Bridge_Inspection_Rpt_STR_5140-129P.pdf
PDF 3 MB Posted
- Attached to
- Blue Ridge Parkway Pavement Preservation Federal contract opportunity
- Solicitation number
- 693C73-18-R-000004
About this file
Bridge Inspection Report_STR_5140-129P
View the file
Other files for this federal contract opportunity
Show all 44
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BRIDGE INSPECTION REPORT
U.S. ROUTE 19 BRIDGE
BLUE RIDGE PARKWAY OVER U.S. ROUTE 19
BLUE RIDGE PARKWAY
LN
STRUCTURE NO. 5140-129P
INSPECTION TYPE: ROUTINE
INSPECTION DATE: 6/16/15
Report prepared by: WS
MILE POINT: 455.68
Federal Highway Administration KILOMETER POINT: 733.36 Federal Lands Bridge Office Bridge Inspection and Management Program 21400 Ridgetop Circle Sterling, Virginia 20166 https://bridge.flhd.fhwa.dot.gov
STRUCTURE SUMMARY STRUCTURE NO. 5140-129P
U.S. ROUTE 19 BRIDGE INSPECTION DATE: 6/16/15
BRIDGE IDENTIFICATION AND DESCRIPTION
MAIN SPAN MATERIAL: ....... PRESTRESSED CONCRETE NO. OF MAIN SPANS:
MAIN SPAN TYPE: ............... BOX BEAMS - MULTIPLE NO. OF APPR. SPANS:
# OF BEAMS, MAIN SPAN: .. 10 STRUCT. TOTAL LENGTH: .. 253.0 FT (77.1 M)
DECK TYPE: ......................... CONCRETE CAST-IN-PLACE MAX. SPAN LENGTH: .......... 73.0 FT (22.3 M) WEARING SURFACE: .......... BITUMINOUS DECK WIDTH: ...................... 33.0 FT (10.1 M) ABUT. FOUNDATIONS: ........ SPREAD FOOTING ON PILES CURB TO CURB WIDTH: ..... 25.8 FT (7.9 M)
PIER FOUNDATION(S): ........ SPREAD FOOTING ON PILES YEAR BUILT:
ABUTMENT / PIER MAT'L: ... CONCRETE YEAR RECONSTRUCTED: .. N/A
PROJ./PLAN REF. NO: ......... 2X4 / SKEW ANGLE: ..................... 50 °
NPS ROAD CLASS: .............. 1 - PRINCIPAL PARK ROAD FRACTURE CRITICAL: ........ NO
STRUCTURE HISTORY: ...... 1985-JOINT REPAIR. 1995-WEARING SURFACE REPLACED.
LOCATION
BLUE RIDGE PARKWAY MILE POINT: ..................... 455.68 (KM PT 733.36)
STATE: ................................. NORTH CAROLINA LOCATION: 12.7 MILES TO U.S. ROUTE 74 & 23.
FACILITY CARRIED: ............ BLUE RIDGE PARKWAY
FEATURE INTERSECTED: .. U.S. ROUTE 19
STRUCTURE EVALUATION SUMMARY
This concrete box beam bridge is in fair condition overall. The most serious problem is the severe cracking and bulging of Beam #10 in Spans #1 and #2. Other problems include moderate cracking of Beam #4 in Span #1; minor spalls on underside of the beams, some with exposed rebar; deflection of the exterior beams under dead load in all spans; an area of erosion at Pier #2; spalling with exposed rebar on the north face of Pier #3 cap; small trees growing on both sides of Pier #1 cap and north abutment cap; and a lack of object markers on Piers #2 and #3 along the underpass roadway and at the ends of the approach parapets.
Corrective action should be taken as outlined in this report to prevent the possible development of more serious or costly problems in the future.
