Bridge Inspection Report_STR_5140-173P

View the file

Other files for this federal contract opportunity

Other files attached to Blue Ridge Parkway Pavement Preservation, newest first.
File Type Posted
69C37018R000004_Amendment_000001.pdf PDF
Bridge_Inspection_Rpt_STR_5140-194P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-149P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-118P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-124P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-143P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-139P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-120P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-185P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-147P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-155P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-141P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-122P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-157P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-146P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-156P.pdf PDF
NEPA_document_CE.pdf PDF
Bridge_Inspection_Rpt_STR_5140-186P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-117P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-116P.pdf PDF
Plans_Adv.pdf PDF
VETS-4212.pdf PDF
Bridge_Inspection_Rpt_STR_5140-142P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-151P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-127P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-153P.pdf PDF
RFP_Solicitation_NP-BLRI_PVT_PRES_FY17.pdf PDF
Bridge_Inspection_Rpt_STR_5140-145P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-125P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-121P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-131P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-203P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-197P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-129P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-119P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-144P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-123P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-126P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-150P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-158P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-148P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-193P.pdf PDF
Bridge_Inspection_Rpt_STR_5140-140P.pdf PDF
Synopsis_-_BLRI_PVT_PRES_FY17.pdf PDF
Show all 44

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CULVERT INSPECTION REPORT

U.S. ROUTE 74A (WBL) ACCESS RAMP CULVERT

U.S. ROUTE 74A (WBL) ACCESS RAMP OVER CREEK

BLUE RIDGE PARKWAY

LW

STRUCTURE NO. 5140-173P

INSPECTION TYPE: ROUTINE

INSPECTION DATE: 6/10/15

Report prepared by: SU

MILE POINT: 384.72

Federal Highway Administration KILOMETER POINT: 618.78 Federal Lands Bridge Office Bridge Inspection and Management Program 21400 Ridgetop Circle Sterling, Virginia 20166 https://bridge.flhd.fhwa.dot.gov

STRUCTURE SUMMARY STRUCTURE NO. 5140-173P

U.S. ROUTE 74A (WBL) ACCESS RAMP CULVERT INSPECTION DATE: 6/10/15

CULVERT IDENTIFICATION AND DESCRIPTION

MAIN SPAN MATERIAL: ........ CONCRETE NO. OF BARRELS:

FOUNDATION: ....................... OTHER BARREL LENGTH: ............... 76 FT (23 M)

STRUCT. TOTAL LENGTH: ... 27.0 FT (8.2 M) SKEW ANGLE: ..................... 0 °

MAX. SPAN LENGTH: ............ 8.0 FT (2.4 M) YEAR BUILT:

PROJ./PLAN REF. NO: .......... 2R1 / 00000 YEAR RECONSTRUCTED: .. N/A

NPS ROAD CLASS: ............... 1 - PRINCIPAL PARK ROAD

STRUCTURE HISTORY: ....... 2002-SOUTH HEADWALL AND WINGWALLS RECONSTRUCTED.

LOCATION

BLUE RIDGE PARKWAY MILE POINT: ..................... 384.72 (KM PT 618.78)

STATE: .................................. NORTH CAROLINA LOCATION: ACCESS RAMP TO U.S. ROUTE 74

WEST FACILITY CARRIED: ............. U.S. ROUTE 74A (WBL) ACCESS RAMP

FEATURE INTERSECTED: ... CREEK

STRUCTURE EVALUATION SUMMARY

This triple barrel concrete culvert is in good condition overall. Problems include minor to moderate cracking of top slab and barrel walls including patched areas, moderate soil and debris accumulation at the upstream end of the structure blocking the center barrel, and moderate soil accumulation in the east barrel.

Corrective measures should be taken as outlined in this report to help prevent the possible development of more serious or costly problems in the future.

It should also be noted that no railing is present along the south side of the structure, and the railing along the north side does not meet current safety height specifications. Consideration should be given to install railing according to current standards to help improve motorist safety.

