This document is an Invitation for Bids (IFB) for a federal construction contract for road improvement work along the Yale-Kilgore Road in Clark County and Fremont County, Idaho. The project involves full-depth reclamation, asphalt paving, drainage, and other roadway construction activities over approximately 21 miles.
The solicitation includes detailed specifications, plans, a bid schedule, and special contract requirements. Bids are due by May 2, 2024. The government estimates the price range for the work to be between $20 million and $30 million. The contract includes provisions for performance and payment bonds, contractor quality control, and specific technical requirements such as use of full-depth reclamation with foamed asphalt. Subcontracting goals are included for small businesses, service-disabled veteran-owned small businesses, HUBZone small businesses, small disadvantaged businesses, and women-owned small businesses. The Federal Highway Administration is the issuing agency for this solicitation.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION FOR BIDS
Solicitation No. 69056721B000015
ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID FREMONT 6805(1), Yale-Kilgore Road, MP 16.9 to 30.8
Solicitation, Offer & Award, Bid Schedule, Contract Clauses, General Wage Decision, Special Contract Requirements, and Plans
This solicitation cites
Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14
This project uses U.S. Customary units of measure
ISSUING OFFICE:
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
610 EAST FIFTH STREET
VANCOUVER, WA 98661-3801
Phone: (360) 619-7520 e-mail: wfl.contracts@dot.gov
Bid Opening Date:
See Page A-3, Block 13A
QUICK INDEX
Page Item --- Bid Submittal Checklist --- Authority to Sign --- Bid Bond --- Table of Contents A-1 Notice to Bidders A-3 SF 1442, Solicitation, Offer and
Award A-6a Subcontracting Plan A-7 Bid Schedule B-1 Solicitation Provisions C-1 Contract Clauses D-1 General Wage Decision E-1 Special Contract Requirements H-1 Permits I-1 Fire Protection and Suppression
Plan
BID REMINDERS
Electronic bids will not be accepted. Submit printed copy of bid to the address listed on the enclosed SF 1442. Before submitting your bid, please review the following:
• Have you rechecked your bid figures?
• Have you completed the bid schedule?
• Have you completed and signed the SF 1442, Solicitation, Offer & Award?
• Have you acknowledged all amendments?
• Have you completed the Representations &
Certifications (Page B-1)?
• Is your bid guarantee enclosed in proper form and amount (see FAR Clause 52.228-1), including Power of Attorney affidavit?
• Does the lower left corner of the proposal envelope state “Bid Enclosed”?
• Does the lower left corner include the Solicitation Number and the project number/name?
This solicitation is offered as full and open competition.
A-1 Notice to Bidders mailto:wfl.contracts@fhwa.dot.gov
PROJECT No. ID CLARK 6805(1), & ID FREMONT 6805(1), PROJECT NAME Yale-Kilgore Road, MP 9 to 16.9 & Yale-Kilgore
Road, MP 16.9 to 30.8
BEGINNING AT See Plans
ENDING AT See Plans
LENGTH 21.27 Miles
NATIONAL FOREST Caribou-Targhee National Forest
COUNTY Clark and Fremont
STATE Idaho
FIXED COMPLETION DATE See FAR Clause 52.211-10 (FAR Clauses begin on page C-1)
Bid Submittal Checklist
Project: ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID FREMONT 6805(1), Yale-Kilgore Road, MP
16.9 to 30.8
Before submitting your bid, please review the following:
Done?
Is this in the envelope?
Bid Envelope Did I correctly address the envelope? (See page A-3, blocks 7 & 8)
Does the lower left corner of the envelope include the Solicitation Number and the project name/number?
Pages A-3 & A-4 (SF 1442, Solicitation Offer & Award)
Did I include our firm name and address in block 14?
Did I include our firm’s phone number in block 15?
Did I include our firm’s remittance address in block 16?
(Use when different than block 14)
Did I include my unique entity identifier and Cage Code?
Did I include the number & date of all amendments in block 19?
Did the appropriate official sign/date in block 20A, 20B & 20C?
Bid Schedule (see page A-7)
Did I insert “Unit Bid Price” and “Amount Bid” for each bid item?
Did the appropriate official initial corrections?
When applicable, did I include the totals for each schedule in the summary page? (See last page of bid schedules.)
Bid Bond (Standard Form 24)
Bids received without a valid bid bond will be rejected.
Did I complete my bid bond correctly?
Did I include the original?
Did I attach the Power of Attorney to the bid bond?
Authority to Sign
Did I include a completed form for each person signing the SF1442 and Bid Bond?
Representations & Certifications & FAR Clause
Did I include the completed B-pages (beginning on B-1)?
Did I include the completed clause 1252.228-74 Notification of Payment Bond Protection (See page C-122)?
System for Award Management (SAM) SAM.gov
Do we have up-to-date data in SAM?
Veteran Reporting (FAR Clause 52.222-37)
If applicable, did I ensure our firm has completed this annual report?
NOTE: The Contractor is fully responsible to verify that all data is correct each time a bid package is submitted. Failure to properly input and/or update your data may cause the bid to be rejected.
https://sam.gov/content/home
Project: ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID FREMONT 6805(1), Yale-Kilgore Road, MP
16.9 to 30.8
Driving Directions to our Vancouver Washington Office:
Directions to WFLHD https://www.google.com/maps/place/610+E+5th+St,+Vancouver,+WA+98661/data=!4m2!3m1!1s0x5495a8ae3f2d7083:0x5b7adcfa96ade37a?hl=en
Authority to Sign
Project: ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID FREMONT 6805(1), Yale-Kilgore
INSTRUCTIONS: When the offeror/principal is a corporation, include this certification with your offer/bid.