INSPECTION TEAM: C. CASTRO, R. SILVESTRY
CONDITION ASSESSMENT:
CARLOS CASTRO, P.E., FIELD TEAM LEADER 571-434-1546
REPORT REVIEW:
MARCUS MILLER, P.E., SENIOR INSPECTION ENGINEER 703-404-6252
REPORT APPROVAL: DATE: 12/31/15
JORGOMAI CEESAY, PH.D., P.E., BIP SUPERVISORY ENGINEER 703-404-6244
RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 5140-129P
A (Critical) - Structure is closed, in imminent danger of collapse, or presents a critical safety hazard.
B (Major) - Structure is seriously deficient or presents a safety hazard, but can remain in service at reduced loads or with frequent inspections.
C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.
D (Minor) - Structure is generally in good condition. Preventative maintenance may be required.
E (Special) - Structure is under construction or reconstruction.
C226 PRIORITY OF IMPROVEMENT
ITEM
NO.
MAINTENANCE RECOMMENDATIONS
(GENERALLY NOT FLHP ELIGIBLE)
QTY. UNIT COST
UNIT
ESTIMATE
COST
PRELIM.
60.1,12,15 REMOVE TREES FROM UNDERSIDE OF SPAN #1. REMOVE TREES FROM PIER #1
CAP AND BELOW OVERHANG ON EAST SIDE OF NORTH ABUTMENT.
1 LS $3,000 $3,000
59.2, 60.15 CLEAN EXPOSED REBAR AND SEAL WITH APPROVED PROTECTIVE COATING ON
PIER #3 CAP AND BEAMS #2 AND #8 IN SPAN #3.
1 LS $2,000 $2,000
222.7 INSTALL TYPE 3 OBJECT MARKER TAPE AT PIERS #2 AND #3 OF UNDERPASS
ROADWAY AND AT ENDS OF APPROACH PARAPETS.
8 EA $250 $2,000
PRELIM. MAINTENANCE TOTAL : $7,000
ITEM
NO.
REHABILITATION/RECONSTRUCTION
(TYPICALLY NEEDED WITHIN 5 YEARS) QTY. UNIT UNIT
COST ESTIMATES
PRELIM. COST
REHAB. RECONSTR.
59.2 REPAIR BEAM #10 IN SPAN #1, AND #2. 1 LS $81,000 $82,000 $0
60.17 FILL AND STABILIZE AREA OF EROSION AT PIER #2. 20 CY $500 $10,000 $0
59 CONTRACT COSTS FOR MOBILIZATION, TRAFFIC CONTROL, AND
DESIGN/CONSTRUCTION ENGINEERING.
1 LS $68,000 $68,000 $0
PRELIM. REHABILITATION/RECONSTRUCTION TOTAL : $160,000 $0
COST ESTIMATE SUMMARY
PRELIM. MAINTENANCE TOTAL:
PRELIM. REHABILITATION TOTAL:
PRELIM. RECONSTRUCTION TOTAL: ...
TOTAL ITEMIZED COSTS:
$0 $160,000 $7,000
$167,000
PRELIMINARY ESTIMATE TOTAL* :
(*Includes typical contract costs for mobilization, traffic control, and design/construction engineering; but does not include detour bridges, work beyond the bridge limits, or work not listed above. Estimates are approximate and are for preliminary planning purposes only; they should not be used as a complete or final engineers estimate.)
$167,000
REMARKS: Deflection of exterior beams will continue to be monitored.
Cost estimates assume that recommended actions will be combined with similar work being performed on other structures.
FIELD INSPECTION REPORT STRUCTURE NO. 5140-129P
G = GOOD (CODES 7 - 9) F = FAIR (CODES 5 - 6) P = POOR (CODES 0 - 4)
CONDITION RATING CODE EQUIVALENTS FOR SUB-ELEMENTS
SERIOUS CONDITION - loss of section, deterioration, spalling, or scour have seriously affected primary structural components. Local failures are possible.
Fatigue cracks in steel or shear cracks in concrete may be present.
CRITICAL CONDITION - advanced deterioration of primary structural elements. Fatigue cracks in steel or shear cracks in concrete may be present or scour may have removed substructure support. Unless closely monitored it may be necessary to close the structure until corrective action can be taken.
