Bridge_Inspection_Rpt_STR_5140-139P.pdf
PDF 1 MB Posted
- Attached to
- Blue Ridge Parkway Pavement Preservation Federal contract opportunity
- Solicitation number
- 693C73-18-R-000004
About this file
Bridge Inspection Report_STR_5140-139P
View the file
Other files for this federal contract opportunity
Show all 44
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TUNNEL INSPECTION REPORT
CRAGGY PINNACLE TUNNEL
BLUE RIDGE PARKWAY THROUGH CRAGGY PINNACLE MOUNTAIN
BLUE RIDGE PARKWAY
NP
STRUCTURE NO. 5140-139P
INSPECTION TYPE: ROUTINE
INSPECTION DATE: 6/9/15
Report prepared by: SP
MILE POINT: 364.39
Federal Highway Administration KILOMETER POINT: 586.41 Federal Lands Bridge Office Bridge Inspection and Management Program 21400 Ridgetop Circle Sterling, Virginia 20166 https://bridge.flhd.fhwa.dot.gov
STRUCTURE SUMMARY STRUCTURE NO. 5140-139P
CRAGGY PINNACLE TUNNEL INSPECTION DATE: 6/9/15
TUNNEL IDENTIFICATION AND DESCRIPTION
LINING MATERIAL: ............... UNLINED / CONCRETE MINIMUM VERTICAL CLR: .... 13.5 FT (4.1 M)
SPRINGLINE LENGTH: ........ 29.7 FT (9.1 M) STRUCT. TOTAL LENGTH: ... 246.0 FT (75.0 M)
CURB TO CURB WIDTH: ..... 29.7 FT (9.1 M) YEAR BUILT:
PROJ./PLAN REF. NO: ......... 2PI,2P6,2L10 / YEAR RECONSTRUCTED:
NPS ROAD CLASS: .............. 1 - PRINCIPAL PARK ROAD
STRUCTURE HISTORY: ...... 1956-NORTH/SOUTH LININGS AND PORTALS; 1992-MAJOR RECONSTRUCTION:
SUPERSTRUCTURE, ROCKBOLTS, AND SCREENING; 2008-DRAIN CHASE REPAIR.
LOCATION
BLUE RIDGE PARKWAY MILE POINT: ..................... 364.39 (KM PT 586.41)
STATE: .................................. NORTH CAROLINA LOCATION: 9.2 MILES TO NC ROUTE 128
FACILITY CARRIED: ............. BLUE RIDGE PARKWAY
FEATURE INTERSECTED: ... CRAGGY PINNACLE MOUNTAIN
STRUCTURE EVALUATION SUMMARY
This tunnel is in fair condition at this time. The most serious problem is the widespread leakage throughout the tunnel. During this inspection, minor to moderate leakage was found at both sides of the north portal, at the west side of the south portal, and through the tunnel lining cracks. The unlined portion of the tunnel was also found wet. The leakage from the tunnel plus running water into the tunnel from a ditch at the west side of the north approach cause the roadway through the tunnel to become wet and slippery, and might create icing and hazardous driving conditions during winter time. Signs at both approaches warn motorists of ice in the tunnel.
Other problems include a drop-off along the west curbline at the north approach, a barrel at the west side near the south portal, and some broken/missing reflectors along both sides of the tunnel. In addition, the clearance signs at both approaches show a vertical clearance higher than the actual one.
Corrective action should be taken as outlined in this report to prevent the possible development of more serious or costly problems in the future.
INSPECTION TEAM: C. CASTRO, R. SILVESTRY
CONDITION ASSESSMENT:
CARLOS CASTRO, P.E., FIELD TEAM LEADER 571-434-1546
REPORT REVIEW:
MARCUS MILLER, P.E., SENIOR INSPECTION ENGINEER 703-404-6252
REPORT APPROVAL: DATE: 12/31/15
JORGOMAI CEESAY, PH.D., P.E., BIP SUPERVISORY ENGINEER 703-404-6244
RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 5140-139P
A (Critical) - Structure is closed, in imminent danger of collapse, or presents a critical safety hazard.
B (Major) - Structure is seriously deficient or presents a safety hazard, but can remain in service at reduced loads or with frequent inspections.
C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.
D (Minor) - Structure is generally in good condition. Preventative maintenance may be required.
E (Special) - Structure is under construction or reconstruction.
C226 PRIORITY OF IMPROVEMENT
ITEM
NO.
MAINTENANCE RECOMMENDATIONS
(GENERALLY NOT FLHP ELIGIBLE)
QTY. UNIT COST
UNIT
ESTIMATE
COST
PRELIM.