Corporate Certificate
I, ____________________________________________ (name), certify that I am the
________________________________________(title), of the corporation named as the Offeror/Principal herein;
that _________________________________________(name), who signed this offer and/or bid bond on behalf of ___________________________ (company name) is
________________________________________ (title) of this corporation;
that the offer was duly signed for and on behalf of said corporation by authority and scope of its governing body, and within the scope of its corporate powers.
_____________________________________ (signature) Affix Corporate Seal
_____________________________________ (title)
INSTRUCTIONS: When the offeror/principal is a limited liability company, include this certification with your offer/bid.
Limited Liability Certificate
I, ____________________________________________ (name), certify that I am the
________________________________________(title), of the limited liability company named as the Offeror/Principal herein;
that _________________________________________(name), who signed this offer and/or bid bond on behalf of ___________________________ (company name) is
________________________________________ (title) of this company;
that the offer was duly signed for and on behalf of said company by authority and scope of its governing body, and within the scope of its powers.
_____________________________________ (signature) Affix Company Seal (as applicable) ___________________________________ (title)
INSTRUCTIONS: When the offeror/principal is a partnership, include this certification
Authority to Bind Partnership
This certifies that the names and signatures of all partners are listed below, and that the person signing the proposal has the authority to actually bind the partnership pursuant to its partnership agreement. Each of the partners individually has full authority to enter into and execute contractual instruments on behalf of said partnership, except as follows:
(State “None” or describe limitations, if any)
This authority shall remain in full force and effect until such time as the revocation of authority by any cause whatsoever has been furnished in writing to and acknowledge by the Contracting Officer.
(Include names and signatures of all partners)
Road, MP 16.9 to 30.8
INSTRUCTIONS: When the offeror/principal is a joint venture, include this certification
Authority to Bind Joint Venture
This certifies that the person signing the proposal has the authority to actually bind the joint venture pursuant to its joint venture agreement, and that each of the named persons listed below individually has full authority to enter into and execute contractual instruments on behalf of said joint venture, except as follows:
(State “None” or describe limitations, if any)
This authority shall remain in full force and effect until such time as the revocation of authority by any cause whatsoever has been furnished in writing to and acknowledge by the Contracting Officer.
(Include names and signatures of all applicable individuals)
INSTRUCTIONS: When the offeror/principal is a sole proprietorship, the signature on the offer/bid and on the bonds must be as follows:
Sole Proprietorship Requirement
An Offeror/Principal that is a sole proprietorship must submit an offer/bid and a bond signed by the sole proprietor, or by one duly authorized to sign for the sole proprietor.
If the signature is by someone other than the sole proprietor, a copy of the power of attorney authorizing the individual to sign must be provided with the offer/bid.
Bid Bond (See Instructions on Page 3)
Date Bond Executed (Must Not Be Later Than Bid Opening Date)
OMB Control Number: 9000-0045 Expiration Date: 8/31/2025
Principal (Legal Name And Business Address) Type Of Organization ("X" One)
State Of Incorporation
Surety(ies) (Name And Business Address)
Percent Of Bid Price
Penal Sum Of Bond Amount Not To Exceed Million(s) Thousand(s) Hundred(s) Cents
Bid Identification Bid Date Invitation Number
Authorized For Local Reproduction Previous Edition Is Not Usable
STANDARD FORM 24 (REV. 10/2023)
Prescribed by GSA - FAR (48 CFR) 53.228(a)
For (Construction, Supplies Or Services)
Obligation:
We, the Principal and Surety(ies) are firmly bound to the United States of America (hereinafter called the Government) in the above penal sum. For payment of the penal sum, we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally. However, where the Sureties are corporations acting as co-sureties, we, the Sureties, bind ourselves in such sum "jointly and severally" as well as "severally" only for the purpose of allowing a joint action or actions against any or all of us. For all other purposes, each Surety binds itself, jointly and severally with the Principal, for the payment of the sum shown opposite the name of the Surety. If no limit of liability is indicated, the limit of liability is the full amount of the penal sum.
Conditions:
The Principal has submitted the bid identified above.
Therefore:
The above obligation is void if the Principal - (a) upon acceptance by the Government of the bid identified above, within the period specified therein for acceptance (sixty (60) days if no period is specified), executes the further contractual documents and gives the bond(s) required by the terms of the bid as accepted within the time specified (ten (10) days if no period is specified) after receipt of the forms by the Principal; or (b) in the event of failure to execute such further contractual documents and give such bonds, pays the Government for any cost of procuring the work which exceeds the amount of the bid.
Each Surety executing this instrument agrees that its obligation is not impaired by any extension(s) of the time for acceptance of the bid that the Principal may grant to the Government. Notice to the Surety(ies) of extension(s) is waived. However, waiver of the notice applies only to extensions aggregating not more than sixty (60) calendar days in addition to the period originally allowed for acceptance of the bid.
Other (Specify) Individual Partnership Joint Venture Corporation
69056721B000015
Construction
2.
(Seal)2.(Seal)
1.
1.
1.
1. 3.2.
Name(s) (Typed)
Signature(s)
Individual Surety(ies)
Name(s) And Title(s) (Typed)
Corporate Seal
(Seal)
3.
(Seal)
2.
(Seal) Signature(s)
Principal
2.
State Of Incorporation Liability Limit ($)
2.
2.