“IMMINENT” FAILURE CONDITION - major deterioration or section loss present in critical structural components or obvious vertical or horizontal movement affecting structure stability. Structure is closed to traffic but corrective action may return structure to light service.
FAILED CONDITION - out of service; beyond corrective action.
CONDITION RATING CODES FOR ITEMS 58 - 62, 222, 223
NOT APPLICABLE
EXCELLENT CONDITION
VERY GOOD CONDITION - no problems noted.
GOOD CONDITION - some minor problems.
SATISFACTORY CONDITION - structural elements show some minor deterioration.
FAIR CONDITION - all primary structural elements are sound but may have minor section loss, cracking, spalling, or scour.
POOR CONDITION - advanced section loss, deterioration, spalling, or scour.
N
58. DECK ITEM REFERENCE AND REMARKS
OTHER
ALIGNMENT
DEFLECTION AND/OR VIBRATION
FASCIA(E)
DIAPHRAGMS AND BRACING
TRUSSES
FLOOR BEAMS AND STRINGERS
ARCH(ES) OR SLAB(S)
GIRDERS OR BEAMS
BEARING DEVICES
59. SUPERSTRUCTURE
OTHER
DEFLECTION AND/OR VIBRATION
UTILITIES
DRAINS AND DRAINAGE
PARAPETS AND/OR RAILINGS
CURBS, SIDEWALKS, AND MEDIAN
RIDEABILITY
WEARING SURFACE
EXPANSION JOINTS
DECK SLAB
OTHER
SETTLEMENT OR DEFLECTION
EROSION AND/OR SCOUR
FOUNDATIONS
CAPS AND/OR BEARING SEATS
PILE BENTS
WALLS AND/OR COLUMNS
PIER(S)
OTHER
SLOPE PROTECTION
SETTLEMENT OR DEFLECTION
EROSION AND/OR SCOUR
EXPANSION JOINTS
WEEP HOLES
WINGWALLS
FOUNDATIONS
BACKWALLS AND/OR BULKHEADS
CAPS AND/OR BEARING SEATS
PILE BENTS
BREASTWALLS OR COLUMNS
ABUTMENTS
60. SUBSTRUCTURE
1.
10.
2.
3.
4.
5.
6.
7.
8.
9.
10.
9.
8.
7.
6.
5.
4.
3.
2.
1.
PAINT
11.
G F G N N N N N F
N G
G N N G N G N N G G N F(Trees)
G N G N F G N
11.
10.
9.
8.
7.
6.
5.
4.
3.
2.
1.
12.
13.
14.
15.
16.
17.
18.
19.
58.5,6 MINOR CRACKING ON CURBS, SIDEWALKS, AND PARAPETS. MINOR
DELAMINATION AND SPALL OF CURB AT SOUTH END OF WEST
CURB. MINOR DELAMINATION OF EAST SIDEWALK NEAR SOUTH
END.
TREE GROWING AT EAST SIDE OF NORTH ABUTMENT WITH LIMBS
OVERHANGING EAST BRIDGE RAIL. TREE LIMBS ARE
OVERHANGING WEST RAIL IN SPANS #2 AND #3.
58.6 FEW LOOSE NUTS ON RAIL POSTS.
59.2 BEAM #10 IN SPAN #1 AND SPAN #2 HAS MINOR SAGGING.
MODERATE CRACK DEVELOPING INTO SPALL ON BOTTOM CORNER
OF BEAM #4 SPAN #1 ABOUT 2' NORTH OF PIER #1; ALSO, CRACK AT
15' NORTH OF PIER #1. MINOR LEAKAGE AND EFFLORESCENCE
BETWEEN BEAMS.
MODERATE CRACKING WITH EFFLORESCENCE AND DELAMINATION
ON BEAM #10 IN SPAN #2 NEAR PIER #1. TRANSVERSE CRACKING
OF BEAM #10 AT APPROXIMATE CENTERLINE IN SPAN #2. WEST
WEB OF BEAM #10 IS BULGING OUTWARD AT SPAN #2. SEVERAL
MINOR SPALLS WITH EXPOSED REBAR DUE TO INSUFFICIENT
COVER ON EAST SIDE OF BEAM #1 IN SPAN #2.
