_BLANK BID FORM E25_IGCE_ATCT_PWM_PWM-HVAC_1302899_001_638555123691731894.pdf PDF
J-2 Wage Determination.pdf PDF
J-3_Past Performance Questionnaire.pdf PDF
J-4a_ALTERNATE 1 BLANK BID FORM E25_IGCE_ATCT_PWM_PWM-HVAC_1302899_001_638555123691731894.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.

PAGE OF PAGES

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

Items 8 and 15, and returning is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required.)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.

E. IMPORTANT: Contractor is not, is required to sign this document and return

ORDER NO. IN ITEM 10A.

1 2

0002 09/25/2024

FEDERAL AVIATION ADMINISTRATION

AAQ-500 - REGIONAL ACQUISITIONS

10101 HILLWOOD PARKWAY

FORT WORTH TX 76177-1524

AAQ520FTW-AFN

x

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ 1 x x

697DCK-24-R-00596

1 copies to the issuing office.

09/25/2024

(x)

LIST OF CHANGES:

Purpose of Amendment 02 is changing the dates for the following timeline:

FIRST: The date for the site visit hereby updated to the following:

A site visit is scheduled for October 29, 2024 at 0900ET. If you wish to attend, submit your name, company and contact information for all attendees to Erin.M.Crabtree@faa.gov and

Joni.L.Haynes@faa.gov no later than October 25, 2024.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Joni L. Haynes

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

697DCK-24-R-00596/0002

SECOND: The due date for questions is hereby updated to the following:

Submit questions in writing to

Erin.M.Crabtree@faa.gov and Joni.L.Haynes@faa.gov no later than November 06, 2024, by 1200 ET.

THIRD: The due date for proposals is hereby updated to the following:

Proposals are due no later than November 29, 2024, at 1200 ET. Any proposal received after this time will be deemed non-responsive and will not be considered for award.

FOURTH: All terms and conditions remain unchanged and in full effect.

File details come from the government source that posted it. Updated .