1.Name(s) And Title(s) (Typed)
Signature(s) 1. 2. Corporate Seal
Corporate Seal
Su re ty C
Name And Address
Signature(s) Name(s) And Title(s) (Typed)
1.
1.
2.
2.
State Of Incorporation Liability Limit ($)
Corporate Seal
Name(s) And Title(s) (Typed)
Su re ty D
Signature(s)
Name And Address
1.
1.
2.
2.
State Of Incorporation Liability Limit ($)
Corporate Seal
Liability Limit ($)State Of Incorporation
1.
1.
Su re ty A
Name And Address
Su re ty B
Name(s) And Title(s) (Typed)
Signature(s)
Name And Address
Corporate Surety(ies)
Witness:
The Principal and Surety(ies) executed this bid bond and affixed their seals on the above date.
STANDARD FORM 24 (REV. 10/2023) PAGE 2
STANDARD FORM 24 (REV. 10/2023) PAGE 3
Corporate Seal
Su re ty F
Name And Address
Signature(s) Name(s) And Title(s) (Typed)
1.
1.
State Of Incorporation
2.
2.
Liability Limit ($)
Corporate Seal
Name(s) And Title(s) (Typed)
Su re ty G
Signature(s)
Name And Address
1.
1.
2.
2.
State Of Incorporation Liability Limit ($)
Corporate Seal
State Of Incorporation Liability Limit ($)
2.
2.
1.
1.
Name And Address
Signature(s) Name(s) And Title(s) (Typed)
Su re ty E
Instructions
1. This form is authorized for use when a bid guaranty is required. Any deviation from this form will require the written approval of the Administrator of General Services.
2. Insert the full legal name and business address of the Principal in the space designated "Principal" on the face of the form. An authorized person shall sign the bond. Any person signing in a representative capacity (e.g., an attorney-in-fact) must furnish evidence of authority if that representative is not a member of the firm, partnership, or joint venture, or an officer of the corporation involved.
3. The bond may express penal sum as a percentage of the bid price. In these cases, the bond may state a maximum dollar limitation (e.g., 20% of the bid price but the amount not to exceed dollars).
4. (a) Corporations executing the bond as sureties must appear on the Department of the Treasury's list of approved sureties and must act within the limitations listed therein. The value put into the Liability
Limit block is the penal sum (i.e., the face value) of the bond, unless a co-surety arrangement is proposed.
(b) When multiple corporate sureties are involved, their names and addresses shall appear in the spaces (Surety A, Surety B, etc.) headed "Corporate Surety(ies)." In the space designated
"Surety(ies)" on the face of the form, insert only the letter identifier corresponding to each of the sureties. Moreover, when co-surety arrangements exist, the parties may allocate their respective limitations of liability under the bond, provided that the sum total of their liability equals 100% of the bond penal sum.
(c) When individual sureties are involved, a completed Affidavit of Individual Surety (Standard Form 28) for each individual surety, shall accompany the bond. The Government may require the surety to furnish additional substantiating information concerning its financial capability.
5. Corporations executing the bond shall affix their corporate seals. Individuals shall execute the bond opposite the word "Corporate Seal"; and shall affix an adhesive seal if executed in Maine, New
Hampshire, or any other jurisdiction requiring adhesive seals.
6. Type the name and title of each person signing this bond in the space provided.
7. In its application to negotiated contracts, the terms "bid" and "bidder" shall include "proposal" and
"offeror."
STANDARD FORM 24 (REV. 10/2023) PAGE 4
Paperwork Reduction Act Statement - This information collection meets the requirements of 44 USC §
3507, as amended by section 2 of the Paperwork Reduction Act of 1995. You do not need to answer these questions unless we display a valid Office of Management and Budget (OMB) control number. The OMB control number for this collection is 9000-0045. We estimate that it will take 1 hour to read the instructions, gather the facts, and answer the questions. Send only comments relating to our time estimate, including suggestions for reducing this burden, or any other aspects of this collection of information to: General
Services Administration, Regulatory Secretariat Division (M1V1CB), 1800 F Street, NW, Washington, DC
20405.
Table of Contents Project: ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID FREMONT 6805(1), Yale-Kilgore Road, MP 16.9 to 30.8
TABLE OF CONTENTS
01/06/23–FP14
DESCRIPTION PAGE
Notice to Bidders ........................................................................................................................ A-1
Solicitation, Offer, and Award (SF 1442) ................................................................................... A-3
Bid Schedule ............................................................................................................................... A-7
Solicitation Provisions ................................................................................................................ B-1
Contract Clauses ......................................................................................................................... C-1
General Wage Decision .............................................................................................................. D-1
SCRs Table of Contents
SPECIAL CONTRACT REQUIREMENTS (SCR)
The following Special Contract Requirements amend and supplement the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-14), U.S. Department of Transportation, Federal Highway Administration.
Division 100 ..................................................................................................................... E-1
Division 150 ................................................................................................................... E-30
Division 200 ..................................................................................................................... F-1
Division 300 ..................................................................................................................... F-7
Division 400 ................................................................................................................... F-28
Division 550 ................................................................................................................... F-50
Division 600 ................................................................................................................... F-66
Division 700 .................................................................................................................... G-1
Permits ........................................................................................................................................ H-1
Fire Protection and Suppression Plan ........................................................................................... I-1
Table of Contents Project: ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID FREMONT 6805(1), Yale-Kilgore Road, MP 16.9 to 30.8
(This page intentionally left blank)
A-1
Notice to Bidders Project: ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID FREMONT 6805(1), Yale-Kilgore Road, MP 16.9 to 30.8
NOTICE TO BIDDERS
01/06/23–FP14
THIS PROJECT IS BEING SOLICITED AND AWARDED UNDER FP-14.