MINOR SPALLS DEVELOPING ON OVERHANG AREAS THROUGHOUT.
MINOR SPALL WITH EXPOSED REBAR ON UNDERSIDE OF BEAM #2
IN SPAN #3. MINOR SPALL WITH EXPOSED REBAR ON UNDERSIDE
OF BEAM #8 IN SPAN #3, AND BEAM #9 IN SPAN #3 NEAR PIER #3.
NUMEROUS EXPOSED AND RUSTED REBAR CHAIRS ALSO VISIBLE.
EXTERIOR BEAMS ARE DEFLECTED 1"-2" UNDER DEAD LOAD IN ALL
SPANS. BEAMS MAY BE DEFLECTED FROM ADDITIONAL DEAD LOAD
OF CURBS AND RAILINGS. SEVERAL BEAMS MAY HAVE SLIGHT
FREEZE/THAW DAMAGE; HOLES HAVE BEEN DRILLED IN
UNDERSIDE FOR DRAINAGE ON EXTERIOR BEAMS. MODERATE
WATER STAINS ON EXTERIOR BEAMS.
60.1 MINOR CRACKING ON NORTH ABUTMENT BREASTWALL.
G G F G G N
N
N
G
F
FIELD INSPECTION REPORT STRUCTURE NO. 5140-129P
ITEM REFERENCE AND REMARKS
STREAM BED COMPOSITION : 9.
AVERAGE CLEAR OPENING8.
NORMAL VELOCITY 7.
ADEQUACY OF OPENING6.
OTHER 5.
WATERWAY OBSTRUCTIONS 4.
CHANNEL PROTECTION3.
EROSION AND/OR SCOUR2.
ALIGNMENT1.
61. CHANNEL N
222. APPROACHES 7
OTHER 9.
ALIGNMENT8.
SIGNS 7.
SETTLEMENT6.
EROSION5.
SURFACING 4.
APPROACH GUARDRAIL 3.
RELIEF JOINTS2.
1. APPROACH SLABS N
N N G G G P G N
223. RETAINING WALL N
OTHER 6.
SETTLEMENT OR DEFLECTION5.
EROSION AND/OR SCOUR4.
FOUNDATION3.
WEEP HOLES2.
1. WALL
36. TRAFFIC AND SAFETY FEATURES
APPROACH GUARDRAIL ENDS D.
APPROACH GUARDRAILS C.
TRANSITIONS B.
BRIDGE RAILINGSA. 1
N N N
60.3 ABUTMENT BEARING SEATS, BREASTWALLS AND PIERS HAVE
STAINING FROM PREVIOUS LEAKAGE.
60.6,9 MINOR TO MODERATE EROSION OF FILL SLOPE AT NORTH
ABUTMENT. EROSION AND UNDERMINING (7'L X15"D) ALONG
SOUTHWEST WINGWALL.
60.12 TREES GROWING AT EAST SIDE OF NORTH ABUTMENT. TREES
GROWING UNDER SPAN #1 ENCROACHING SUPERSTRUCTURE.
60.15 TYPICAL CONCRETE SCALING AT ALL PIERS. MINOR CRACKING ON
PIER #2 CAP WITH EFFLORESCENCE. WATER LEAKING THROUGH
JOINTS ONTO PIER BEARING SEATS. WATER STAINING ON ALL
PIERS. SMALL TREE GROWING OUT OF JOINT ON EAST SIDE OF
PIER #1 CAP. MINOR SPALL WITH EXPOSED REBAR DUE TO
INSUFFICIENT CONCRETE COVER ON NORTH FACE OF PIER #3 CAP
AT TWO SPOTS.
60.17 MODERATE TO SEVERE EROSION AT BASE OF PIER #2 FROM
UNDERPASS ROADWAY DRAINAGE; ENCROACHING ON ROADWAY
AND IS POTENTIAL TRAFFIC HAZARD.