INSPECTION TEAM: C. CASTRO, R. SILVESTRY

CONDITION ASSESSMENT:

CARLOS CASTRO, P.E., FIELD TEAM LEADER 571-434-1546

REPORT REVIEW:

MARCUS MILLER, P.E., SENIOR INSPECTION ENGINEER 703-404-6252

REPORT APPROVAL: DATE: 12/31/15

JORGOMAI CEESAY, PH.D., P.E., BIP SUPERVISORY ENGINEER 703-404-6244

RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 5140-173P

A (Critical) - Structure is closed, in imminent danger of collapse, or presents a critical safety hazard.

B (Major) - Structure is seriously deficient or presents a safety hazard, but can remain in service at reduced loads or with frequent inspections.

C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.

D (Minor) - Structure is generally in good condition. Preventative maintenance may be required.

E (Special) - Structure is under construction or reconstruction.

D226 PRIORITY OF IMPROVEMENT

ITEM

NO.

MAINTENANCE RECOMMENDATIONS

(GENERALLY NOT FLHP ELIGIBLE)

QTY. UNIT COST

UNIT

ESTIMATE

COST

PRELIM.

61.4, 62.5 REMOVE SEDIMENT FROM INSIDE BARRELS. REMOVE DEBRIS ACCUMULATION AT

UPSTREAM END OF STRUCTURE.

1 LS $4,000 $4,000

PRELIM. MAINTENANCE TOTAL : $4,000

ITEM

NO.

REHABILITATION/RECONSTRUCTION

(TYPICALLY NEEDED WITHIN 5 YEARS) QTY. UNIT UNIT

COST ESTIMATES

PRELIM. COST

REHAB. RECONSTR.

PRELIM. REHABILITATION/RECONSTRUCTION TOTAL :

COST ESTIMATE SUMMARY

PRELIM. MAINTENANCE TOTAL:

PRELIM. REHABILITATION TOTAL:

PRELIM. RECONSTRUCTION TOTAL: ...

TOTAL ITEMIZED COSTS:

$0 $0 $4,000

$4,000

PRELIMINARY ESTIMATE TOTAL* :

(*Includes typical contract costs for mobilization, traffic control, and design/construction engineering; but does not include detour bridges, work beyond the bridge limits, or work not listed above. Estimates are approximate and are for preliminary planning purposes only; they should not be used as a complete or final engineers estimate.)

$4,000

REMARKS: Cost estimates assume that the recommended actions will be combined with similar work being performed on other structures.

It should also be noted that no railing is present along the south side of the structure, and the railing along the north side does not meet current safety height specifications. Consideration should be given to install railing according to current standards to help improve motorist safety.

FIELD INSPECTION REPORT STRUCTURE NO. 5140-173P

CONDITION RATING CODES FOR ITEMS 58 - 62, 222, 223

N

NOT APPLICABLE

EXCELLENT CONDITION

VERY GOOD CONDITION - no problems noted.

GOOD CONDITION - some minor problems.

SATISFACTORY CONDITION - structural elements show some minor deterioration.

FAIR CONDITION - all primary structural elements are sound but may have minor section loss, cracking, spalling, or scour.

POOR CONDITION - advanced section loss, deterioration, spalling, or scour.

SERIOUS CONDITION - loss of section, deterioration, spalling, or scour have seriously affected primary structural components. Local failures are possible.

Fatigue cracks in steel or shear cracks in concrete may be present.

CRITICAL CONDITION - advanced deterioration of primary structural elements. Fatigue cracks in steel or shear cracks in concrete may be present or scour may have removed substructure support. Unless closely monitored it may be necessary to close the structure until corrective action can be taken.

“IMMINENT” FAILURE CONDITION - major deterioration or section loss present in critical structural components or obvious vertical or horizontal movement affecting structure stability. Structure is closed to traffic but corrective action may return structure to light service.