The FP-14 is FLH’s Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects. To view the FP-14 electronically go to:
https://highways.dot.gov/federal-lands/specs.
The FP-14 is a dual unit document with U.S. Customary units being the primary unit shown.
Metric equivalents are shown in parenthesis.
When submitting bids, drawings, calculations, and other construction documents, use only U.S. Customary units of measure, unless otherwise stated.
I. Project Location
General Location. The project work is located along Yale-Kilgore Road in both Clark County and Fremont County, Idaho. Approximate Global Positioning System (GPS) coordinates for the beginning of the project are 44°27’19.37” N, 111°45’25.58”W and coordinates for the end of the project are 44°27’15.35” N, 111°21’48.27”W.
Project Limits. Signs have not been erected to identify the project limits. After October 15, 2023, access along the Clark County segment of Yale-Kilgore road is weather dependent. When the Clark County segment of road is closed, Clark County will allow coordinated site visits. Obtain current road conditions and coordinate site visits with the Clark County Road and Bridge Department at (208) 709-6705 (Attn: Mark Wilson). No Government personnel will be available for show-me tours.
II. Pre‐ bid Information.
GENERAL AND TECHNICAL QUESTIONS REGARDING PROPOSED WORK FOR
THIS PROJECT WILL BE ACCEPTED UNTIL CLOSE-OF-BUSINESS ON
04/23/2024.
Refer to page A-5 for information on how to submit questions related to General Information and Technical Information. Answers to General and Technical Questions will be posted at https://sam.gov/opp/29ba809dcddf41d8863bfd8f3cc8b693/view.
Every attempt to respond to questions will be made. However, response to questions received after the above posted date is not guaranteed.
A-2
Project: ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID FREMONT 6805(1), Yale-Kilgore Road, MP 16.9 to 30.8
Electronic Plan Sheets. This solicitation includes electronic plan sheets available at https://sam.gov/opp/29ba809dcddf41d8863bfd8f3cc8b693/view.
Physical Data. Physical data applicable to this project is listed in FAR Clause 52.236-4 Physical Data.
Representations & Certifications. Submit or update Representations and Certifications online at https://www.sam.gov/SAM/ before bid submittal. For more details go to FAR Provision 52.204- 8 Annual Representations and Certifications (see page B-2.). If you have previously registered on-line and the NAICS code for this solicitation is different than the code listed in your online file, please note the amended changes on the lines provided in FAR 52.204-8.
Requests for Information. Requests for technical information (Plan and Division 100 – 700 Specification questions only) about this project will only be accepted in writing (see Block 9 on page A-5).
Price Evaluation Factor. This solicitation contains a Price Evaluation Factor. In accordance with 13 CFR subsection 126.613, we will apply a factor of 10% to an apparent low bid submitted by a large business when we also receive a bid from a HUBZone small business; the 10% factor does not apply to an apparent low bid submitted by a small business.
HUBZone. If the contract is awarded after applying the price preference for HUBZone small business concerns under FAR clause 52.219-4; at least 50 percent of the cost of the contract performance incurred for personnel must be spent on the prime Contractor’s employees or the employees of other qualified HUBZone small business concerns.
SF 1442, Solicitation, Offer, and Award. Particular attention should be paid to Standard Form l442, Solicitation, Offer and Award, to assure that Blocks 14, 15, 16, 19, 20A, and 20C are completed correctly. Sign Block 20B according to the instructions in Subsection 102.02. You must submit a completed ‘Authority to Sign’ document. You must also complete the representations and certifications contained in the Contract Provisions beginning on page B-1.
Failure to furnish or complete any of the above may result in your bid being considered nonresponsive and being rejected.
Facsimile and email bids, modifications, and withdrawals. Facsimile and email bids are not authorized for this solicitation. Bids may be modified or withdrawn by email, if such notice is received by the time specified for receipt of bids. The Government will not be responsible for any failure attributable to the transmission or receipt of email data. See FAR Provision 52.214-5, Submission of Bids. EMAIL WFL.Contracts@dot.gov. To confirm receipt, call 360.619.7520.
A-2a
Project: ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID FREMONT 6805(1), Yale-Kilgore Road, MP 16.9 to 30.8
Fraud Alert. Current and potential U.S. Department of Transportation (DOT) Contractors have recently been receiving fraudulent letters purporting to be issued by DOT. These fraudulent letters request that the Contractors resubmit their banking information to DOT. If you receive such a letter, please DO NOT complete the requested worksheet that is attached to the letters and DO NOT release any information. To register or update information, Contractors are required to go directly through the System for Award Management (SAM) website and never through a third party. You can access SAM at https://www.sam.gov/SAM/.
III. Post Award Information.
Insurance. Insurance requirements are described in Subsection 107.05.
Contractor Performance Evaluations. This office posts performance evaluations in the Contractor Performance Assessment Reporting System (CPARS); for additional information, see http://www.cpars.gov/index.htm. Upon receiving an email notice of evaluation availability, you will have 14-60 days to review the evaluation online and submit comments. If you are unable to access the system, call 360.619.7520 for assistance or for a copy of the evaluation.
IV. Specifications and Permits.
Specifications. This solicitation and subsequent contract are governed by the Federal Acquisition Regulation (FAR), agency supplemental regulations, and the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14. An electronic version may be found at https://highways.dot.gov/federal-lands/specs. A single paper copy can also be obtained from the Research & Technology Product Distribution Center (RTPDC) by e-mail to:
report.center@dot.gov, or by phone 814-239-1160, or fax 814-239-2156.