59.8 REPLACE MISSING REFLECTORS ALONG BOTH SIDE OF TUNNEL AS NECESSARY.
REMOVE BARREL FROM WEST SIDE.
1 LS $2,000 $2,000
222.7 POST CORRECT VERTICAL CLEARANCE ON SIGNS AT BOTH APPROACHES. 2 EA $250 $500
PRELIM. MAINTENANCE TOTAL : $2,500
ITEM
NO.
REHABILITATION/RECONSTRUCTION
(TYPICALLY NEEDED WITHIN 5 YEARS) QTY. UNIT UNIT
COST ESTIMATES
PRELIM. COST
REHAB. RECONSTR.
59.1 SEAL CRACKS IN LINING. 150 LF $100 $15,000 $0
59.4 INSTALL ROADWAY DRAINAGE SYSTEM ALONG TUNNEL. 500 LF $50 $25,000 $0
59 CONTRACT COSTS FOR MOBILIZATION, TRAFFIC CONTROL, AND
DESIGN/CONSTRUCTION ENGINEERING.
1 LS $20,000 $20,000 $0
PRELIM. REHABILITATION/RECONSTRUCTION TOTAL : $60,000 $0
COST ESTIMATE SUMMARY
PRELIM. MAINTENANCE TOTAL:
PRELIM. REHABILITATION TOTAL:
PRELIM. RECONSTRUCTION TOTAL: ...
TOTAL ITEMIZED COSTS:
$0 $60,000 $2,500
$62,500
PRELIMINARY ESTIMATE TOTAL* :
(*Includes typical contract costs for mobilization, traffic control, and design/construction engineering; but does not include detour bridges, work beyond the bridge limits, or work not listed above. Estimates are approximate and are for preliminary planning purposes only; they should not be used as a complete or final engineers estimate.)
$62,500
REMARKS: Cost estimates assume that recommended actions will be combined with similar work being performed on other structures.
FIELD INSPECTION REPORT STRUCTURE NO. 5140-139P
CONDITION RATING CODES FOR ITEMS 58 - 62, 222, 223
N
NOT APPLICABLE
EXCELLENT CONDITION
VERY GOOD CONDITION - no problems noted.
GOOD CONDITION - some minor problems.
SATISFACTORY CONDITION - structural elements show some minor deterioration.
FAIR CONDITION - all primary structural elements are sound but may have minor section loss, cracking, spalling, or scour.
POOR CONDITION - advanced section loss, deterioration, spalling, or scour.
SERIOUS CONDITION - loss of section, deterioration, spalling, or scour have seriously affected primary structural components. Local failures are possible.
Fatigue cracks in steel or shear cracks in concrete may be present.
CRITICAL CONDITION - advanced deterioration of primary structural elements. Fatigue cracks in steel or shear cracks in concrete may be present or scour may have removed substructure support. Unless closely monitored it may be necessary to close the structure until corrective action can be taken.
“IMMINENT” FAILURE CONDITION - major deterioration or section loss present in critical structural components or obvious vertical or horizontal movement affecting structure stability. Structure is closed to traffic but corrective action may return structure to light service.
FAILED CONDITION - out of service; beyond corrective action.
CONDITION RATING CODE EQUIVALENTS FOR SUB-ELEMENTS
G = GOOD (CODES 7 - 9) F = FAIR (CODES 5 - 6) P = POOR (CODES 0 - 4)
59. TUNNEL 6
F
2. PORTALS
1. LINING
G
N3. CURBS AND SIDEWALKS
F4. DRAINS AND DRAINAGE
G5. WEARING SURFACE
G6. RIDEABILITY
N7. LIGHTING
F8. OTHER (REFLECTORS)
9. ADEQUACY OF OPENING SUFF
222. APPROACHES 7
N1. APPROACH SLABS
N2. RELIEF JOINTS
G3. APPROACH GUARDRAIL
G4. SURFACING
G5. EROSION
G6. SETTLEMENT
P7. SIGNS
F8. ALIGNMENT
N9. OTHER
223. RETAINING WALL N
1. WALL
2. WEEP HOLES
3. FOUNDATION
4. EROSION AND/OR SCOUR
5. SETTLEMENT OR DEFLECTION
6. OTHER
36. TRAFFIC AND SAFETY FEATURES
NA. BRIDGE RAILINGS
NB. TRANSITIONS
NC. APPROACH GUARDRAILS
ND. APPROACH GUARDRAIL ENDS
TRAFFIC SAFETY RATING CODES
0 - Does not meet standards or a safety feature is required and none is provided.
1 - Meets currently acceptable standards.
N - Not applicable or a safety feature is not required.
