Bridge_Inspection_Rpt_STR_5140-147P.pdf
PDF 2 MB Posted
- Attached to
- Blue Ridge Parkway Pavement Preservation Federal contract opportunity
- Solicitation number
- 693C73-18-R-000004
About this file
Bridge Inspection Report_STR_5140-147P
View the file
Other files for this federal contract opportunity
Show all 44
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TUNNEL INSPECTION REPORT
YOUNG PISGAH RIDGE TUNNEL
BLUE RIDGE PARKWAY THROUGH YOUNG PISGAH RIDGE
BLUE RIDGE PARKWAY
NP
STRUCTURE NO. 5140-147P
INSPECTION TYPE: ROUTINE
INSPECTION DATE: 6/13/15
Report prepared by: SP
MILE POINT: 403.05
Federal Highway Administration KILOMETER POINT: 648.63 Federal Lands Bridge Office Bridge Inspection and Management Program 21400 Ridgetop Circle Sterling, Virginia 20166 https://bridge.flhd.fhwa.dot.gov
STRUCTURE SUMMARY STRUCTURE NO. 5140-147P
YOUNG PISGAH RIDGE TUNNEL INSPECTION DATE: 6/13/15
TUNNEL IDENTIFICATION AND DESCRIPTION
LINING MATERIAL: ............... CONCRETE MINIMUM VERTICAL CLR: .... 14.7 FT (4.5 M)
SPRINGLINE LENGTH: ........ 29.0 FT (8.8 M) STRUCT. TOTAL LENGTH: ... 418.0 FT (127.4 M)
CURB TO CURB WIDTH: ..... 29.0 FT (8.8 M) YEAR BUILT:
PROJ./PLAN REF. NO: ......... 2T5,2T1,2T10 / 00000 YEAR RECONSTRUCTED:
NPS ROAD CLASS: .............. 1 - PRINCIPAL PARK ROAD
STRUCTURE HISTORY: ...... 1985-LINING REHABILITATION.
LOCATION
BLUE RIDGE PARKWAY MILE POINT: ..................... 403.05 (KM PT 648.63)
STATE: .................................. NORTH CAROLINA LOCATION: 8.9 MILES TO U.S. ROUTE 276
FACILITY CARRIED: ............. BLUE RIDGE PARKWAY
FEATURE INTERSECTED: ... YOUNG PISGAH RIDGE
STRUCTURE EVALUATION SUMMARY
This concrete lined tunnel is in fair condition overall, but has some problems that require attention. These include missing stones on the north portal and fallen small trees at the east side of the north portal; missing, faded, and damaged reflectors along the lining and the centerline of roadway; and few spalls with exposed rebar along the tunnel lining. In addition, the vertical clearance, 14'-3", shown on the sign at the south approach is higher than the actual minimum clearance 14-2".
Corrective action should be taken as outlined in this report to prevent the possible development of more serious or costly problems in the future.
INSPECTION TEAM: C. CASTRO, R. SILVESTRY
CONDITION ASSESSMENT:
CARLOS CASTRO, P.E., FIELD TEAM LEADER 571-434-1546
REPORT REVIEW:
MARCUS MILLER, P.E., SENIOR INSPECTION ENGINEER 703-404-6252
REPORT APPROVAL: DATE: 12/31/15
JORGOMAI CEESAY, PH.D., P.E., BIP SUPERVISORY ENGINEER 703-404-6244
RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 5140-147P
A (Critical) - Structure is closed, in imminent danger of collapse, or presents a critical safety hazard.
B (Major) - Structure is seriously deficient or presents a safety hazard, but can remain in service at reduced loads or with frequent inspections.
C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.
D (Minor) - Structure is generally in good condition. Preventative maintenance may be required.
E (Special) - Structure is under construction or reconstruction.
D226 PRIORITY OF IMPROVEMENT
ITEM
NO.
MAINTENANCE RECOMMENDATIONS
(GENERALLY NOT FLHP ELIGIBLE)
QTY. UNIT COST
UNIT
ESTIMATE
COST
PRELIM.
59.2 REPLACE MISSING STONES ON EAST SIDE OF NORTH PORTAL. REMOVE FALLEN
TREES AT EAST SIDE OF NORTH PORTAL.
1 LS $4,000 $4,000
59.8 REPLACE MISSING REFLECTORS ON LINING AND ALONG CENTERLINE OF
ROADWAY.
1 LS $3,000 $3,000
222.7 UPDATE VERTICAL CLEARANCE ON SIGNS AT APPROACHES ACCORDING TO
ACTUAL MINIMUM VERTICAL CLEARANCE AS NECESSARY.
