This document is a tabulation of bids report for solicitation number 69056721B000009 issued by the Department of Transportation Federal Highway Administration. The solicitation is for a project to construct a wildlife overpass on SH-21 at Cervidae Peak, milepost 19.3, and includes items such as mobilization, surveying, erosion control, roadway excavation, retaining walls, asphalt paving, guardrails, fencing, signage and temporary traffic control. Seven contractors submitted bids by the March 22, 2022 deadline. Bid amounts ranged from $7,272,729.09 by STG Pacific, LLC as the apparent low bid to $9,962,862.00 by National Native American Construction, Inc. as the high bid. The engineer's estimate was $4,454,000.00. Award is pending and no award date or contractor is indicated. The report provides unit pricing for over 100 line items to allow for evaluation of bids received.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 03/22/22
1 out of 15Source Selection Information - See FAR 2.101 & 3.104
Project No: ID DOT 21(1)
Project Name: SH-21 Wildlife Overpass at Cervidae Peak, MP 19.3
Schedule: A
Schedule Type: Base
Solcitation No: 69056721B000009
Division: Western Federal Lands
State: ID County: Boise
Federal Land: USFS, Idaho Fish and Game, USACE Opened at: FHWA Vancouver, WA Office
Opened by: Andres Arredondo
Date: 03/22/22
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
STG Pacific, LLC $7,272,729.09 3700 Centerpoint Drive, Suite 8155 Anchorage, AK 99503
Winspear Construction, LLC $7,660,000.00 1735 S. Federal Way Boise, ID 83705
EWS-RSCI, LLC $8,276,530.00
2506 Little Powder River Rd Gillette, WY 82716
Seabee Construction, Inc. $8,383,766.92 14777 SE Crosscreek Ct.
Damascus, OR 97089
National Native American Construction, Inc. $9,962,862.00 3901 N. Schreiber Way Coeur d'ALene , ID 83815
Engineer's Estimate $4,454,000.00
2 out of 15Source Selection Information - See FAR 2.101 & 3.104
Project No: ID DOT 21(1)
Project Name: SH-21 Wildlife Overpass at Cervidae Peak, MP 19.3
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0020 15101-0000 MOBILIZATION
STG Pacific, LLC Lump Sum $203,045.00 Winspear Construction, LLC Lump Sum $365,000.00 EWS-RSCI, LLC Lump Sum $827,000.00 Seabee Construction, Inc. Lump Sum $1,024,442.75 National Native American Construction, Inc. Lump Sum $1,250,424.00 Engineer's Estimate ALL LPSM Lump Sum $576,535.00
A0040 15201-0000 CONSTRUCTION SURVEY AND STAKING
STG Pacific, LLC Lump Sum $58,132.00 Winspear Construction, LLC Lump Sum $82,500.00 EWS-RSCI, LLC Lump Sum $90,000.00 Seabee Construction, Inc. Lump Sum $42,768.65 National Native American Construction, Inc. Lump Sum $128,196.00 Engineer's Estimate ALL LPSM Lump Sum $39,000.00
A0060 15301-0010 CONTRACTOR QUALITY CONTROL AND ASSURANCE
STG Pacific, LLC Lump Sum $132,942.00 Winspear Construction, LLC Lump Sum $114,000.00 EWS-RSCI, LLC Lump Sum $175,000.00 Seabee Construction, Inc. Lump Sum $171,074.59 National Native American Construction, Inc. Lump Sum $116,553.00 Engineer's Estimate ALL LPSM Lump Sum $77,000.00
A0080 15401-0000 CONTRACTOR TESTING
STG Pacific, LLC Lump Sum $53,159.00 Winspear Construction, LLC Lump Sum $62,000.00 EWS-RSCI, LLC Lump Sum $100,000.00 Seabee Construction, Inc. Lump Sum $90,883.37 National Native American Construction, Inc. Lump Sum $96,147.00 Engineer's Estimate ALL LPSM Lump Sum $77,000.00
A0100 15501-0000 CONSTRUCTION SCHEDULE
STG Pacific, LLC Lump Sum $12,259.00 Winspear Construction, LLC Lump Sum $26,800.00 EWS-RSCI, LLC Lump Sum $30,000.00 Seabee Construction, Inc. Lump Sum $10,692.16 National Native American Construction, Inc. Lump Sum $32,049.00 Engineer's Estimate ALL LPSM Lump Sum $20,000.00
3 out of 15Source Selection Information - See FAR 2.101 & 3.104
Project No: ID DOT 21(1)
Project Name: SH-21 Wildlife Overpass at Cervidae Peak, MP 19.3
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0120 15704-1100 SOIL EROSION CONTROL, BRUSH BLANKET
STG Pacific, LLC $7.20 $4,320.00 Winspear Construction, LLC $14.50 $8,700.00
EWS-RSCI, LLC $7.50 $4,500.00
