Attachment #9-PAR 56 300W Production Unit Test and Test Result Form 11-29-17.pdf

PDF 246 KB Posted

Attached to
SIR/RFO - Par-56, 300 Watt, Incandescent Lamps
Solicitation number
6973GH-18-R-00028
Issued by

About this file

Attachment #9-PAR 56 300W Production Unit Test and Test Result Form 11-29-17 (pdf)

View the file

Other files

File Type Posted
Attachment #9-PAR 56 300W Production Unit Test and Test Result Form 10-24-17_FINAL.docx DOCX document
Attachment #1-PAR 56 300W SOW 11-29-2017 Revision I.pdf PDF
6973GH-18-R-00028-A0001.pdf PDF
6973GH-18-R-00028-A0002.pdf PDF
Attachment #4-Past Performance Questionnaire UPDATEDFINAL.pdf PDF
Attachment #3-ORGANIZATIONAL EXPERIENCE INFORMATION.pdf PDF
6973GH-18-R-00028_Final.pdf PDF
Attachment#8-PAR 56 300W Production Unit Test Plan- Procedure Form 10-24-2017_FINAL.docx DOCX document
Attachment #5-ANSI_ASQCZ1-4-1993.pdf PDF
Attachment #6-PAR 56 300W First Article Test Plan- Procedure Form 10-24-2017_FINAL.docx DOCX document
Attachment #1-PAR 56 300W SOW 10-31-2017_FINAL.pdf PDF
Attachment #4-Past Performance Questionnaire Revision I.pdf PDF
Attachment #2-PAR 56 300W CDRLs-DIDs 11-29-2017.pdf PDF
Attachment #7-PAR 56 300W First Article Test Procedure and Result Form Changes 11-29-2017.pdf PDF
Attachment #7-PAR 56 300W First Article Test Procedure and Result Form 10-30-2017_FINAL.docx DOCX document
Attachment #2-PAR 56 300W CDRLs-DIDs 10-31-2017_FINAL.pdf PDF
Attachment #4-Past Performance Questionnaire UPDATEDFINAL.pdf PDF
Attachment #3-ORGANIZATIONAL EXPERIENCE INFORMATION.pdf PDF
Attachment #1-PAR 56 300W SOW 10-31-2017_FINAL.pdf PDF
Attachment #2-PAR 56 300W CDRLs-DIDs 11-29-2017.pdf PDF
Attachment #9-PAR 56 300W Production Unit Test and Test Result Form 11-29-17.pdf PDF
Attachment #4-Past Performance Questionnaire Revision I.pdf PDF
Attachment #1-PAR 56 300W SOW 11-29-2017 Revision I.pdf PDF
Attachment #7-PAR 56 300W First Article Test Procedure and Result Form 10-30-2017_FINAL.docx DOCX document
6973GH-18-R-00028-A0001.pdf PDF
Attachment #2-PAR 56 300W CDRLs-DIDs 10-31-2017_FINAL.pdf PDF
Attachment #9-PAR 56 300W Production Unit Test and Test Result Form 10-24-17_FINAL.docx DOCX document
Attachment #6-PAR 56 300W First Article Test Plan- Procedure Form 10-24-2017_FINAL.docx DOCX document
Attachment #7-PAR 56 300W First Article Test Procedure and Result Form Changes 11-29-2017.pdf PDF
6973GH-18-R-00028_Final.pdf PDF
Attachment #5-ANSI_ASQCZ1-4-1993.pdf PDF
Attachment#8-PAR 56 300W Production Unit Test Plan- Procedure Form 10-24-2017_FINAL.docx DOCX document
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 | P a g e

November/21/ 2017

Production Unit Test Result Form.

For FAA 20A 300W Par 56

Q20A/PAR-56/C INCANDESCENT LAMP

TYPE I, MOGUL END PRONG, 300W

NSN: 6240-01-432-3996

1.0 Scope

1.1 The specifications covers halogen-cycle PAR-56 aviation service lamps or equivalent used for runway approach lighting systems.

1.2 Reference FAA-E-2408b Dated July 31, 2000.

1.3 This procedure will outline any and all test requirements for production build units.

1.4 A test sample rate of 5pcs or 1% whichever is greater shall be tested per production batch.

2.0 Test Equipment List with calibration date (as need).

List all of the equipment

3.0 Test methods

Testing of the UUT shall be performed IAW FAA-E-2408b Dated July 31, 2000.

4.0 Wattage rating test (paragraph 4.5.1)

Test set up and procedure: (prepare by contractor)

5.0 Filament Motion and Shorting Test (paragraph 4.5.2)

Test set up and procedure:

(prepare by contractor)

2 | P a g e

6.0 Photometric Testing (paragraph 4.5.4)

Photometric tests shall be conducted to demonstrate compliance with the intensity and beam dimension requirements of Table I, as applicable.

Table 2 is used to fill the photometric required in table 1.

Table I. Lamp Design Parameters (Mogul End Prong, Type I)

Q20A/PAR56/C

Wattage Rating

300 +18

Rated Amperes

20 ±0.5%

Average Life, Minimum Candela Requirements Within Beam Field Point Location (degrees from mechanical axis)

3.5 up - 13.5 left 7,000

3.5 down - 13.5 left 7,000

3.5 up - 13.5 right 7,000

3.5 down - 13.5 right 7,000

4 up - vertical 16,000 4 down - vertical horizontal - 10 left horizontal - 10 right

16,000

16,000 16,000 horizontal - 14 left 7,000 horizontal - 14 right 7,000

Maximum Intensity, 48,000 Candela (not to be exceeded in any direction)

Cover Glass Prismatic

Prismatic Prismatic

Base All three (3) lamps - Mogul End Prong

Burning Position All three (3) lamps - Horizontal to 25°

Base Down

3 | P a g e

Sample No:

Flash Period: On t ime-one flash:

Brightness Step:

Style:

Input:

Neutral Density Filter:

Calibration Factor:

Serial #

NA I

Vertical Position (deg.)