ITEM REFERENCE AND REMARKS
59.1,4 APPROXIMATELY 28' OF CONCRETE LINING AT EACH END OF
TUNNEL WITH REMAINING PORTION BEING UNLINED.
MINOR TO MODERATE CRACKING WITH EFFLORESCENCE AND
LEAKAGE FROM NORTH AND SOUTH CONCRETE LINING; SEE ALSO
59.4. DRAIN HOLE THROUGH LINING NEAR SOUTH PORTAL FILLED
WITH DEBRIS.
METAL SCREENING AND ROCKBOLTING IN UNLINED PORTION OF
TUNNEL WITH MINOR RUSTING OF EXPOSED PORTIONS OF
ROCKBOLTS. MODERATE LEAKAGE IN UNLINED SECTION, WHICH
CAN CAUSE LARGE ICE PATCHES TO FORM ACROSS ENTIRE
ROADWAY WHEN TEMPERATURE FALLS BELOW FREEZING. MINOR
CRACKING WITH EFFLORESCENCE ON SHOTCRETE TRANSITION.
59.2 ACTIVE MODERATE LEAKAGE ALONG BOTH SIDES OF NORTH
PORTAL AND WEST SIDE OF SOUTH PORTAL; SEE ALSO 59.4. MINOR
DETERIORATION OF MASONRY MORTAR JOINTS AT BASE OF NORTH
PORTAL. MINOR EFFLORESCENCE ON NORTH PORTAL RING
STONES. BARREL AT WEST SIDE OF SOUTH PORTAL.
59.4 GRAVEL ALONG WEST SHOULDER. WATER LEAKING AND RUNNING
ONTO ROADWAY FROM LEAKAGE AT BOTH PORTALS AND THROUGH
CRACKING OF TUNNEL LINING, AND FROM DITCH AT WEST SIDE OF
NORTH APPROACH.
59.8 ONE REFLECTOR IS MISSING ON WEST SIDE OF TUNNEL, AT NORTH
END, AND ONE PULLED OUT OF GROUND LEANING AGAINST WEST
WALL. TWO REFLECTORS MISSING AND TWO PULLED OUT OF
GROUND ON EAST SIDE.
222.3 MINOR CHECKING OF TIMBER RAILS AT SOUTH APPROACH, EAST
SIDE.
222.7 "14'-3" MINIMUM CLEARANCE" SIGNS POSTED AT APPROACHES;
ACTUAL MINIMUM CLEARANCE IS 12'-10". "CRAGGY PINNACLE
TUNNEL" SIGN POSTED AT BOTH APPROACHES. "WATCH FOR ICE IN
TUNNEL" SIGN AT NORTH APPROACH; "ICE ON PAVEMENT" SIGN AT
SOUTH APPROACH.
FIELD INSPECTION REPORT STRUCTURE NO. 5140-139P
ADDITIONAL ITEM REFERENCE AND REMARKS
222.8 MODERATELY SHARP CURVES AT BOTH APPROACHES.
STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 5140-139P
STRUCTURE IDENTIFICATION
(201) PARK: BLUE RIDGE PARKWAY (1) STATE: ....................................... 374 - NORTH CAROLINA (NC)
(202) STRUCTURE NAME: .......... CRAGGY PINNACLE TUNNEL (2) STATE HWY. AGENCY DIST:
(203) STRUCTURE KIND: ............3 - TUNNEL (3) COUNTY CODE: ........................ 021 - BUNCOMBE
(204) STRUCTURE NUMBER: ..... 5140-139P (4) CITY/PLACE CODE:
(205) NPS REGION: .................... 4 - SOUTHEAST (5) INVENTORY ROUTE:
(206) ROUTE CODE NUMBER: ... 1 (6) FEATURES INTERSECTED:....... CRAGGY PINNACLE MOUNTA
(207) ROAD SECTION NO: .......... 139P (7) FACILITY CARRIED: .................. BLUE RIDGE PARKWAY
(208) NPS ROAD CLASS: ............ 1 - PRINCIPAL PARK ROAD (8) STATE STRUCTURE NO: .......... 5140139P0000000
(209) WITHIN NPS BNDRY?: ....... YES (9) LOCATION: ................................ 9.2 MILES TO NC ROUTE 128
(210) OPERATING UNIT: ............. GILLESPE (10) INV. RTE. - MIN. VERT. CLR: .. 14.30 FT (4.36 M)
(211) PROJECT NO(S): ................ 2PI,2P6,2L10 (11) MILE POINT: ............................. 364.39 (KM PT 586.41)
(212) DRAWING NUMBERS: ....... (27) YEAR BUILT:
(21) MAINTAINED BY: ................. 66 - NATIONAL PARK SERVICE (106) YEAR RECONSTRUCTED:
(22) OWNER: ............................... 66 - NATIONAL PARK SERVICE (20) TOLL: ........................................ 3 - FREE ROAD
(37) HISTORICAL DESIGNATION: .. 5 - NOT ELIGIBLE
STRUCTURE DESCRIPTION, FOUNDATION, AND DECK TYPE
(43A) MAIN STR. MATERIAL: ..