Electronic Documentation. Requires all documents (including but not limited to correspondence, notifications, submittals, reports, and pay notes) to be submitted in a pdf format, or an approved fixed-layout electronic format. See Subsection 103.06.
Material Sources. Material sources, water sources, staging areas, stockpile areas and waste areas have not been identified for this project. Secure all permits and clearances for Contractor-located sites and sources. See Subsection 105.02(c).
Price Adjustment Clause. A price adjustment specification for fuel and binder has been included in this contract. See Subsection 109.06A.
Progress Schedules. This project includes new specifications for Prosecution and Progress and for Schedules for Construction Contracts. Carefully review Special Contract Requirements Section 108 - Prosecution and Progress, and Section 155 – Schedules for Construction Contracts.
A-2b
Project: ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID FREMONT 6805(1), Yale-Kilgore Road, MP 16.9 to 30.8
(This page intentionally left blank)
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
Federal Highway Administration
FHWA WESTERN FED LANDS DIVISION
610 E FIFTH STREET
Vancouver WA 98661
690567 8. ADDRESS OFFER TO
Federal Highway Administration
FHWA WESTERN FED LANDS DIVISION
610 E FIFTH STREET
Vancouver WA 98661 x
03/29/2024
69056721B000015
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
This solicitation is designed ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID
FREMONT 6805(1), Yale-Kilgore Road, MP 16.9 to 30.8
IN STRICT ACCORDANCE WITH:
Federal Acquisition Regulation (FAR) and Transportation Acquisition Regulations (TAR)
General Wage Decision
Special Contract Requirements
Standard Specifications for Construction of Roads and Bridges on Federal Highway
Projects, FP-14
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 calendar days and complete it within ________________ ________________ calendar days after receiving
Page A-5
05/02/2024
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
See Page A-5 360-619-7520
A-3
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
See Bid Schedule
See Page A-5 690567
Federal Highway Administration
FHWA WESTERN FED LANDS DIVISION
610 E FIFTH STREET
Vancouver WA 98661
A-4
A-5
Continuation SF 1442 Project: ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID FREMONT 6805(1), Yale- Kilgore Road, MP 16.9 to 30.8
Block 9 FOR GENERAL INFORMATION, call 360.619.7520 from the hours of 8:00 a.m. to
4:00 p.m. local time or e-mail us at wfl.contracts@dot.gov.
FOR TECHNICAL INFORMATION (plan and specification questions only), requests for technical information about this project will only be accepted in writing.
Submit questions via e-mail at wfl.plans-spec@dot.gov.
QUESTIONS/ANSWERS POSTED ONLINE. You can view questions and answers on the Contract Opportunities Websitehttps://sam.gov/ .
• Insert the solicitation number in the search box
• Scroll to the project.
• Make sure you are on the most recent view and look in the right section of the page for the most recent Q&A document.
FOR DAVIS-BACON WAGE RATE INFORMATION go to the U.S. Department of
Labor, Branch of Construction Wage Determinations Website:
https://www.dol.gov/agencies/whd/government-contracts/state-assignments.
FOR BID RESULTS, the bid opening summary will be posted on the Contract
Opportunities Website SAM.gov shortly after bid opening. Bid tabulations will be available on SAM.gov approximately 3 working days after the bid opening.
FOR PHYSICAL DATA, See FAR Contract Clause 52.236-4, Physical Data, (clauses begin on page C-1) for a listing of available data. Physical Data will be posted with the solicitation on the SAM website.
FOR BID RESULTS, the bid opening summary will be posted on the Contract
Opportunities Website SAM.gov shortly after bid opening. Bid tabulations will be available on SAM.gov approximately 3 working days after the bid opening.
Block 11 COMPLETION DATE: Work shall be completed on or before the date specified in
FAR Clause 52.211-10, Commencement, Prosecution, and Completion of Work, subject to such extensions as may be authorized by the terms of the contract and the specifications made a part thereof. Contract Clauses begin on pages C-1.
Block 12A PERFORMANCE & PAYMENT BONDS: See FAR Clause, 52.228-15, Performance and Payment Bonds - Construction (clauses begin on page C-1) and Subsection 102.06 of the Standard Specifications for Construction of Roads and Bridges on Federal Highway
Projects, FP-14, U.S. Customary Units.
Block 13B BID BOND AMOUNT: See FAR Clause 52.228-1, Bid Guarantee (clauses begin on page C-1).
ADDITIONAL INFORMATION: See Subsections 102.03 and 102.04 of Standard
Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-
14, U.S. Customary Units.
mailto:wfl.contracts@dot.gov mailto:wfl.plans-spec@dot.gov https://sam.gov/ https://www.dol.gov/agencies/whd/government-contracts/state-assignments
A-6
Continuation SF 1442 Project: ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID FREMONT 6805(1), Yale- Kilgore Road, MP 16.9 to 30.8
Block 24 SUBMITTING INVOICES: See Subsection 109.08 of the Standard Specifications for
Construction of Roads and Bridges on Federal Highway Projects FP-14, U.S. Customary
Units.
ESTIMATED PRICE RANGE. The price range of the project work is between $20,000,000 and
$30,000,000,000.
