QA_07-23-2024.pdf

PDF 107 KB Posted

Attached to
WA NP MORA 123(2) SR-123: Laughingwater Creek Bridge to Panther Creek Bridge
Solicitation number
69056723B000008
Issued by

About this file

This document appears to be a set of questions and answers related to a federal contract opportunity for the "WA NP MORA 123(2) SR-123: Laughingwater Creek Bridge to Panther Creek Bridge" project.

The key details are:

  • This is a highway construction project for the Department of Transportation Federal Highway Administration.
  • Prospective bidders asked questions about the project requirements, including temporary access roads, staging areas, site services, pre-bid meetings, bid extensions, quantity discrepancies, material requirements, traffic control, and erosion control products.
  • The agency responded by referring bidders to the solicitation documents for full details, and indicated some questions would be addressed in future amendments.
  • The solicitation number is 69056723B000008 and the bid opening date was not extended.

The document does not appear to contain a full Performance Work Statement or other key contract details. It is focused on responding to specific technical questions from prospective bidders.

View the file

Other files

File Type Posted
BidTab_WA NP MORA 123(2).pdf PDF
BidSum_WA NP MORA 123(2).pdf PDF
QA_07-31-2024.pdf PDF
Amendment A005.pdf PDF
QA_07-24-2024.pdf PDF
Amendment A004.pdf PDF
QA1_07-19-2024.pdf PDF
Amendment A003.pdf PDF
QA_07-18-2024.pdf PDF
Amendment A002.pdf PDF
Amendment A001.pdf PDF
QA_07-09-2024.pdf PDF
QA_07-05-2024.pdf PDF
QA_08-24-2023.pdf PDF
mora 12302_XYZ asphalt_APPR01.xlsx XLSX spreadsheet
mora 12302_XYZ subex_MAIN01.xlsx XLSX spreadsheet
mora 12302_XYZ base_APPR01.xlsx XLSX spreadsheet
mora12302_control-points.xlsx XLSX spreadsheet
mora12302_plans.pdf PDF
WA NP MORA 123(2) - EPA_CompiledSWPPP_Final Signed.pdf PDF
mora12302_BIR_9450-020P.pdf PDF
mora12302_Earthwork_APPR 01.pdf PDF
mora 12302_XYZ asphalt_MAIN01.xlsx XLSX spreadsheet
Physical Data_WA NP MORA 123(2).zip ZIP file
mora12302_Project Name Change Memo.pdf PDF
mora12302_construction staking notes_APPR01.xlsx XLSX spreadsheet
mora12302_construction staking notes_MAIN01.xlsx XLSX spreadsheet
mora12302_Earthwork_MAIN 01.pdf PDF
mora12302_XS.pdf PDF
IFB 69056723B000008.pdf PDF
mora12302_GR09-22.pdf PDF
mora12302_proposed-alignment_MAIN01.pdf PDF
FLH Bridge oversized or overload vehicle permit request form Oct 2018.pdf PDF
mora12302_clearing limits (culverts).pdf PDF
mora12302_1992_LaughingwaterCreekBridgePlans.pdf PDF
mora12302_proposed-alignment_APPR01.pdf PDF
mora 12302_XYZ base_MAIN01.xlsx XLSX spreadsheet
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WA NP MORA 123(2)

SR‐123: Laughingwater Creek Bridge to Panther Creek Bridge

# General Technical Question Answer Date

1 X

I wanted to inquire if any temporary access roads or equipment staging areas would be necessary in the execution of this project?

The preliminary documents posted on sam.gov have been posted to aid prospective bidders in identifying the location and type of work for this project.

Please monitor the SAM site for the actual date of solicitation release

(https://sam.gov/), and the duration of the advertisement period; and submit your questions during the advertisement period for the project. To receive automatic notification through SAM, you must login and select “Follow” feature and follow the steps as indicated.

8/24/2023

2 X How do we get added ro the Planholder's list.

To add to or view the Interested Vendors

List, you must register as a SAM.gov user, be logged in, and linked to an entity. If you are signed into SAM.gov with your registered entity and you cannot see the

Interested Vendors List, you will need to be assigned the Contract Opportunities

Administrator role for your entity in

SAM.gov. If you need assistance, call the

Federal Service Desk at 866‐606‐8220.

7/5/2024

3 X

Are you going to need any site services on this project? Any rest rooms, hand washing stations or fencing?

Please see specs and Plans 7/9/2024

4 X Will you please confirm if there is a pre‐bid meeting scheduled for the above project?

Page A‐1 indicates “No Government personnel will be available for show‐me tours.”; hence there is no pre‐bid meeting(s) scheduled for this project.

Please bid according to the solicitation documents.