FAILED CONDITION - out of service; beyond corrective action.

CONDITION RATING CODE EQUIVALENTS FOR SUB-ELEMENTS

G = GOOD (CODES 7 - 9) F = FAIR (CODES 5 - 6) P = POOR (CODES 0 - 4)

STREAM BED COMPOSITION :9.

AVG. CLEAR OPENING 8.

NORMAL VELOCITY7.

ADEQUACY OF OPENING6.

OTHER 5.

WATERWAY OBSTRUCTIONS 4.

CHANNEL PROTECTION3.

EROSION AND/OR SCOUR2.

ALIGNMENT1.

61. CHANNEL 7

G G G F

7 FT.

MED

SUFF

N

ITEM REFERENCE AND REMARKS

62. CULVERT 7

PARAPETS AND/OR RAILINGS9.

ADEQUACY OF COVER8.

SETTLEMENT AND/OR DEFLECTION7.

EROSION AND/OR SCOUR6.

DEBRIS AND/OR SILT 5.

WINGWALLS 4.

HEADWALLS 3.

FOOTINGS 2.

BARREL(S)1.

ROADWAY SURFACE 10.

RIDEABILITY 11.

OTHER 12.

G N G F F G G G P G G N

222. APPROACHES 6

OTHER 9.

ALIGNMENT8.

SIGNS 7.

SETTLEMENT6.

EROSION5.

SURFACING 4.

APPROACH GUARDRAIL 3.

RELIEF JOINTS2.

1. APPROACH SLABS N

N P G G G G G N

223. RETAINING WALL N

OTHER 6.

SETTLEMENT OR DEFLECTION5.

EROSION AND/OR SCOUR4.

FOUNDATION3.

WEEP HOLES2.

1. WALL

36. TRAFFIC AND SAFETY FEATURES

APPROACH GUARDRAILS C.

TRANSITIONS B.

BRIDGE RAILINGSA.

APPROACH GUARDRAIL ENDS D.

N N

GRAVEL, SAND

61.4, 62.5 MINOR ACCUMULATION OF SEDIMENT AND ROCKS IN WEST AND

CENTER BARRELS, MODERATE IN EAST BARREL. MODERATE

DEBRIS ACCUMULATION UP TO 4' HIGH, AT UPSTREAM END

BLOCKING CENTER BARREL.

62.1 MINOR TO MODERATE CRACKING ON UNDERSIDE OF TOP SLAB,

SOME CRACKS CONTINUING ON VERTICAL WALLS. MINOR TO

MODERATE VERTICAL CRACKING OF BARREL WALLS. MINOR

CRACKING OF BARREL WALLS AT APPROXIMATE CENTERLINE.

CRACKING OF PATCHES THROUGHOUT BARRELS.

62.3 EFFLORESCENT ON END OF SOUTH BARREL FROM HEADWALL

MORTAR JOINTS.

62.3 UPSTREAM HEADWALL HAS BEEN RECONSTRUCTED.

DOWNSTREAM HEADWALL IN GOOD CONDITION.

62.4 MODERATE VEGETATION GROWTH ALONG SOUTH WINGWALLS.

62.6 MINOR SCOUR AT UPSTREAM NEAR STRUCTURE.

62.9, 222.3, 36.A,C

NO TIMBER RAILING ALONG SOUTH SIDE OF ROADWAY. EXISTING

2'-0" BRIDGE RAILING HEIGHT DOES NOT MEET AASHTO HEIGHT

SPECIFICATION OF 2'-3".

TRAFFIC SAFETY RATING CODES

0 - Does not meet standards or a safety feature is required and none is provided.

1 - Meets currently acceptable standards.

