QA 11_30_22.pdf

PDF 103 KB Posted

Attached to
OR DOT 18(2) OR58: Fix it Corridor Culverts Federal contract opportunity
Solicitation number
69056721B000023
Issued by
Department of Transportation Federal Highway Administration

About this file

This document contains questions and answers regarding the federal contract opportunity for the OR DOT 18(2) OR58: Fix it Corridor Culverts project. Key details include that the project involves culvert work along OR58 and requires guardrail, excavation, temporary barrier, and flagging. Questions addressed clarification around guardrail lengths, whether a pre-bid conference would be held, discharge spreadsheet discrepancies, material testing requirements, permitting responsibilities, and the need for temporary barrier and flagging at specific locations. Amendments A001 and A002 will provide additional information. The contracting agency is the Department of Transportation Federal Highway Administration.

View the file

Other files for this federal contract opportunity

Other files attached to OR DOT 18(2) OR58: Fix it Corridor Culverts, newest first.
File Type Posted
BidSum OR DOT 18(2).pdf PDF
BidTab OR DOT 18(2).pdf PDF
QA 12_07_22.pdf PDF
QA2 12_06_22.pdf PDF
QA 12_06_22.pdf PDF
QA 12_05_22.pdf PDF
Amendment A003.pdf PDF
QA 12_01_22.pdf PDF
H.1 through H.3.pdf PDF
A.1.pdf PDF
F.9.pdf PDF
D.3.pdf PDF
Amendment A002.pdf PDF
H.16.pdf PDF
A.4.pdf PDF
QA 11_29_22.pdf PDF
Amendment_A001.pdf PDF
QA 11_28_22.pdf PDF
QA 11_21_22.pdf PDF
QA 11_16_22.pdf PDF
OR DOT 18(2)_Mobility Considerations Checklist.pdf PDF
ORDOT18(2)_plans.pdf PDF
IFB 69056721B000023.pdf PDF
OR DOT 18(2)_Traffic Management Plan.pdf PDF
OR DOT 18(2)_Hydraulic Report.pdf PDF
Physical Data_1.zip ZIP file
OR DOT 18(2)_Limited ESA Report.pdf PDF
OR DOT 18(2)_Geotechnical_Report.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No.: OR DOT 18(2) Project: OR58: Fix it Corridor Culverts

# General Technical Question Answer Date

1 x

I am bidding on the guardrail portion of this project. Bid Item A1000 is for Buried in Backslope Terminal by the each, but they have a minimum of 125 Lnft per the standard drawing. Sheet # D.13 has a length of 85 Lnft and sheet # D.14 has a length of 77 Lnft. Please advise.

The limits/lengths listed on sheets D.13 and D.14 are those of existing guardrail installations. New guardrail needs to meet minimum lengths per the standard drawings

11/15/22

2 X Is there a Pre Bid Conference for the OR58: Fix‐It Corridor Culverts Project?

At this time, we are not planning on having a pre‐bid conference. If you have any questions about the Invitation for Bid (IFB), plans, or specs, please email wfl.plans‐spec@dot.gov, and we will publicly post responses to your questions on SAM.gov.

11/16/22

3 X

See Plan Sheet Number F.9

More than half of the MP locations referenced in the discharge spreadsheets do not correspond to MP locations provided elsewhere in the plans.

Revised Response this will be addressed under Amendment A001 A002

11/21/2022 revised 11/29/2022

4 X Will the bid date be extended? this will be addressed under Amendment A001 11/21/22

5 X Do materials disposed of with in right of way need to be tested per 201.14?

No, the contractor is required to test excavated materials outside the existing highway pavement generated to a depth of 18‐inch prior to disposal according to Subsection 203.05(a). Per 204.14, “Dispose of unsuitable or excess material within the right‐of‐way within 5 miles of the excavation at locations approved by the CO or according to Subsection 203.05(a).”

11/28/22

6 X Is the CO expecting a test at each excavation location?

If the material will be disposed of according to 203.05(a) then the requirements specified under subsection 204.14 will apply.

11/28/22

7 X

There is no reference if the project will be providing the in water work permits, or if they are required. Please clarify if these will be required at all or some of the culverts, and if Federal Highways is obtaining the permits or if this is the contractor is responsible for obtaining these permits.

Please see sub‐section 107.01, 107.10(4) and Section H (permits) of the SCR’s

11/28/22

8 X Is there any other allowance for 24‐hour flagging other than MP15.51? No, please bid according to the Solicitation Documents. 11/28/22

9 X Sheet H.1, H.2, & H.3 Call out item number 63503‐0400 & 63502‐2100 utilized at 42 of the project sites. Is it the intent of the CO to require temp barrier at all of these locations.

This will be addressed under Amendment A002 11/30/22

10 X Also sheet H.8 shows pinning all of the temporary barrier. Will this be a requirement as well?

pinning is required for all Temporary Concrete Barrier. 11/30/22

Check General or Technical

11 X

Moving 500 LF of barrier, pinning (if required), and setting attenuators does not allow for enough time to perform the work and remove the barrier to open traffic per 156.04. If it the CO’s intent to do this at each location listed in H.1‐H.3?

This will be addressed under Amendment A002 11/30/22