222.4,5 MINOR TRANSVERSE CRACKING OF WEARING SURFACE AT END OF
APPROACHES. MINOR GRAVEL ACCUMULATION ON WEST SIDE OF
NORTH APPROACH.
222.7 NO OBJECT MARKERS AT ENDS OF BRIDGE PARAPETS. NO OBJECT
MARKERS AT PIERS ADJACENT TO UNDERPASS ROADWAY.
TRAFFIC SAFETY RATING CODES
N
Does not meet standards or a safety feature is required and none is provided.
Meets currently acceptable standards.
Not applicable or a safety feature is not required.
STRUCTURE LOAD RATING STRUCTURE NO. 5140-129P
TRUCK TYPE
INVENTORY RATING (NORMAL TRAFFIC) OPERATING RATING (MAXIMUM LOAD)
TONS METRIC TONS TONS METRIC TONS
H 15 14 25 23
HS 20 18 33 30
TYPE 3 19 17 31 28
TYPE 3S2 24 22 40 36
TYPE 3-3 28 26 47 43
DESIGN LOADING: H15 (M13.5)
X CAPACITY MEETS OR EXCEEDS DESIGN LOAD
CAPACITY IS LESS THAN DESIGN LOAD
ORIGINAL LOAD RATING CALCULATION APPLICABLE
ORIGINAL LOAD RATING CALCULATION REVISED
DATE OF LOAD RATING CALCULATION:
LOAD RATING CONTROLLED BY:
REMARKS: RATING IS BASED ON DESIGN LOAD OF STRUCTURE.
STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 5140-129P
STRUCTURE IDENTIFICATION
(201) PARK: BLUE RIDGE PARKWAY (1) STATE: ....................................... 374 - NORTH CAROLINA (NC)
(202) STRUCTURE NAME: .......... U.S. ROUTE 19 BRIDGE (2) STATE HWY. AGENCY DIST:
(203) STRUCTURE KIND: ............1 - BRIDGE (3) COUNTY CODE: ........................ 087 - HAYWOOD
(204) STRUCTURE NUMBER: ..... 5140-129P (4) CITY/PLACE CODE:
(205) NPS REGION: .................... 4 - SOUTHEAST (5) INVENTORY ROUTE:
(206) ROUTE CODE NUMBER: ... 1 (6) FEATURES INTERSECTED:....... U.S. ROUTE 19
(207) ROAD SECTION NO: .......... 129P (7) FACILITY CARRIED: .................. BLUE RIDGE PARKWAY
(208) NPS ROAD CLASS: ............ 1 - PRINCIPAL PARK ROAD (8) STATE STRUCTURE NO: .......... 5140129P0000000
(209) WITHIN NPS BNDRY?: ....... YES (9) LOCATION: ................................ 12.7 MILES TO U.S. ROUTE
(210) OPERATING UNIT: ............. PARK (10) INV. RTE. - MIN. VERT. CLR: .. 99.99 FT (99.99 M)
(211) PROJECT NO(S): ................ 2X4 (11) MILE POINT: ............................. 455.68 (KM PT 733.36)
(212) DRAWING NUMBERS: ....... (27) YEAR BUILT:
(21) MAINTAINED BY: ................. 66 - NATIONAL PARK SERVICE (106) YEAR RECONSTRUCTED: .... N/A
(22) OWNER: ............................... 66 - NATIONAL PARK SERVICE (20) TOLL: ........................................ 3 - FREE ROAD
(37) HISTORICAL DESIGNATION: .. 5 - NOT ELIGIBLE
STRUCTURE DESCRIPTION, FOUNDATION, AND DECK TYPE
(43A) MAIN STR. MATERIAL: ..
(43B) MAIN STR. TYPE:
(45) NO. OF MAIN SPANS:
(48) MAX. SPAN LENGTH:
(49) STRUCTURE LENGTH:
(216A) ABUTMENT #1 FDN:
(216B) ABUTMENT #2 FDN:
(217A) PREDOM. PIER FDN.: ..