N - Not applicable or a safety feature is not required. 3 OF 15

STRUCTURE LOAD RATING STRUCTURE NO. 5140-173P

TRUCK TYPE

INVENTORY RATING (NORMAL TRAFFIC) OPERATING RATING (MAXIMUM LOAD)

TONS METRIC TONS TONS METRIC TONS

H 15 14 25 23

HS 27 24 45 41

TYPE 3 29 26 49 44

TYPE 3S2 46 42 77 70

TYPE 3-3 57 52 94 85

DESIGN LOADING: H15 (M13.5) (ASSUMED - SEE REMARKS)

X CAPACITY MEETS OR EXCEEDS DESIGN LOAD

CAPACITY IS LESS THAN DESIGN LOAD

ORIGINAL LOAD RATING CALCULATION APPLICABLE

ORIGINAL LOAD RATING CALCULATION REVISED

DATE OF LOAD RATING CALCULATION:

LOAD RATING CONTROLLED BY:

REMARKS: DESIGN LOADING IS UNKNOWN; ASSUMPTION IS BASED ON STRUCTURE TYPE, LOCATION, AGE, AND

CONDITION.

STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 5140-173P

STRUCTURE IDENTIFICATION

(201) PARK: BLUE RIDGE PARKWAY

(202) STRUCTURE NAME: .......... U.S. ROUTE 74A (WBL) ACCESS RAMP C

(203) STRUCTURE KIND: ............2 - CULVERT

(204) STRUCTURE NUMBER: ..... 5140-173P

(205) NPS REGION: .................... 4 - SOUTHEAST

(206) ROUTE CODE NUMBER: ... 111

(207) ROAD SECTION NO: .......... 173P

(208) NPS ROAD CLASS: ............ 1 - PRINCIPAL PARK ROAD

(209) WITHIN NPS BNDRY?: ....... YES

(210) OPERATING UNIT: ............. GILLESPE

(211) PROJECT NO(S): ................ 2R1

(212) DRAWING NUMBERS:

(21) MAINTAINED BY: ................. 66 - NATIONAL PARK SERVICE

(22) OWNER: ............................... 66 - NATIONAL PARK SERVICE

(1) STATE:

(2) STATE HWY. AGENCY DIST:

(3) COUNTY CODE:

(4) CITY/PLACE CODE:

(5) INVENTORY ROUTE:

(6) FEATURES INTERSECTED:

(7) FACILITY CARRIED:

(8) STATE STRUCTURE NO:

(9) LOCATION:

(10) INV. RTE. - MIN. VERT. CLR: ..

(11) MILE POINT:

(27) YEAR BUILT:

(106) YEAR RECONSTRUCTED:

(20) TOLL:

(37) HISTORICAL DESIGNATION: ..

374 - NORTH CAROLINA (NC)

021 - BUNCOMBE

167001110

CREEK

U.S. ROUTE 74A (WBL) ACCE

5140173P0000000

ACCESS RAMP TO U.S. ROU

99.99 FT (99.99 M)

384.72 (KM PT 618.78)

N/A

3 - FREE ROAD

5 - NOT ELIGIBLE

STRUCTURE DESCRIPTION, FOUNDATION, AND DECK TYPE

(43A) MAIN STR. MATERIAL: ..

(43B) MAIN STR. TYPE:

(45) NO. OF MAIN SPANS:

(48) MAX. SPAN LENGTH:

(49) STRUCTURE LENGTH:

(216A) ABUTMENT #1 FDN:

(216B) ABUTMENT #2 FDN:

(217A) PREDOM. PIER FDN.: ..

(217B) SECOND. PIER FDN: ...