7/18/2024

Check General or Technical

5 X

After a thorough and thoughtful review of the plans and specifications it has become clear this is a fairly complicated project located in a fairly remote area that will require an outstanding performance from all involved to successfully complete the project. Given the current state of the economy, as well as the construction market as a whole, Johansen has determined that we require additional time and effort to investigate every possible lead and angle to give the best possible value in competing for this project. There are a variety of trades involved and we must contact several venders from each in order to give enough time for each of them it do their own investigations, and estimating their portions of the work. Just getting to the project requires more effort than most projects. For this reason, we respectfully request a two week bid extension to further analyze and work on the estimate in order to give the best possible value on this project.

The Government does not intend to extend the bid opening date for this project.

Please submit bids according to the solicitation documents.

7/18/2024

6 X Will Section 204.06(b) Earth Cuts ‐Roadway

Excavation apply? Will 6” Scarify be required?

In accordance with FP‐14 and the SCRs, comply with the requirements of

Subsections 204.06.

7/18/2024

7 X Based off of the Square Yardage take‐off, the

Select borrow appears to be short 6,000 CY.

This has been addressed under

Amendment A002.

7/18/2024

8 X Where is the blotter item being placed?

Comply with the requirements of

Subsection 108.01(c).

7/18/2024

9 X Is compaction for Recycled Aggregate Base per

Subsection 204.11(a) or 301.05?

Recycled aggregate base specifications are under Section 308. Please submit bids according to the solicitation documents.

7/18/2024

10 X Are the complete closures limits from the start of the project to the end of the project?

In accordance with Subsection

156.04(b)(2)(b), closure lengths need to be coordinated with the CO. Please submit bids according to the solicitation documents.

7/18/2024

11 X

Is the existing clearing areas material going to be mixed with aggregate and placed back on to the project?

See Section 313 and submit bids according to the solicitation documents.

7/18/2024

12 X

There appear to be several quantity discrepancies between the proposal and the plans. See Bid Items A0420; A0720;

A0740; A0960; A1320; A1360; A1380; A1400;

A1420; A1440; and A1460. Please clarify.

This has been addressed under

Amendment A002.

7/18/2024

13 X

Will a lab trailer be available for asphalt testing for the project? If not, will there be any changes to result reporting time in Table 401‐8 to allow time for sample transportation?

This will be addressed under Amendment

A003.

7/18/2024

14 X

SCR 308.05 – SCR 308.05(a) seems to indicate compaction of recycled aggregate based on method specified number of roller passes. SCR

308.05(b) notes that the effort of the method spec may be decreased if compaction meets FP‐

14 301.05 which requires the use of nuclear density gauge. Please clarify if density is to be determined according to SCR 308.05(b)

(AASHTO 310). If so, this will require substantial test effort.

Subsection 308.05 of the SCRs requires compaction by Subsection (a) or (b). Please submit bids according to the solicitation documents.

7/18/2024

15 X

Is the prime coat and blotter intended only to protect the subgrade prior to paving for winter shutdowns or is it to be applied to the final roadway surface as a wearing course? Please provide revised roadway sections and or limits of the blotter and prime coat if it is intended to be final wearing surface.

Comply with the requirements of

Subsection 108.01(c).

7/19/2024

16 X

If the prime coat and blotter are intended for winter shutdown, are there any restrictions on providing base lift asphalt in lieu of prime coat and blotter for winter shutdown?

Comply with the requirements of

Subsection 108.01(c).

7/19/2024

17 X

Please confirm that one lane traffic with up to

30 min delays (per 156.07(i)) is required at all times except from September 2, 2025 to

September 30, 2025?

Yes, this is in accordance with Subsection

156.04.

7/19/2024

18 X

Special Provision 156.04(b) references

Subsection 156.07(l). Subsection 156.07(l) does not exist within FHWA Standard Specifications

FP‐14; the Subsection ends at 156.07(j). Please provide the missing information.

See the Special Contract Requirements shown in the solicitation documents.

7/19/2024

19 X

We cannot find specific traffic control restrictions on the duration of the full road closure shown on plan sheet G.2.

See FP‐14 and the SCRs for Section 156. 7/22/2024

20 X

Addendum 2 changed quantities on the plan sheets, but a revised proposal form was not included. Please forward a revised bid proposal.

Amendment A002 only had changes to the plan sheets while the bid schedule did not change. Please submit bids according to the solicitation documents.

7/23/2024

21 X

Is there a specific Type required for the Rolled

Erosion Control Product (Item No. A1120) on this project? Typically there is a specific type called out for use.

No. Please submit bids according to the solicitation documents, which will be amended under Amendment A004.

7/23/2024

File details come from the government source that posted it. Updated .