SUBCONTRACTING PLAN. This invitation for bids requires a low bidder who is a LARGE business to submit an acceptable subcontracting plan prior to contract award. Do not submit this form with your bid. A large business is one whose average gross annual receipts over the past 3 years equal $45 million or more. For your information the subcontracting plan form is included beginning on page A-6a. This requirement does not apply to SMALL businesses.
A-6a
APM 025E – Revised 1/17/2024 ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID FREMONT 6805(1), Yale-Kilgore Road, MP 16.9 to 30.8
ATTACHMENT 1 – FHWA SUBCONTRACTING PLAN
1. INSTRUCTIONS:
• Where subcontracting opportunities will not exist for the solicitation, the bidder/offeror shall submit a response outlining the rationale for making this determination with its proposal/bid. The statement shall be signed by an official authorized to make decisions on behalf of the firm.
• The following information shall be provided in the bidder/offeror subcontracting plan submission and shall be expressed in terms of goal percentages of the total planned subcontracting dollars.
• Text lines may be added to this template as needed.
*insert and complete additional tables if the contract includes option year(s).
1 Percentage = (subcontracted amount in the category/total planned subcontracted amount) 2 Planned subcontracts to “other than small business” concerns + subcontracts to Small Business concerns = 100% 3 SDVOSB is a subcategory of VOSB. Any dollar amount applied to SDVOSB also applies to VOSB.
4 In this document, the term WOSB includes Economically Disadvantaged WOSB (EDWOSB) concerns.
SUBCONTRACTING GOALS – BASE YEAR
Total prime contract amount – Base Year: $ [insert amount]
Total planned subcontracted amount (regardless of firm/entity size status) – Base Year:
$ [insert amount]
Total planned subcontracts to “other than small business” concerns (i.e., large, non-profit, university, etc.)
$[insert amount] [insert #]%1
Total planned subcontracts to Small Business concerns: $[insert amount] [insert #]%2
• Total planned subcontracts to Veteran Owned Small Business concerns (VOSB)3:
$[insert amount] [insert #]% o Total planned subcontracts to Service-Disabled Veteran Owned Small Business (SDVOSB) concerns:
$[insert amount] [insert #]%
• Total planned subcontracts to Historically Underutilized Business Zones (HUBZones): $[insert amount] [insert #]%
• Total planned subcontracts to Small Disadvantaged Business (SDB) concerns (includes 8(a), Alaska Native Corporations (ANC), and Indian Tribes):
$[insert amount] [insert #]%
• Total planned subcontract awards to Women-Owned Small Business concerns (WOSB)4 concerns:
$[insert amount] [insert #]%
A-6b
ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID FREMONT 6805(1), Yale-Kilgore Road, MP 16.9 to 30.8
1.1 Rationale if establishing a goal lower than 5% for VOSB:
1.2 Rationale if establishing a goal lower than 5% for SDVOSB:
1.3 Rationale if establishing a goal lower than 3% for HUBZone:
1.4 Rationale if establishing a goal lower than 5% for SDB:
1.5 Rationale if establishing a goal lower than 5% for WOSB:
1.6 Rationale if establishing a goal lower than the current DOT subcontracting goal:
2. The following principal types of supplies and/or services are planned to be subcontracted under this contract. [Add additional rows if more space is needed.]
5 List all applicable size standards for each proposed subcontractor.
Type of
Supply/Service to be Subcontracted
Company/Firm
Name
Subcontracted
Amount
Subcontractor Size
Standard (Other Than
SB, SB, VOSB, SDVOSB,
HUBZone, SDB, WOSB)5 https://www.sba.gov/document/support-agency-contracting-goals
A-6c
ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID FREMONT 6805(1), Yale-Kilgore Road, MP 16.9 to 30.8
3. The following methods were used to develop the subcontract percentage goals:
4. The following methods were used to identify potential subcontract sources for solicitation purposes. (i.e. source lists used and organizations contacted to identify potential SB concerns, such as the System for Award Management (www.SAM.gov), Dynamic Small Business Search (www.DSBS.sba.gov), trade associations, industry conferences/fairs, etc.)
5. [Select appropriate option.] Indirect costs [were/were not] included in establishing the subcontracting goals specified in the table above.
6. If indirect costs were included, the following method was used to determine the proportionate share of indirect costs to be incurred with SB, VOSB, SDVOSB, HUBZone, SDB and WOSB subcontractors:
7. The following individual will administer the subcontracting program:
Name:
Title:
Address:
Telephone:
E-mail:
This individual's specific duties, as they relate to the subcontracting program, are as follows:
8. The following efforts will be taken to ensure that SB, SDB, VOSB, SDVOSB, HUBZone, and
WOSB subcontractors will have an equitable opportunity to compete for subcontracts:
http://www.sam.gov/ http://www.dsbs.sba.gov/
A-6d
ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID FREMONT 6805(1), Yale-Kilgore Road, MP 16.9 to 30.8
[initial] It is agreed that FAR Clause 52.219-8, Utilization of Small Business Concerns, will be included in all subcontracts, which offer further subcontracting opportunities. It is further agreed that all subcontractors (except small business concerns) at all tiers below the prime contractor who receive subcontracts in excess of $700,000 ($1.5M for construction of any public facility with further subcontracting possibilities) will be required to adopt and comply with a subcontracting plan in accordance with FAR Clause 52.219-9.