(107) DECK TYPE:

1 - CONCRETE

19 - CULVERT

8.0 FT (2.4 M)

27.0 FT (8.2 M)

5 - OTHER

5 - OTHER

5 - OTHER

5 - OTHER

N - NOT APPLICABLE

(44A) APPR. STR. MATERIAL: ........ 0 - OTHER

(44B) APPR. STR. TYPE: ................ 00 - OTHER

(46) NO. OF APPROACH SPANS: .. 0

(108) WEAR SURFACE/PROTECT SYSTEM:

A) TYPE WEARING SURFACE: .. N - NOT APPLICABLE

B) TYPE MEMBRANE: ................. N - NOT APPLICABLE

C) TYPE PROTECTION: .............. N - NOT APPLICABLE

(218) IS SALT USED?: ..................... YES

LOAD RATING AND POSTING

(31) DESIGN LOAD: ................. 2 - H15 (M13.5) (41) LOAD RESTRICTION: ......... A - OPEN, NO RESTRICTION

(66) INVENTORY RATING: ...... 27.0 TONS (24.0 METRIC TONS) (70) BRIDGE POSTING: .............. 5 - NO POSTING REQUIRED

(64) OPERATING RATING: ...... 45.0 TONS (40.8 METRIC TONS)

INSPECTION DATES

(90) INSPECTION DATE: 6/15 (91) FREQ. OF INSP: 48 MONTHS (92 / 93) CRITICAL FEATURE INSPECTION (CFI):

(219) ADD. STUDIES NEEDED: N - 0 - NONE (A) FRACTURE CRITICAL: ... NO

INSP. EVERY: MONTHS - LAST INSP. : (220) SPECIAL STUDY TYPE: 0 - NONE

(B) UNDERWATER: .............. NO

(221) SPECIAL STUDY DATE: INSP. EVERY: MONTHS - LAST INSP. :

(C) SPECIAL INSPECTION: .. NO

INSP. EVERY: MONTHS - LAST INSP. :

STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 5140-173P

GEOMETRY, TRAFFIC, AND NAVIGATIONAL DATA

(16) LATITUDE: ............................. 35°33'49.20" (51) CURB TO CURB WIDTH: ........... 0.0 FT (0.0 M)

(17) LONGITUDE: ......................... 82°29'43.80" (52) DECK WIDTH: ............................ 0.0 FT (0.0 M)

(19) DETOUR LENGTH: ............... 1 MI (2 KM) (32) APPR. ROADWAY WIDTH: ........ 36.0 FT (11.0 M)

(28A) LANES ON STRUCT: .......... 02 (213) APPR. PAVEMENT WIDTH: ..... 28.0 FT (8.5 M)

(28B) LANES UNDER STRUCT: ... 00 LEFT SHOULDER: .................. 8.0 FT (2.4 M)

(42A) SERVICE ON: ..................... 1 - HIGHWAY RIGHT SHOULDER: ................ 8.0 FT (2.4 M)

(42B) SERVICE UNDER: .............. 5 - WATERWAY (33) BRIDGE MEDIAN: ....................... 0 - NO MEDIAN

(29) AVG. DAILY TRAFFIC: .......... 1000 (34) SKEW ANGLE: ............................ 0 °

(30) YEAR OF ADT: ...................... 2011 (35) DECK FLARE?: ........................... NO

(114) FUTURE ADT: ..................... 1100 (47) TOTAL HORIZ. CLEARANCE: .... 36.0 FT (11.0 M)

(115) YEAR OF FUTURE ADT: ..... 2031 (50) SIDEWALKS:

(101) PARALLEL STRUCTURE: ... N - NONE LEFT : ...................................... 0.0 FT (0.0 M)

(38) NAVIGATION CONTROL?: ... 0 RIGHT : ................................... 0.0 FT (0.0 M)

(39) VERTICAL CLEARANCE: ...... 0.0 FT (0.0 M) (214) BRIDGE RAIL TYPE:

(40) HORIZ. CLEARANCE: ........... 0.0 FT (0.0 M) RAIL CONFIGURATION: ......... 0 - N/A

(111) ABUT. OR PIER PROT: ....... MATERIAL: .............................. 0 - N/A

DESIGN TYPE: ........................ 0 - N/A LATERAL UNDERCLEARANCE:

(55) RIGHT: ....................... 0.0 FT (0.0 M) (215) BRIDGE RAIL HEIGHT: ............ 2.00 FT (0.61 M)