(217B) SECOND. PIER FDN: ...
(107) DECK TYPE:
5 - PRESTRESSED CONCRETE
05 - BOX BEAMS - MULTIPLE
73.0 FT (22.3 M)
253.0 FT (77.1 M)
3 - SPREAD FOOTING ON PILES
3 - SPREAD FOOTING ON PILES
3 - SPREAD FOOTING ON PILES
3 - SPREAD FOOTING ON PILES
1 - CONCRETE CAST-IN-PLACE
(44A) APPR. STR. MATERIAL: ........ 0 - OTHER
(44B) APPR. STR. TYPE: ................ 00 - OTHER
(46) NO. OF APPROACH SPANS: .. 0
(108) WEAR SURFACE/PROTECT SYSTEM:
A) TYPE WEARING SURFACE: .. 6 - BITUMINOUS
B) TYPE MEMBRANE: ................. 8 - UNKNOWN
C) TYPE PROTECTION: .............. 0 - NONE
(218) IS SALT USED?: ..................... YES
LOAD RATING AND POSTING
(31) DESIGN LOAD: ................. 2 - H15 (M13.5) (41) LOAD RESTRICTION: ......... A - OPEN, NO RESTRICTION
(66) INVENTORY RATING: ...... 19.6 TONS (17.8 METRIC TONS) (70) BRIDGE POSTING: .............. 5 - NO POSTING REQUIRED
(64) OPERATING RATING: ...... 32.8 TONS (29.8 METRIC TONS)
INSPECTION DATES
(90) INSPECTION DATE: 6/15 (91) FREQ. OF INSP: 24 MONTHS (92 / 93) CRITICAL FEATURE INSPECTION (CFI):
(219) ADD. STUDIES NEEDED: N - 0 - NONE (A) FRACTURE CRITICAL: ... NO
INSP. EVERY: MONTHS - LAST INSP. : (220) SPECIAL STUDY TYPE: 0 - NONE
(B) UNDERWATER: .............. NO
(221) SPECIAL STUDY DATE: INSP. EVERY: MONTHS - LAST INSP. :
(C) SPECIAL INSPECTION: .. NO
INSP. EVERY: MONTHS - LAST INSP. :
STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 5140-129P
GEOMETRY, TRAFFIC, AND NAVIGATIONAL DATA
(51) CURB TO CURB WIDTH: ........... 25.8 FT (7.9 M) (16) LATITUDE: ............................. 35°29'46.80"
(17) LONGITUDE: ......................... 83°09'20.20"
(19) DETOUR LENGTH: ............... 30 MI (48 KM)
(28A) LANES ON STRUCT:
(28B) LANES UNDER STRUCT: ... 02
(42A) SERVICE ON: ..................... 5 - HIGHWAY-PEDESTRIAN
(42B) SERVICE UNDER: .............. 1 - HIGHWAY
(29) AVG. DAILY TRAFFIC:
(30) YEAR OF ADT:
(114) FUTURE ADT:
(115) YEAR OF FUTURE ADT:
(101) PARALLEL STRUCTURE: ... N - NONE
(38) NAVIGATION CONTROL?: ... N
(39) VERTICAL CLEARANCE: ...... 0.0 FT (0.0 M)
(40) HORIZ. CLEARANCE: ........... 0.0 FT (0.0 M)
(111) ABUT. OR PIER PROT:
LATERAL UNDERCLEARANCE:
(55) RIGHT: ....................... 6.0 FT (1.8 M)
(56) LEFT: ......................... 0.0 FT (0.0 M)
CONDITION AND APPRAISAL DATA, PROPOSED IMPROVEMENTS, AND COST
(58) DECK:
(59) SUPERSTRUCTURE:
(60) SUBSTRUCTURE:
(61) CHANNEL: .......................... N
(62) CULVERT: ........................... N
(222) APPROACHES:
(223) RETAINING WALL: ........... N
(36) TRAFFIC SAFETY FEAT: ... 1NNN
(75A) TYPE OF WORK:
(75B) WORK DONE BY:
(76) IMPROVEMENT LENGTH: ..