1 LS $500 $1,000
PRELIM. MAINTENANCE TOTAL : $8,000
ITEM
NO.
REHABILITATION/RECONSTRUCTION
(TYPICALLY NEEDED WITHIN 5 YEARS) QTY. UNIT UNIT
COST ESTIMATES
PRELIM. COST
REHAB. RECONSTR.
59.1 CLEAN AND SEAL EXPOSED REBAR WITH AN APPROVED
PROTECTIVE SEALANT IN TUNNEL LINING AS NECESSARY.
1 LS $10,000 $10,000 $0
59 CONTRACT COSTS FOR MOBILIZATION, TRAFFIC CONTROL, AND
DESIGN/CONSTRUCTION ENGINEERING.
1 LS $7,000 $7,000 $0
PRELIM. REHABILITATION/RECONSTRUCTION TOTAL : $17,000 $0
COST ESTIMATE SUMMARY
PRELIM. MAINTENANCE TOTAL:
PRELIM. REHABILITATION TOTAL:
PRELIM. RECONSTRUCTION TOTAL: ...
TOTAL ITEMIZED COSTS:
$0 $17,000 $8,000
$25,000
PRELIMINARY ESTIMATE TOTAL* :
(*Includes typical contract costs for mobilization, traffic control, and design/construction engineering; but does not include detour bridges, work beyond the bridge limits, or work not listed above. Estimates are approximate and are for preliminary planning purposes only; they should not be used as a complete or final engineers estimate.)
$25,000
REMARKS: Cost estimates assume that recommended actions will be combined with similar work being performed on other structures.
FIELD INSPECTION REPORT STRUCTURE NO. 5140-147P
CONDITION RATING CODES FOR ITEMS 58 - 62, 222, 223
N
NOT APPLICABLE
EXCELLENT CONDITION
VERY GOOD CONDITION - no problems noted.
GOOD CONDITION - some minor problems.
SATISFACTORY CONDITION - structural elements show some minor deterioration.
FAIR CONDITION - all primary structural elements are sound but may have minor section loss, cracking, spalling, or scour.
POOR CONDITION - advanced section loss, deterioration, spalling, or scour.
SERIOUS CONDITION - loss of section, deterioration, spalling, or scour have seriously affected primary structural components. Local failures are possible.
Fatigue cracks in steel or shear cracks in concrete may be present.
CRITICAL CONDITION - advanced deterioration of primary structural elements. Fatigue cracks in steel or shear cracks in concrete may be present or scour may have removed substructure support. Unless closely monitored it may be necessary to close the structure until corrective action can be taken.
“IMMINENT” FAILURE CONDITION - major deterioration or section loss present in critical structural components or obvious vertical or horizontal movement affecting structure stability. Structure is closed to traffic but corrective action may return structure to light service.
FAILED CONDITION - out of service; beyond corrective action.
CONDITION RATING CODE EQUIVALENTS FOR SUB-ELEMENTS
G = GOOD (CODES 7 - 9) F = FAIR (CODES 5 - 6) P = POOR (CODES 0 - 4)
59. TUNNEL 6
F
2. PORTALS
1. LINING
F
N3. CURBS AND SIDEWALKS
F4. DRAINS AND DRAINAGE
G5. WEARING SURFACE
G6. RIDEABILITY
N7. LIGHTING
F8. OTHER (REFLECTORS)
9. ADEQUACY OF OPENING SUFF
222. APPROACHES 8
N1. APPROACH SLABS
N2. RELIEF JOINTS
N3. APPROACH GUARDRAIL
G4. SURFACING
G5. EROSION
G6. SETTLEMENT
G7. SIGNS
G8. ALIGNMENT
N9. OTHER
223. RETAINING WALL N
1. WALL
2. WEEP HOLES
3. FOUNDATION
4. EROSION AND/OR SCOUR
5. SETTLEMENT OR DEFLECTION
6. OTHER
36. TRAFFIC AND SAFETY FEATURES
NA. BRIDGE RAILINGS
NB. TRANSITIONS
NC. APPROACH GUARDRAILS
ND. APPROACH GUARDRAIL ENDS
ITEM REFERENCE AND REMARKS
59.1 MINOR SPALLING WITH EXPOSED REBAR AND DELAMINATION ON
WEST SIDE AT ~45' FROM NORTH PORTAL. MINOR SPALLING AND
MODERATE CRACKING WITH EFFLORESCENCE AT SEVERAL SPOTS.