(43B) MAIN STR. TYPE:
(45) NO. OF MAIN SPANS:
(48) MAX. SPAN LENGTH:
(49) STRUCTURE LENGTH:
(216A) ABUTMENT #1 FDN:
(216B) ABUTMENT #2 FDN:
(217A) PREDOM. PIER FDN.: ..
(217B) SECOND. PIER FDN: ...
(107) DECK TYPE:
0 - OTHER
18 - TUNNEL
29.7 FT (9.1 M)
246.0 FT (75.0 M)
6 - N/A
6 - N/A
6 - N/A
6 - N/A
N - NOT APPLICABLE
(44A) APPR. STR. MATERIAL: ........ 0 - OTHER
(44B) APPR. STR. TYPE: ................ 00 - OTHER
(46) NO. OF APPROACH SPANS: .. 0
(108) WEAR SURFACE/PROTECT SYSTEM:
A) TYPE WEARING SURFACE: .. 6 - BITUMINOUS
B) TYPE MEMBRANE: ................. 0 - NONE
C) TYPE PROTECTION: .............. 0 - NONE
(218) IS SALT USED?: ..................... NO
LOAD RATING AND POSTING
(31) DESIGN LOAD: ................. 0 - UNKNOWN (41) LOAD RESTRICTION: ......... R - POSTED (OTHER)
(66) INVENTORY RATING: ...... 0.0 TONS (0.0 METRIC TONS) (70) BRIDGE POSTING: .............. 5 - NO POSTING REQUIRED
(64) OPERATING RATING: ...... 0.0 TONS (0.0 METRIC TONS)
INSPECTION DATES
(90) INSPECTION DATE: 6/15 (91) FREQ. OF INSP: 24 MONTHS (92 / 93) CRITICAL FEATURE INSPECTION (CFI):
(219) ADD. STUDIES NEEDED: N - 0 - NONE (A) FRACTURE CRITICAL: ... NO
INSP. EVERY: MONTHS - LAST INSP. : (220) SPECIAL STUDY TYPE: 0 - NONE
(B) UNDERWATER: .............. NO
(221) SPECIAL STUDY DATE: INSP. EVERY: MONTHS - LAST INSP. :
(C) SPECIAL INSPECTION: .. NO
INSP. EVERY: MONTHS - LAST INSP. :
STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 5140-139P
GEOMETRY, TRAFFIC, AND NAVIGATIONAL DATA
(51) CURB TO CURB WIDTH: ........... 29.7 FT (9.1 M) (16) LATITUDE: ............................. 35°42'04.30"
(17) LONGITUDE: ......................... 82°22'34.80"
(19) DETOUR LENGTH: ............... 40 MI (64 KM)
(28A) LANES ON STRUCT:
(28B) LANES UNDER STRUCT: ... 02
(42A) SERVICE ON: ..................... 1 - HIGHWAY
(42B) SERVICE UNDER: .............. 0 - OTHER
(29) AVG. DAILY TRAFFIC:
(30) YEAR OF ADT:
(114) FUTURE ADT:
(115) YEAR OF FUTURE ADT:
(101) PARALLEL STRUCTURE: ... N - NONE
(38) NAVIGATION CONTROL?: ... N
(39) VERTICAL CLEARANCE: ...... 0.0 FT (0.0 M)
(40) HORIZ. CLEARANCE: ........... 0.0 FT (0.0 M)
(111) ABUT. OR PIER PROT:
LATERAL UNDERCLEARANCE:
(55) RIGHT: ....................... 0.0 FT (0.0 M)
(56) LEFT: ......................... 0.0 FT (0.0 M)
(52) DECK WIDTH:
(32) APPR. ROADWAY WIDTH:
(213) APPR. PAVEMENT WIDTH:
LEFT SHOULDER:
RIGHT SHOULDER:
(33) BRIDGE MEDIAN:
(34) SKEW ANGLE:
(35) DECK FLARE?:
(47) TOTAL HORIZ. CLEARANCE:
(50) SIDEWALKS:
LEFT :
RIGHT :
(214) BRIDGE RAIL TYPE:
RAIL CONFIGURATION:
MATERIAL:
DESIGN TYPE:
(215) BRIDGE RAIL HEIGHT:
(53) MIN. VRT. CLEAR. OVER DECK:
(54) MIN. VRT. UNDERCLEARANCE:
0.0 FT (0.0 M)
38.0 FT (11.6 M)
22.0 FT (6.7 M)
8.0 FT (2.4 M)
8.0 FT (2.4 M)
0 - NO MEDIAN
0 °
NO
29.7 FT (9.1 M)
0.0 FT (0.0 M)
0.0 FT (0.0 M)
0 - N/A
0 - N/A
0 - N/A
0.00 FT (0.00 M)
13.50 FT (4.11 M)
13.50 FT (4.11 M)
CONDITION AND APPRAISAL DATA, PROPOSED IMPROVEMENTS, AND COST
(58) DECK: ................................. N
(59) SUPERSTRUCTURE: .........N
(60) SUBSTRUCTURE: ..............N
(61) CHANNEL: .......................... N
(62) CULVERT: ........................... N
(222) APPROACHES:
(223) RETAINING WALL: ........... N
(36) TRAFFIC SAFETY FEAT: ... NNNN
(75A) TYPE OF WORK:
(75B) WORK DONE BY:
(76) IMPROVEMENT LENGTH: ..