(56) LEFT: ......................... 0.0 FT (0.0 M) (53) MIN. VRT. CLEAR. OVER DECK: 99.99 FT (99.99 M)

(54) MIN. VRT. UNDERCLEARANCE: 0.00 FT (0.00 M)

CONDITION AND APPRAISAL DATA, PROPOSED IMPROVEMENTS, AND COST

(58) DECK: ................................. N

(59) SUPERSTRUCTURE: .........N

(60) SUBSTRUCTURE: ..............N

(61) CHANNEL:

(62) CULVERT:

(222) APPROACHES:

(223) RETAINING WALL: ........... N

(36) TRAFFIC SAFETY FEAT: ... 0N0N

(75A) TYPE OF WORK:

(75B) WORK DONE BY:

(76) IMPROVEMENT LENGTH: ..

(67) STRUCTURAL EVALUATION:

(68) DECK GEOMETRY:

(69) UNDERCLEARANCES:

(71) WATERWAY ADEQUACY:

(72) APPROACH ALIGNMENT:

(113) SCOUR CRITICAL:

(225) PURPOSE OF IMPROVEMENT:

(226) PRIORITY OF IMPROVEMENT:

(227) MAINTENANCE COST:

(228) REHAB./RECONSTR. COST: ...

(229) CONSTRUCTION COST:

N

8 - Stable; scour above top of fo

1 - MAINTENANCE

D - MINOR

$4,000

$0

$0

ADDITIONAL INFORMATION

(230) STRUCTURE HISTORY:

2002-SOUTH HEADWALL AND WINGWALLS RECONSTRUCTED.

(231) ADDITIONAL CONSIDERATIONS:

(330) ADDITIONAL CONFIG. INFO.:

APPENDIX STRUCTURE NO. 5140-173P

PHOTOGRAPHS STRUCTURE NO. 5140-173P

PHOTO #1 - LOOKING EAST

FLOW

PHOTO #2 - NORTH (DOWNSTREAM) SIDE

PHOTO #3 - GENERAL TOPSIDE VIEW LOOKING WEST

PHOTO #4 - GENERAL UNDERSIDE VIEW LOOKING UPSTREAM

PHOTO #5 - GENERAL VIEW INSIDE OF WEST BARREL LOOKING

UPSTREAM; NOTE DEBRIS ACCUMULATION AT END AND ON BOTTOM

SLAB AT MIDSECTION

PHOTO #6 - GENERAL VIEW INSIDE OF CENTER BARREL LOOKING

UPSTREAM; NOTE DEBRIS ACCUMULATION AT UPSTREAM END

PHOTO #7 - DEBRIS AND FILL ACCUMULATION THROUGHOUT EAST

BARREL

PHOTO #8 - DEBRIS BUILT UP TO 4' ON SOUTH (UPSTREAM) SIDE

BLOCKING APPROXIMATELY 30% OF CENTER BARREL

PHOTO #9 - TYPICAL HONEYCOMBING AND

ABRASION OF CONCRETE ALONG WATER

LINE, EAST WALL AT DOWNSTREAM END OF

CENTER BARREL SHOWN

PHOTO #10 - CRACKING OF PATCH AT

CONSTRUCTION JOINT AT MIDSECTION OF

EAST BARREL

PHOTO #11 - CRACKING OF PATCH AT

CONSTRUCTION JOINT ON WEST WALL OF

EAST BARREL

PHOTO #12 - CRACK FROM WEST WALL IN

CENTER BARREL CONTINUING ON TOP SLAB

UNDERSIDE

PHOTO #13 - CRACKING OF WEST SIDE OF

CENTER BARREL

PHOTO #14 - VERTICAL CRACKING ON WEST

SIDE OF CENTER BARREL, ~30' FROM

DOWNSTREAM END

PHOTO #15 - LOOKING UPSTREAM FROM STRUCTURE

PHOTO #16 - LOOKING DOWNSTREAM FROM STRUCTURE