MINOR (6" LONG) SPALL WITH EXPOSED REBAR AND LEAKAGE AT
~370' FROM NORTH PORTAL, WEST SIDE. MINOR SPALL WITH
EXPOSED REBAR ON CROWN OF TUNNEL AT ~70' AND ~320' FROM
NORTH PORTAL. MOISTURE ON CROWN OF TUNNEL THROUGHOUT
LENGTH OF TUNNEL.
59.2 MINOR CRACKING OF PORTAL MASONRY MORTAR JOINTS; MINOR
EFFLORESCENCE FROM RING STONE JOINTS. SEVERAL STONES
MISSING FROM EAST SIDE OF NORTH PORTAL.
59.4 MODERATE CRACKING WITH EFFLORESCENCE AND LEAKAGE AT
DRAIN CHASE AREAS PARTICULARLY AT APPROXIMATELY 50', 210',
265', AND 370' FROM NORTH PORTAL.
59.8 MISSING OR DAMAGED REFLECTORS ALONG TUNNEL LINING.
THREE MISSING AND ONE DAMAGED REFLECTIVE DEVICES ALONG
CENTERLINE AND CURBLINES OF ROADWAY.
222.7 14'-3" VERTICAL CLEARANCE SIGNS AND "YOUNG PISGAH RIDGE
TUNNEL" SIGNS AT BOTH APPROACHES. ACTUAL MINIMUM
VERTICAL CLEARANCE IS 14'-2".
TRAFFIC SAFETY RATING CODES
N
Does not meet standards or a safety feature is required and none is provided.
Meets currently acceptable standards.
Not applicable or a safety feature is not required.
STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 5140-147P
STRUCTURE IDENTIFICATION
(201) PARK: BLUE RIDGE PARKWAY (1) STATE: ....................................... 374 - NORTH CAROLINA (NC)
(202) STRUCTURE NAME: .......... YOUNG PISGAH RIDGE TUNNEL (2) STATE HWY. AGENCY DIST:
(203) STRUCTURE KIND: ............3 - TUNNEL (3) COUNTY CODE: ........................ 021 - BUNCOMBE
(204) STRUCTURE NUMBER: ..... 5140-147P (4) CITY/PLACE CODE:
(205) NPS REGION: .................... 4 - SOUTHEAST (5) INVENTORY ROUTE:
(206) ROUTE CODE NUMBER: ... 1 (6) FEATURES INTERSECTED:....... YOUNG PISGAH RIDGE
(207) ROAD SECTION NO: .......... 147P (7) FACILITY CARRIED: .................. BLUE RIDGE PARKWAY
(208) NPS ROAD CLASS: ............ 1 - PRINCIPAL PARK ROAD (8) STATE STRUCTURE NO: .......... 5140147P0000000
(209) WITHIN NPS BNDRY?: ....... YES (9) LOCATION: ................................ 8.9 MILES TO U.S. ROUTE 2
(210) OPERATING UNIT: ............. GILLESPE (10) INV. RTE. - MIN. VERT. CLR: .. 14.50 FT (4.42 M)
(211) PROJECT NO(S): ................ 2T5,2T1,2T10 (11) MILE POINT: ............................. 403.05 (KM PT 648.63)
(212) DRAWING NUMBERS: ....... 00000 (27) YEAR BUILT:
(21) MAINTAINED BY: ................. 66 - NATIONAL PARK SERVICE (106) YEAR RECONSTRUCTED:
(22) OWNER: ............................... 66 - NATIONAL PARK SERVICE (20) TOLL: ........................................ 3 - FREE ROAD
(37) HISTORICAL DESIGNATION: .. 5 - NOT ELIGIBLE
STRUCTURE DESCRIPTION, FOUNDATION, AND DECK TYPE
(43A) MAIN STR. MATERIAL: ..
(43B) MAIN STR. TYPE:
(45) NO. OF MAIN SPANS:
(48) MAX. SPAN LENGTH:
(49) STRUCTURE LENGTH:
(216A) ABUTMENT #1 FDN:
(216B) ABUTMENT #2 FDN:
(217A) PREDOM. PIER FDN.: ..
(217B) SECOND. PIER FDN: ...