9. The following types of records will be maintained concerning procedures that have been adopted to comply with the requirements and goals in the plan (i.e., establishment of source lists, guides and other data that identify SB, VOSB, SDVOSB, HUBZone, SDB and WOSB concerns; a description of the offeror’s efforts to locate SB, VOSB, SDVOSB, HUBZone, SDB and WOSB concerns and to award subcontracts to them, etc.) and shall be maintained through completion of the contract:
10. In accordance with FAR Subpart 19.704(a)(10) through (15), the Contractor further agrees to:
[Initial each line]
Cooperate in any studies or surveys as may be required;
Submit periodic reports as may be required so that the Government can determine the extent of compliance by the Contractor with the subcontracting plan;
After November 30, 2017, include subcontracting data for each order when reporting subcontracting achievements for indefinite-delivery, indefinite-quantity contracts intended for use by multiple agencies;
Submit the Individual Subcontract Report (ISR), and the Summary Subcontract Report (SSR) using the Electronic Subcontracting Reporting System (eSRS) at http://www.esrs.gov/ within the timeframes identified at FAR Subpart 19.704(a)(10)(iv);
Ensure that other than small business subcontractors with subcontracting plans agree to submit eSRS documents online as required;
Provide its prime contract number and its unique entity identifier, and the e-mail address of the offeror’s official responsible for acknowledging receipt of or rejecting the ISRs to all first-tier subcontractors with subcontracting plans so they can enter this information into the eSRS when submitting their ISRs;
http://www.esrs.gov/
A-6e
ID CLARK 6805(1), Yale-Kilgore Road, MP 9 to 16.9 & ID FREMONT 6805(1), Yale-Kilgore Road, MP 16.9 to 30.8
Require that each subcontractor with a subcontracting plan provide the prime contract number, its own unique entity identifier, and the e-mail address of the subcontractor’s official responsible for acknowledging receipt of or rejecting the ISRs, to its subcontractors with subcontracting plans;
Make a good faith effort to acquire articles, equipment, supplies, services, or materials, or obtain the performance of construction work from the small business concerns that the offeror used in preparing the bid or proposal, in the same or greater scope, amount, and quality used in preparing and submitting the bid or proposal;
Provide the contracting officer with a written explanation if the contractor fails to acquire articles, equipment, supplies, services or materials or obtain the performance of construction work as described in FAR 19.704(a)(12) of this section. This written explanation will be submitted to the contracting officer within 30 days of contract completion;
Will not prohibit a subcontractor from discussing with the contracting officer any material matter pertaining to payment to or utilization of a subcontractor; and
Pay its small business subcontractors on time and in accordance with the terms and conditions of the subcontract, and notify the contracting officer if the offeror pays a reduced or an untimely payment to a small business subcontractor (see FAR 52.242-5).
Submitted by:
POC Name:
Title:
Email Address:
Company Name:
DUNS/CAGE:
Mailing Address:
Signature http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/far/52_237.htm#P308_50712
A - 7
BID SCHEDULE
Bidder/Offeror please note: Before preparing the bid, carefully read the Solicitation Provisions.
Insert a unit bid price, in figures, for each pay item for which a quantity appears in the bid schedule. Multiply the unit price by the quantity for each pay item and show the amount bid. Should any mathematical check made by the Government show a mistake in the amount bid, the corrected unit price extension shall govern.
When the word "LPSM" (Lump Sum) appears as a unit bid price, insert an amount for each lump sum pay item.
When a sum based on a fixed rate appears for any pay item in the amount bid column, include the Government inserted amount bid for the item in the total bid amount.
Total all of the amounts bid for each pay item and show the total bid amount.
Do not include an amount to protect against contingent cost increases to prices subject to the escalation coverage.
Bid Schedule
Project No:ID CLARK 6805(1) & ID FREMONT 6805(1)
Project Name:Yale-Kilgore Road, MP 9 to 16.9 & Yale-Kilgore Road, MP 16.9 to 30.8
A - 8
Contract Quantity Pay Items
20303-0200 REMOVAL OF BRIDGE DECK
55210-0000 PRECAST STRUCTURAL CONCRETE (MILL CREEK STRUCUTRAL PLATE CULVERT FOOTING)
55210-0000 PRECAST STRUCTURAL CONCRETE (BENT CAP)
55210-0400 PRECAST STRUCTURAL CONCRETE, CLASS A(AE), ABUTMENT
55703-2000 STRUCTURAL TIMBER AND LUMBER, TREATED, DECKING
60304-0000 STRUCTURAL PLATE ARCH , (10' SPAN X 4'-5" RISE)
Item No. Pay Item No. Description Quantity Unit Unit Price Amount
A0020 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
A0040 15201-0000 CONSTRUCTION SURVEY AND STAKING
ALL LPSM $___LPSM_____ $____________
A0060 15301-0010 CONTRACTOR QUALITY CONTROL AND ASSURANCE
ALL LPSM $___LPSM_____ $____________
A0080 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
A0100 15501-0000 CONSTRUCTION SCHEDULE