(52) DECK WIDTH:
(32) APPR. ROADWAY WIDTH:
(213) APPR. PAVEMENT WIDTH:
LEFT SHOULDER:
RIGHT SHOULDER:
(33) BRIDGE MEDIAN:
(34) SKEW ANGLE:
(35) DECK FLARE?:
(47) TOTAL HORIZ. CLEARANCE:
(50) SIDEWALKS:
LEFT :
RIGHT :
(214) BRIDGE RAIL TYPE:
RAIL CONFIGURATION:
MATERIAL:
DESIGN TYPE:
(215) BRIDGE RAIL HEIGHT:
(53) MIN. VRT. CLEAR. OVER DECK:
(54) MIN. VRT. UNDERCLEARANCE:
33.0 FT (10.1 M)
38.0 FT (11.6 M)
22.0 FT (6.7 M)
8.0 FT (2.4 M)
8.0 FT (2.4 M)
0 - NO MEDIAN
50 °
NO
25.8 FT (7.9 M)
2.5 FT (0.8 M)
2.5 FT (0.8 M)
2 - MOUNTED ON PARAPET
3 - CONCRETE/STEEL
1 - CONTINUOUS RAIL
2.50 FT (0.76 M)
99.99 FT (99.99 M)
15.08 FT (4.60 M)
(67) STRUCTURAL EVALUATION:
(68) DECK GEOMETRY:
(69) UNDERCLEARANCES:
(71) WATERWAY ADEQUACY:
(72) APPROACH ALIGNMENT:
(113) SCOUR CRITICAL:
(225) PURPOSE OF IMPROVEMENT:
(226) PRIORITY OF IMPROVEMENT:
(227) MAINTENANCE COST:
(228) REHAB./RECONSTR. COST: ...
(229) CONSTRUCTION COST:
N
N - Not over waterway.
2 - REHAB/RECONSTRUCTION
C - MODERATE
$7,000
$160,000
$0
ADDITIONAL INFORMATION
(230) STRUCTURE HISTORY:
1985-JOINT REPAIR. 1995-WEARING SURFACE REPLACED.
(231) ADDITIONAL CONSIDERATIONS:
(330) ADDITIONAL CONFIG. INFO.:
APPENDIX STRUCTURE NO. 5140-129P
PHOTOGRAPHS STRUCTURE NO. 5140-129P
PHOTO #1 - LOOKING SOUTH TOWARD CHEROKEE
PHOTO #2 - EAST SIDE; NOTE VEGETATION GROWTH AT NORTHEAST
CORNER AND ALSO ON EAST SIDE OF PIER #1 CAP
PHOTO #3 - GENERAL TOPSIDE VIEW
LOOKING SOUTH
PHOTO #4 - PATCHED AREA AT JOINT OVER
PIER #1
PHOTO #5 - SPALLING ON WEST PARAPET ABOVE PIER #1
PHOTO #6 - CRACKING WITH EFFLORESCENCE AND DELAMINATION
ALONG WEST CURBLINE NEAR PIER #2
PHOTO #7 - SPALLING AND DELAMINATION ON WEST PARAPET ABOVE
PIER #2
PHOTO #8 - CRACKING WITH EFFLORESCENCE ON WEST CURB ABOVE
PIER #2
PHOTO #9 - RECENTLY REPAIRS ON EAST
PARAPET AT SPAN 3; NOTE CRACKING ALONG
SIDEWALK
PHOTO #10 - DETERIORATION OF JOINT
FILLING IN CURB AT NORTHEAST CORNER
PHOTO #11 - TRANSVERSE CRACKING ON
APPROACH PAVEMENT AT END OF NORTH
APPROACH
PHOTO #12 - TRANSVERSE CRACKING ON
APPROACH PAVEMENT AT END OF SOUTH
APPROACH ALONG NORTHBOUND LANE
PHOTO #13 - TRANSVERSE CRACKING IN
APPROACH PAVEMENT AT END OF SOUTH
APPROACH ALONG SOUTHBOUND LANE