(107) DECK TYPE:
1 - CONCRETE
18 - TUNNEL
29.0 FT (8.8 M)
418.0 FT (127.4 M)
6 - N/A
6 - N/A
6 - N/A
6 - N/A
N - NOT APPLICABLE
(44A) APPR. STR. MATERIAL: ........ 0 - OTHER
(44B) APPR. STR. TYPE: ................ 00 - OTHER
(46) NO. OF APPROACH SPANS: .. 0
(108) WEAR SURFACE/PROTECT SYSTEM:
A) TYPE WEARING SURFACE: .. 6 - BITUMINOUS
B) TYPE MEMBRANE: ................. 0 - NONE
C) TYPE PROTECTION: .............. 0 - NONE
(218) IS SALT USED?: ..................... YES
LOAD RATING AND POSTING
(31) DESIGN LOAD: ................. 0 - UNKNOWN (41) LOAD RESTRICTION: ......... R - POSTED (OTHER)
(66) INVENTORY RATING: ...... 0.0 TONS (0.0 METRIC TONS) (70) BRIDGE POSTING: .............. 5 - NO POSTING REQUIRED
(64) OPERATING RATING: ...... 0.0 TONS (0.0 METRIC TONS)
INSPECTION DATES
(90) INSPECTION DATE: 6/15 (91) FREQ. OF INSP: 24 MONTHS (92 / 93) CRITICAL FEATURE INSPECTION (CFI):
(219) ADD. STUDIES NEEDED: N - 0 - NONE (A) FRACTURE CRITICAL: ... NO
INSP. EVERY: MONTHS - LAST INSP. : (220) SPECIAL STUDY TYPE: 0 - NONE
(B) UNDERWATER: .............. NO
(221) SPECIAL STUDY DATE: INSP. EVERY: MONTHS - LAST INSP. :
(C) SPECIAL INSPECTION: .. NO
INSP. EVERY: MONTHS - LAST INSP. :
STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 5140-147P
GEOMETRY, TRAFFIC, AND NAVIGATIONAL DATA
(51) CURB TO CURB WIDTH: ........... 29.0 FT (8.8 M) (16) LATITUDE: ............................. 35°27'20.00"
(17) LONGITUDE: ......................... 82°41'58.00"
(19) DETOUR LENGTH: ............... 50 MI (80 KM)
(28A) LANES ON STRUCT:
(28B) LANES UNDER STRUCT: ... 02
(42A) SERVICE ON: ..................... 1 - HIGHWAY
(42B) SERVICE UNDER: .............. 1 - HIGHWAY
(29) AVG. DAILY TRAFFIC:
(30) YEAR OF ADT:
(114) FUTURE ADT:
(115) YEAR OF FUTURE ADT:
(101) PARALLEL STRUCTURE: ... N - NONE
(38) NAVIGATION CONTROL?: ... 0
(39) VERTICAL CLEARANCE: ...... 0.0 FT (0.0 M)
(40) HORIZ. CLEARANCE: ........... 0.0 FT (0.0 M)
(111) ABUT. OR PIER PROT:
LATERAL UNDERCLEARANCE:
(55) RIGHT: ....................... 0.0 FT (0.0 M)
(56) LEFT: ......................... 0.0 FT (0.0 M)
CONDITION AND APPRAISAL DATA, PROPOSED IMPROVEMENTS, AND COST
(58) DECK: ................................. N
(59) SUPERSTRUCTURE: .........N
(60) SUBSTRUCTURE: ..............N
(61) CHANNEL: .......................... N
(62) CULVERT: ........................... N
(222) APPROACHES:
(223) RETAINING WALL: ........... N
(36) TRAFFIC SAFETY FEAT: ... NNNN
(75A) TYPE OF WORK:
(75B) WORK DONE BY:
(76) IMPROVEMENT LENGTH: ..
(52) DECK WIDTH:
(32) APPR. ROADWAY WIDTH:
(213) APPR. PAVEMENT WIDTH:
LEFT SHOULDER:
RIGHT SHOULDER:
(33) BRIDGE MEDIAN:
(34) SKEW ANGLE:
(35) DECK FLARE?:
(47) TOTAL HORIZ. CLEARANCE:
(50) SIDEWALKS:
LEFT :
RIGHT :
(214) BRIDGE RAIL TYPE:
RAIL CONFIGURATION:
MATERIAL:
DESIGN TYPE:
(215) BRIDGE RAIL HEIGHT:
(53) MIN. VRT. CLEAR. OVER DECK:
(54) MIN. VRT. UNDERCLEARANCE:
0.0 FT (0.0 M)
38.0 FT (11.6 M)
22.0 FT (6.7 M)
8.0 FT (2.4 M)
8.0 FT (2.4 M)
0 - NO MEDIAN
0 °
NO
29.0 FT (8.8 M)
0.0 FT (0.0 M)
0.0 FT (0.0 M)
0 - N/A
0 - N/A
0 - N/A
0.00 FT (0.00 M)
14.67 FT (4.47 M)
14.67 FT (4.47 M)
(67) STRUCTURAL EVALUATION:
(68) DECK GEOMETRY:
(69) UNDERCLEARANCES:
(71) WATERWAY ADEQUACY:
(72) APPROACH ALIGNMENT:
(113) SCOUR CRITICAL:
(225) PURPOSE OF IMPROVEMENT:
(226) PRIORITY OF IMPROVEMENT:
(227) MAINTENANCE COST:
(228) REHAB./RECONSTR. COST: ...