Calculated Effective Intensity Data (candela) Horizontal Position (deg.)

15L 14L 13.5 L 10L 11L 7.5L 5L 0 5R 7.5R 10R 12R

13.5 R 14R

5U 4U

3.5U 2.5U 1U

1D 2.5D 3.5D 4D 5D

Table 2: Photometric Test Data for S/N:

4 | P a g e

7.0 Two Hour Test (paragraph 4.5.13)

8.0 Examination Of Product (paragraph 4.4.1)

9.1 The lamp shall be inspected to determine compliance with the requirements specified herein with respect to materials, workmanship and marking. The lamp shall be inspected to determine that outline dimensions meet the dimensions given in Figure 1 as applicable. Lamp prongs shall be flat any curvature in design shall be cause for rejection.

Record Inspection results on data sheet.

5 | P a g e

Prepared for: FAA Logistics Center

Name of Company:

Address:

Phone number:

Prepared By:

Title:

Test By:

Title:

Date: ______________

Part Name: _____________________

Manufacture Part Number: ______________________

NSN:_____________________________

Production Date Code: _________________

Production Build QTY: ______________

Sample rate of 5 pcs or 1% whichever is greater shall be tested.

QTY: No Lamp Fail – all five Lamp should pass

List of test performed and attach the test result for each test.

4.0 Wattage Rating Test

5.0 Filament Motion Test and Shorting of Turn Test

6.0 Photometric Test

7.0 Two Hour Test

9.0 Examination of Product

6 | P a g e

Test Equipment Used Calibration Date Calibration Due Date

7 | P a g e

Lamp # – serial number

4.0 Wattage Rating Test

Details/Requirements Results UUT start date/time

Measured current at start 20 Amps +/-.5%(19.1-20.1)

Actual measured:

pass/fail

Measured voltage at start 15 Volts nominal

Time accumulated on UUT 5 hour minimum

Measured current after 5 hours

Measured voltage after 5 hours

Calculated watts 300 Watt

8 | P a g e

5.0 Filament Motion and Shorting Test: Date/Time:

Details/Requirements Measured Results Measured current at start

15 min interval Measured voltage within +/-0.5 volts of original Measurement

30 min interval Measured voltage within

60 min interval Measured voltage within

120 min interval Measured voltage within

9 | P a g e

6.0 Photometric Testing. Date performed: ____________

Measured Voltage:___________ 15 V Nominal

Measured Current:___________ 20Amps +/-.5%(19.9-20.1)

Max Candela Measurement 48,000 Max Candela allowed

Actual Measured___________ pass/fail

3.5°up 13.5°left Reading 7,000 Candela Min.

3.5°down 13.5°left Reading

3.5° up 13.5° Right Reading

3.5°down 13.5° Right Reading

4.0°up 0°Vertical Reading 16,000 Candela Min.

4.0°down 0°Vertical Reading

0°Horizontal 10°Left Reading

0°Horizontal 10°Right Reading

0°Horizontal 14°Left Reading

0°Horizontal 14°Right Reading

10 | P a g e

(deg.)

Calculated Effective Intensity Data (candela)

4U

3.5U 2.5U 1U

1D 2.5D 3.5D 4D

7.0 Two Hour Test, Date

Start time:

Stop time:

Pass Fail

9.0 Examination of Product Pass Fail

11 | P a g e

Details/Requirements Results UUT start date/time

12 | P a g e

Measured voltage within

30 min interval Measured voltage within

60 min interval Measured voltage within

120 min interval Measured voltage within

13 | P a g e

Measured Current:___________ 20Amps +/-.5%(19.9-20.1)

14 | P a g e

(deg.)

Calculated Effective Intensity Data (candela)

4U

3.5U 2.5U 1U

1D 2.5D 3.5D 4D

9.0 Examination of Product Pass Fail

15 | P a g e

Details/Requirements Results UUT start date/time

15 Voltsnominal

16 | P a g e

Measured voltage within

30 min interval Measured voltage within

60 min interval Measured voltage within

120 min interval Measured voltage within

17 | P a g e

Measured Current:___________ 20Amps +/-.5%(19.9-20.1)

18 | P a g e

(deg.)

Calculated Effective Intensity Data (candela)

4U

3.5U 2.5U 1U

1D 2.5D 3.5D 4D

9.0 Examination of Product Pass Fail

19 | P a g e

Details/Requirements Results UUT start date/time

20 | P a g e

Measured voltage within

30 min interval Measured voltage within

60 min interval Measured voltage within

120 min interval Measured voltage within

21 | P a g e

Measured Current:___________ 20Amps +/-.5%(19.9-20.1)

22 | P a g e

(deg.)

Calculated Effective Intensity Data (candela)

4U

3.5U 2.5U 1U

1D 2.5D 3.5D 4D

9.0 Examination of Product Pass Fail

23 | P a g e

Details/Requirements Results UUT start date/time

24 | P a g e

Measured voltage within

30 min interval Measured voltage within

60 min interval Measured voltage within

120 min interval Measured voltage within

25 | P a g e

Measured Current:___________ 20Amps +/-.5%(19.9-20.1)

26 | P a g e

(deg.)

Calculated Effective Intensity Data (candela)

4U

3.5U 2.5U 1U

1D 2.5D 3.5D 4D

27 | P a g e

9.0 Examination of Product Pass Fail