PHOTO #14 - SPALLING OF FINISH COAT AT
EAST SIDEWALK NEAR SOUTH END
PHOTO #15 - DEBRIS ACCUMULATION ALONG
WEST CURBLINE, NORTH END SHOWN
PHOTO #16 - CRACKING OF PAVEMENT AND
SETTLEMENT AT SOUTHEAST CORNER
PHOTO #17 - GENERAL UNDERSIDE VIEW OF
SPAN #1 LOOKING NORTH
PHOTO #18 - UNDERSIDE VIEW OF SOUTH
SPAN, NOTE EXPOSED REBAR CHAIRS
PHOTO #19 - SPALL WITH EXPOSED REBAR ON EAST FACE OF BEAM #1
NEAR PIER #1
PHOTO #20 - TYPICAL EXPOSURE OF REBAR CHAIRS ON BEAM #6,
SPAN #1 NEAR PIER #1
PHOTO #21 - LEAKAGE, SAGGING, AND STAINING ON UNDERSIDE OF
BEAM #10 AT SPAN #1
PHOTO #22 - SAG IN BEAM #10 AT SPAN #1
PHOTO #23 - CRACKING WITH EFFLORESCENCE ON WEST SIDE OF
BEAM #10 ON SPAN #1
PHOTO #24 - CRACKING WITH EFFLORESCENCE ON UNDERSIDE OF
BEAM #10 IN SPAN #2; NOTE WATER LEAKAGE
PHOTO #25 - EVIDENCE OF ACTIVE WATER
LEAKAGE AND WATER STAINING ALONG JOINT
BETWEEN BEAM #1 AND #2 IN SPAN #2
PHOTO #26 - EXPOSURE OF FILLING MATERIAL
IN JOINT OVER PIER #2, EAST SIDE
PHOTO #27 - SPALL WITH EXPOSED REBAR ON UNDERSIDE OF BEAM
#2 IN SPAN #3
PHOTO #28 - SPALLING WITH EXPOSED REBAR ON UNDERSIDE OF BAY
#8 AND #9 AT PIER #3, NORTH FACE SHOWN
PHOTO #29 - PATCHING ON EXTERIOR SIDE OF BOX GIRDER AT EAST
SIDE NEAR SOUTH END
PHOTO #30 - GENERAL VIEW OF NORTH ABUTMENT; NOTE EVIDENCE
OF ACTIVE WATER LEAKAGE THROUGH JOINT ON WEST SIDE
PHOTO #31 - WATER STAINING ON EAST SIDE OF NORTH ABUTMENT;
NOTE WET BEARING SEAT
PHOTO #32 - TREE GROWING ON EAST SIDE OF NORTH ABUTMENT;
NOTE ALSO SOME TREES GROWING UNDER SPAN #1, ENCROACHING
ON SUPERSTRUCTURE
PHOTO #33 - GENERAL VIEW OF SOUTH ABUTMENT; NOTE MOSS
GROWTH AND EVIDENCE OF PREVIOUS LEAKAGE THROUGH JOINTS IN
BEARING SEAT
PHOTO #34 - VERTICAL CRACKING ON PIER #1 ON NORTH FACE
UNDERNEATH BEAM #4
PHOTO #35 - GENERAL VIEW OF PIER #2;
NOTE WATER STAINING DUE TO WATER
LEAKAGE THROUGH JOINT
PHOTO #36 - EROSION AT WEST SIDE OF PIER
#2
PHOTO #37 - SPALL ON WEST SIDE OF PIER #2
CAP
PHOTO #38 - SPALLING WITH EXPOSED
REBAR ON NORTH SIDE OF PIER #3
PHOTO #39 - MOSS GROWTH AND BEARING PAD EXTRUDING FROM
SEAT AT WEST END OF PIER CAP #3
PHOTO #40 - UP TO 15" TOWARD CENTERLINE X 7' OF UNDERMINING
ALONG SOUTHEAST WINGWALL
File details come from the government source that posted it.