This document is an amendment (Amendment A002) to a federal solicitation (Solicitation No. 69056723B000008) for the WA NP MORA 123(2) SR-123: Laughingwater Creek Bridge to Panther Creek Bridge project.
The amendment revises various plan sheets by deleting and adding new versions dated between December 2023 and March 2024. Key changes include revisions to plan sheets B.1, B.2, B.3, C.1, C.5, D.2, D.3, G.1, G.2, G.3, and G.4. This amendment is issued by the Department of Transportation Federal Highway Administration and the changes are effective as of July 18, 2024. The original solicitation had a bid due date of June 28, 2024. No other changes to the contract terms or requirements are noted in this amendment.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A002 07/18/2024 N/A See Box 14
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X
69056723B000008
9B. DATED (SEE ITEM 11)
06/28/2024
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A
N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
(__ ) is extended, ( x ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D OTHER (Specify type of modification and authority)
N/A
E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
WA NP MORA 123(2), SR-123 Laughingwater Creek to Panther Creek Bridge
See page 2.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N/A
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Amendment No. A002, dated 07-18-2024 WA NP MORA 123(2)
Solicitation No. 69056723B000008 SR-123 Laughingwater Creek
Page 2 to Panther Creek Bridge
REVISIONS ARE AS FOLLOWS:
PLANS
Plan Sheet B.1 dated 12-01-23 Deletes Sheet from Plans.
Plan Sheet B.1 dated 03-25-24 Adds Sheet to Plans.
Plan Sheet B.2 dated 12-01-23 Deletes Sheet from Plans.
Plan Sheet B.2 dated 03-25-24 Adds Sheet to Plans.
Plan Sheet B.3 dated 12-01-23 Deletes Sheet from Plans.
Plan Sheet B.3 dated 03-25-24 Adds Sheet to Plans.
Plan Sheet C.1 Revises Sheet by Adding Detail.
Plan Sheet C.5 Revises Sheet Title.
Plan Sheet D.2 dated 11-21-23 Deletes Sheet from Plans.
Plan Sheet D.2 dated 03-25-24 Adds Sheet to Plans.
Plan Sheet D.3 dated 11-21-23 Deletes Sheet from Plans.
Plan Sheet D.3 dated 03-25-24 Adds Sheet to Plans.
Plan Sheet G.1 dated 11-21-23 Deletes Sheet from Plans.
Plan Sheet G.1 dated 03-25-24 Adds Sheet to Plans.
Plan Sheet G.2 dated 06-30-23 Deletes Sheet from Plans.
Plan Sheet G.2 dated 03-21-24 Adds Sheet to Plans.
Plan Sheet G.3 Revises location for bottom right sign.
Plan Sheet G.4 dated 09-06-23 Deletes Sheet from Plans.
Plan Sheet G.4 dated 03-22-24 Adds Sheet to Plans.
ENCLOSURES
Plan Sheets:
B.1 dated 12-01-23 / B.1 dated 03-25-24 / B.2 dated 12-01-23 / B.2 dated 03-25-24 /
B.3 dated 12-01-23 / B.3 dated 03-25-24 / C.1 / C.5 / D.2 dated 11-21-23 /
D.2 dated 03-25-24 / D.3 dated 11-21-23 / D.3 dated 03-25-24 / G.1 dated 11-21-23 /
G.1 dated 03-25-24 / G.2 dated 06-30-23 / G.2 dated 03-21-24 / G.3 /
G.2 dated 09-06-23 / G.4 dated 03-22-24
Revised by Amendment A002
ADDED TO PLANS
SHEET B.1 DATED 03-25-24
REMOVED FROM PLANS
SHEET B.1 DATED 12-01-23
Revised by Amendment A002
SHEET B.2 DATED 03-25-24
SHEET B.2 DATED 12-01-23
Revised by Amendment A0022
SHEET B.3 DATED 03-25-24
SHEET B.3 DATED 12-01-23
SUBEXCAVATION CONNECTION
AND UNDERDRAIN DETAIL
ADDED TO PLANS
SHEET D.2 DATED 03-25-24
M a r
SHEET D.2 DATED 11-21-23
Revised by Amendment A002
ADDED TO PLANS
SHEET D.3 DATED 03-25-24
M a r
SHEET D.3 DATED 11-21-23
SHEET G.1 DATED 03-25-24
SHEET G.1 DATED 11-21-23
Revised by Amendment A002
SHEET G.2 DATED 03-21-24
SHEET G.2 DATED 06-30-23
Revised by Amendment A002
SHEET G.4 DATED 03-22-24
SHEET G.4 DATED 09-06-23
Revised by Amendment A002
| Amended Plans.pdf |
| Sheet B.1 dated 03-25-24 |
| Sheet B.1 dated 12-01-23 |
| Sheet B.2 dated 03-25-24 |
| Sheet B.2 dated 12-01-23 |
| Sheet B.3 dated 03-25-24 |
| Sheet B.3 dated 12-01-23 |
File details come from the government source that posted it. Updated .