(67) STRUCTURAL EVALUATION:
(68) DECK GEOMETRY:
(69) UNDERCLEARANCES:
(71) WATERWAY ADEQUACY:
(72) APPROACH ALIGNMENT:
(113) SCOUR CRITICAL:
(225) PURPOSE OF IMPROVEMENT:
(226) PRIORITY OF IMPROVEMENT:
(227) MAINTENANCE COST:
(228) REHAB./RECONSTR. COST: ...
(229) CONSTRUCTION COST:
N
N
N
N - Not over waterway.
2 - REHAB/RECONSTRUCTION
C - MODERATE
$2,500
$60,000
$0
ADDITIONAL INFORMATION
(230) STRUCTURE HISTORY:
1956-NORTH/SOUTH LININGS AND PORTALS; 1992-MAJOR RECONSTRUCTION: SUPERSTRUCTURE, ROCKBOLTS, AND SCREENING;
2008-DRAIN CHASE REPAIR.
(231) ADDITIONAL CONSIDERATIONS:
(330) ADDITIONAL CONFIG. INFO.:
APPENDIX STRUCTURE NO. 5140-139P
PHOTOGRAPHS STRUCTURE NO. 5140-139P
PHOTO #1 - NORTH PORTAL
PHOTO #2 - SOUTH PORTAL
PHOTO #3 - GENERAL UNDERSIDE VIEW OF
SOUTH CONCRETE LINING
PHOTO #4 - SCALING AT NORTH END OF
SOUTH CONCRETE LINING, EAST SIDE
PHOTO #5 - CRACKING WITH
EFFLORESCENCE OF CONCRETE LINING ON
EAST SIDE NEAR SOUTH PORTAL
PHOTO #6 - CRACKING WITH
EFFLORESCENCE ON CONCRETE LINING AT
WEST SIDE NEAR SOUTH PORTAL; NOTE WET
PAVEMENT
PHOTO #7 - ACTIVE WATER LEAKAGE AND
CRACKING WITH EFFLORESCENCE ON WEST
CONCRETE LINING NEAR NORTH PORTAL
PHOTO #8 - CRACKING WITH
EFFLORESCENCE ON EAST SIDE OF
CONCRETE LINING AT NORTH PORTAL
PHOTO #9 - GENERAL VIEW OF ROADWAY LOOKING NORTH
PHOTO #10 - CRACKING WITH EFFLORESCENCE ON UNLINED SECTION
NEAR NORTH CONCRETE LINING
PHOTO #11 - CRACKING WITH
EFFLORESCENCE ON NORTH TRANSITION
LINING BETWEEN LINED AND UNLINED
SECTIONS; NOTE ACTIVE WATER LEAKAGE
PHOTO #12 - MISSING REFLECTOR ON EAST
SIDE NEAR SOUTH PORTAL
PHOTO #13 - TYPICAL DETERIORATION OF
MORTAR JOINT ALONG BASE OF NORTH
PORTAL RING STONES; WEST SIDE SHOWN
PHOTO #14 - WATER PONDING AT
NORTHWEST CORNER
PHOTO #15 - LEAKAGE ALONG WEST SIDE OF
SOUTH PORTAL; NOTE VEGETATION GROWTH
PHOTO #16 - TYPICAL SIGNAGE AT
APPROACHES, SIGNS AT SOUTH APPROACH
SHOWN