(229) CONSTRUCTION COST:
N
N
N
N - Not over waterway.
2 - REHAB/RECONSTRUCTION
D - MINOR
$8,000
$17,000
$0
ADDITIONAL INFORMATION
(230) STRUCTURE HISTORY:
1985-LINING REHABILITATION.
(231) ADDITIONAL CONSIDERATIONS:
(330) ADDITIONAL CONFIG. INFO.:
APPENDIX STRUCTURE NO. 5140-147P
PHOTOGRAPHS STRUCTURE NO. 5140-147P
PHOTO #1 - NORTH PORTAL
PHOTO #2 - SOUTH PORTAL
PHOTO #3 - GENERAL VIEW OF ROADWAY LOOKING NORTH; NOTE
MISSING REFLECTORS ALONG LINING AND ALONG CENTERLINE
PHOTO #4 - GENERAL UNDERSIDE VIEW OF TUNNEL LINING LOOKING
SOUTH
PHOTO #5 - FALLEN SMALL TREE ON EAST
SIDE OF NORTH PORTAL; NOTE ALSO FALLEN
STONES SAME AS PREVIOUS INSPECTION
PHOTO #6 - EFFLORESCENCE ON EAST
RINGSTONES AT NORTH PORTAL
PHOTO #7 - CRACKING WITH
EFFLORESCENCE ON EAST LINING NEAR
NORTH PORTAL
PHOTO #8 - CRACKING, DELAMINATION,
EFFLORESCENCE, AND EXPOSED REBAR ON
WEST WALL APPROXIMATELY 45' FROM
NORTH PORTAL
PHOTO #9 - MISSING REFLECTORS ALONG EAST LINING
APPROXIMATELY 45' TO 80' FROM NORTH PORTAL
PHOTO #10 - SPALLING WITH EXPOSED REBAR AT CROWN
APPROXIMATELY 70' FROM NORTH PORTAL
PHOTO #11 - FULL CRACK AT WEST WALL
APPROXIMATELY 85' FROM NORTH PORTAL
PHOTO #12 - CRACKING WITH
EFFLORESCENCE ON EAST LINING
APPROXIMATELY 160' FROM NORTH PORTAL
PHOTO #13 - CRACKING AT WEST WALL
APPROXIMATELY 180' FROM NORTH PORTAL
PHOTO #14 - CRACKING WITH
EFFLORESCENCE ON EAST LINING
APPROXIMATELY 200' FROM NORTH PORTAL
PHOTO #15 - CRACKING WITH
EFFLORESCENCE AND ACTIVE WATER
LEAKAGE ALONG DRAIN CHASE ON EAST
LINING APPROXIMATELY 210' FROM NORTH
PORTAL
PHOTO #16 - SPALL WITH ACTIVE WATER
LEAKAGE ON EAST LINING APPROXIMATELY
265' FROM NORTH PORTAL; NOTE SCALING
PHOTO #17 - SPALL WITH EXPOSED REBAR ON
CROWN APPROXIMATELY 320' FROM NORTH
PORTAL
PHOTO #18 - ACTIVE WATER LEAKAGE ALONG
DRAIN CHASE ON WEST SIDE APPROXIMATELY
370' FROM NORTH PORTAL; NOTE
EFFLORESCENCE AND SPALLING
PHOTO #19 - OPEN POPOUTS ON WEST WALL NEAR SOUTH PORTAL;
NOTE SOME HAVE BEEN PATCHED
PHOTO #20 - FADED REFLECTOR ON EAST SIDE AT SOUTH PORTAL;
PHOTO #21 - EFFLORESCENCE AT
RINGSTONES ON WEST SIDE OF SOUTH
PORTAL
PHOTO #22 - VERTICAL CLEARANCE SIGN AT
SOUTH APPROACH (PHOTO FROM 6/26/13
INSPECTION)