ALL LPSM $___LPSM_____ $____________
A0120 15702-1000 SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL
ALL LPSM $___LPSM_____ $____________
A0140 15702-2000 SOIL EROSION CONTROL, TURBIDITY MONITORING
ALL LPSM $___LPSM_____ $____________
A0160 15705-0100 SOIL EROSION CONTROL, SILT FENCE
21,520 LNFT $____________ $____________
A0180 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
1,840 LNFT $____________ $____________
A0200 20101-0000 CLEARING AND GRUBBING
22.02 ACRE $____________ $____________
A0220 20201-0000 SELECTIVE CLEARING
1.73 ACRE $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
A - 9
A0240 20301-0600 REMOVAL OF CATTLE GUARD
2 EACH $____________ $____________
A0260 20301-1900 REMOVAL OF PIPE CULVERT
1 EACH $____________ $____________
A0280 20301-2400 REMOVAL OF SIGN
52 EACH $____________ $____________
A0300 20302-0150 REMOVAL OF BRIDGE RAILING (W-BEAM)
60 LNFT $____________ $____________
A0320 20302-1200 REMOVAL OF GUARDRAIL
538 LNFT $____________ $____________
A0340 20303-0200 REMOVAL OF BRIDGE DECK
72 SQYD $____________ $____________
A0360 20401-0000 ROADWAY EXCAVATION , (TRAIL)
1,070 CUYD $____________ $____________
A0380 20401-0000 ROADWAY EXCAVATION , (MAINLINE)
29,900 CUYD $____________ $____________
A0400 20403-0000 UNCLASSIFIED BORROW
1,450 CUYD $____________ $____________
A0420 25101-2200 PLACED RIPRAP, METHOD B, CLASS 2
72 CUYD $____________ $____________
A0440 30101-2000 AGGREGATE BASE GRADING D
98,170 TON $____________ $____________
A0460 30110-0000 AGGREGATE SURFACE COURSE
3,030 TON $____________ $____________
A0480 30202-1000 ROADWAY AGGREGATE, METHOD 1
300 TON $____________ $____________
A0500 30603-0600 FULL DEPTH RECLAMATION WITH FOAMED ASPHALT, 6-INCH DEPTH
12.00 MILE $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
A - 10
A0520 30611-0000 CEMENT
592.0 TON $____________ $____________
A0540 30613-0000 ASPHALT BINDER , (GRADE PG 58-28)
1,775.0 TON $____________ $____________
A0580 40101-5600 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH OR 3/4-INCH
NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION ESAL , (TYPE III
PAVEMENT ROUGHNESS)
67,000 TON $____________ $____________
A0620 41201-0000 TACK COAT
223.0 TON $____________ $____________
A0640 55210-0000 PRECAST STRUCTURAL CONCRETE (MILL CREEK STRUCUTRAL PLATE
CULVERT FOOTING)
40 CUYD $____________ $____________
A0660 55210-0000 PRECAST STRUCTURAL CONCRETE (BENT CAP)
9 CUYD $____________ $____________
A0680 55210-0400 PRECAST STRUCTURAL CONCRETE, CLASS A(AE), ABUTMENT
15.7 CUYD $____________ $____________
A0700 55504-0000 PRE-FABRICATED STEEL BRIDGE
ALL LPSM $___LPSM_____ $____________
A0720 55601-0900 BRIDGE RAILING, STEEL
118.5 LNFT $____________ $____________
A0740 55703-2000 STRUCTURAL TIMBER AND LUMBER, TREATED, DECKING
76 SQYD $____________ $____________
A0760 56701-0000 MICROPILE (TRAIL BRIDGE)
420 LNFT $____________ $____________
A0780 56706-0000 MICROPILE PROOF LOAD TEST (TRAIL BRIDGE)
4 EACH $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
A - 11
A0800 60201-0400 12-INCH PIPE CULVERT (TRAIL)
24 LNFT $____________ $____________
A0820 60201-0600 18-INCH PIPE CULVERT
598 LNFT $____________ $____________
A0840 60201-0800 24-INCH PIPE CULVERT
2,610 LNFT $____________ $____________
A0860 60216-0000 LARGE PRECAST CONCRETE ARCH CULVERT , (18 FEET SPAN BY 4 FEET
RISE WITH WINGWALLS AND FOOTINGS)
45 LNFT $____________ $____________
A0880 60304-0000 STRUCTURAL PLATE ARCH , (10' SPAN X 4'-5" RISE)
76 LNFT $____________ $____________
A0900 60704-0000 CLEANING CULVERT IN PLACE
11 EACH $____________ $____________
A0920 60705-0000 REPAIRING DRAINAGE STRUCTURE
6 EACH $____________ $____________
A0940 61701-4550 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A WOOD POSTS
575 LNFT $____________ $____________
A0960 61702-1600 TERMINAL SECTION, TYPE MGS FLARED
12 EACH $____________ $____________
A0980 61707-4000 STRUCTURE TRANSITION RAILING, MGS SYSTEM
150 LNFT $____________ $____________
A1000 61903-1000 CATTLE GUARD, 30 FEET
2 EACH $____________ $____________
A1020 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
40 HOUR $____________ $____________
A1040 62201-0450 BACKHOE LOADER, 4 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET,
18-INCH WIDTH
40 HOUR $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
A - 12
A1060 62201-0900 WHEEL LOADER, 2 CUBIC YARD MINIMUM RATED CAPACITY
40 HOUR $____________ $____________
A1080 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE
40 HOUR $____________ $____________
A1100 62201-3400 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY WITH
THUMB ATTACHMENT
40 HOUR $____________ $____________
A1120 62301-0000 GENERAL LABOR
40 HOUR $____________ $____________
A1140 62501-0000 TURF ESTABLISHMENT
2.0 ACRE $____________ $____________
A1160 63302-0000 SIGN SYSTEM
564.1 SQFT $____________ $____________
A1180 63309-0300 DELINEATOR, TYPE 3
196 EACH $____________ $____________
A1200 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID , (YELLOW)
256,230 LNFT $____________ $____________
A1220 63401-0400 PAVEMENT MARKINGS, TYPE B, BROKEN , (YELLOW)
132,800 LNFT $____________ $____________
A1240 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
100 EACH $____________ $____________
A1260 63503-0700 TEMPORARY…