This document is a Questions and Answers (Q&A) file for the Yellowstone National Park Rescue Creek Bridge project (Project No.: MT ERFO NP YELL 2022-1(3)). The document contains seven technical questions from potential contractors, addressing site access, parking, bid bond validity, steel erection certification requirements, material specifications for rub rail and approach railing, and construction access limitations. Key responses include: the roadway is closed to vehicular traffic but open to pedestrian access, entrance fees will be waived for site reviews, and contractors must follow existing specifications without material substitutions. The project involves bridge construction with specific technical requirements around material usage, site access, and topsoil preservation. Responses are dated between 8/14/2025 and 8/27/2025, indicating an upcoming bidding process for this National Park Service infrastructure project.

View the file

Other files

File Type Posted
Amendment A003.pdf PDF
QA_09-02-2025.pdf PDF
Amendment A002.pdf PDF
QA_08-21-2025.pdf PDF
QA2_08-18-2025.pdf PDF
QA_08-18-2025.pdf PDF
Amendment A001.pdf PDF
QA_08-14-2025.pdf PDF
mt-ep-yell2022-1-3_xs.pdf PDF
RFP 69056725R000010_MT ERFO NP YELL 2022-1(3).pdf PDF
mt-ep-yell2022-1-3_Rescue Creek Bridge Final Foundation Memo.pdf PDF
mt-ep-yell2022-1-3_Rescue creek_control-sheet.xlsx XLSX spreadsheet
mt-ep-yell2022-1-3_ali.pdf PDF
mt-ep-yell2022-1-3_plans_Final.pdf PDF
Physical Data.zip ZIP file
RescueCreek_Waterway_Hydraulics_Memo_95pct.pdf PDF
mt-ep-yell2022-1-3_earthwork.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No.: MT ERFO NP YELL 2022-1(3)

Project : Yellowstone NP Rescue Creek Bridge

# General Technical Question Answer Date

1 X

Do we have access to the project site during bidding and if so who do we contact a NPS to gain access?

The roadway is closed to vehicular traffic due to the flood damage. The area is open to pedestrian access. It is approximately 0.6 miles from the vehicular traffic closure to the project location.

8/14/25

2 X

Do we park outside the park and walk in or do we enter the park and if so would we be able to obtain a contractors pass the enter?

The entrance fee will be waived for contractor’s performing a site review.

Parking would be just outside the closure barricade past the entrance station, not blocking emergency access that might need to pass through closure the gate.

8/14/25

3 X

The Bid Bond Form provided in the solicitation expires on 08/31/2025. Will this bond form still be acceptable to submit with our bid?

This will be addressed under Amendment

A001.

8/18/25

4 X

According to the supplemental specification

555.18 the steel erector is required to be AISC certified in steel erection. This requirement prohibits many bridge/steel erectors (many of which have completed work in the park) from being able to provide quotes for the project.

Please let us know if this supplemental specification was intended to limit the number of qualified contractors or if another steel erection certification could be used instead.

Please bid as shown according to the solicitation documents.

8/18/25

5 X

Rub Rail – specs state DF # 1 1” x 4” using Copper-

8- Quinolinolate…This treatment is no longer being used by most suppliers. Is 5/4” x 6” Ipe wood acceptable in its’ place? (higher quality and longer lasting)

This will be addressed in the next amendment.

8/19/2025

6 X

Approach Railing decorative weathering steel spheres – can this material be iron or some other material other than weathering steel?

Bid as shown. 8/19/2025

Check General or Technical

7 X

Section 201.03 of the contract documents states:

“Do not access any part of the construction access limits without providing a surface that can be driven on and does not disturb the topsoil layer.”

Plan Sheet D.3 further clarifies that topsoil disturbance is only permitted within the

Construction Limits. Topsoil may not be disturbed within the Construction Access Limits.

However, based on both Plan Sheet D.3 and observations during a recent site visit, the existing pathways within the designated

Construction Access Limits are too narrow to accommodate construction equipment or allow for transport of large materials, including the new pedestrian bridge, temporary work bridge, and other necessary materials.

Can we disturb topsoil with the Construction

Access Limits provided full restoration is completed post-construction? If not, how do we access the construction limits?

No, disturbance of topsoil layer is not permitted within the construction access limits as described in 201.03. Contractor to determine means and methods to gain access with equipment and materials without disturbing the topsoil layer.

8/27/2025