Seabee Construction, Inc. $2.94 $1,764.00 National Native American Construction, Inc. $3.00 $1,800.00 Engineer's Estimate 600 SQYD $5.00 $3,000.00
A0140 15705-0100 SOIL EROSION CONTROL, SILT FENCE
STG Pacific, LLC $1.43 $1,430.00 Winspear Construction, LLC $4.00 $4,000.00
EWS-RSCI, LLC $3.25 $3,250.00
Seabee Construction, Inc. $2.46 $2,460.00 National Native American Construction, Inc. $2.00 $2,000.00 Engineer's Estimate 1,000 LNFT $5.50 $5,500.00
A0160 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
STG Pacific, LLC $4.57 $45,700.00 Winspear Construction, LLC $3.00 $30,000.00
EWS-RSCI, LLC $3.25 $32,500.00
Seabee Construction, Inc. $2.94 $29,400.00 National Native American Construction, Inc. $3.00 $30,000.00 Engineer's Estimate 10,000 LNFT $4.50 $45,000.00
A0180 15706-0200 SOIL EROSION CONTROL, CHECK DAM
STG Pacific, LLC $200.38 $1,603.04 Winspear Construction, LLC $370.00 $2,960.00
EWS-RSCI, LLC $800.00 $6,400.00
Seabee Construction, Inc. $181.77 $1,454.16 National Native American Construction, Inc. $170.00 $1,360.00 Engineer's Estimate 8 EACH $150.00 $1,200.00
A0200 15706-0700 SOIL EROSION CONTROL, SILT CONTROL GATE
STG Pacific, LLC $157.20 $2,043.60 Winspear Construction, LLC $62.00 $806.00
EWS-RSCI, LLC $75.00 $975.00
Seabee Construction, Inc. $58.81 $764.53 National Native American Construction, Inc. $55.00 $715.00 Engineer's Estimate 13 EACH $100.00 $1,300.00
4 out of 15Source Selection Information - See FAR 2.101 & 3.104
Project No: ID DOT 21(1)
Project Name: SH-21 Wildlife Overpass at Cervidae Peak, MP 19.3
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0220 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT
STG Pacific, LLC $648.97 $3,244.85 Winspear Construction, LLC $3,600.00 $18,000.00
EWS-RSCI, LLC $3,100.00 $15,500.00
Seabee Construction, Inc. $2,566.12 $12,830.60 National Native American Construction, Inc. $2,400.00 $12,000.00 Engineer's Estimate 5 EACH $3,000.00 $15,000.00
A0240 15802-0000 WATERING FOR DUST CONTROL
STG Pacific, LLC Lump Sum $14,097.77 Winspear Construction, LLC Lump Sum $36,400.00 EWS-RSCI, LLC Lump Sum $50,000.00 Seabee Construction, Inc. Lump Sum $21,384.32 National Native American Construction, Inc. Lump Sum $25,639.00 Engineer's Estimate ALL LPSM Lump Sum $20,000.00
A0260 20101-0000 CLEARING AND GRUBBING
STG Pacific, LLC $16,549.58 $66,198.32 Winspear Construction, LLC $8,000.00 $32,000.00
EWS-RSCI, LLC $1,500.00 $6,000.00
Seabee Construction, Inc. $12,830.59 $51,322.36 National Native American Construction, Inc. $15,384.00 $61,536.00 Engineer's Estimate 4.00 ACRE $10,000.00 $40,000.00
A0280 20302-0700 REMOVAL OF FENCE (WILDLIFE)
STG Pacific, LLC $36.93 $33,606.30 Winspear Construction, LLC $24.50 $22,295.00
EWS-RSCI, LLC $6.50 $5,915.00
Seabee Construction, Inc. $6.95 $6,324.50 National Native American Construction, Inc. $7.00 $6,370.00 Engineer's Estimate 910 LNFT $6.00 $5,460.00
A0300 20302-1200 REMOVAL OF GUARDRAIL
STG Pacific, LLC $3.68 $2,723.20 Winspear Construction, LLC $3.75 $2,775.00
EWS-RSCI, LLC $2.00 $1,480.00
Seabee Construction, Inc. $3.53 $2,612.20 National Native American Construction, Inc. $4.00 $2,960.00 Engineer's Estimate 740 LNFT $6.50 $4,810.00
5 out of 15Source Selection Information - See FAR 2.101 & 3.104
Project No: ID DOT 21(1)
Project Name: SH-21 Wildlife Overpass at Cervidae Peak, MP 19.3
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0320 20302-1300 REMOVAL OF GUARDRAIL, CONCRETE BARRIER
STG Pacific, LLC $30.65 $613.00 Winspear Construction, LLC $41.00 $820.00
EWS-RSCI, LLC $2.00 $40.00
Seabee Construction, Inc. $28.87 $577.40 National Native American Construction, Inc. $35.00 $700.00 Engineer's Estimate 20 LNFT $70.00 $1,400.00
A0340 20302-2600 REMOVAL OF PAVEMENT MARKINGS
STG Pacific, LLC $7.91 $1,582.00 Winspear Construction, LLC $5.00 $1,000.00
EWS-RSCI, LLC $9.00 $1,800.00
Seabee Construction, Inc. $4.70 $940.00 National Native American Construction, Inc. $4.00 $800.00 Engineer's Estimate 200 LNFT $6.00 $1,200.00
A0360 20303-1900 REMOVAL OF PAVEMENT, ASPHALT, 3-INCH DEPTH
STG Pacific, LLC $42.10 $50,520.00 Winspear Construction, LLC $8.00 $9,600.00
EWS-RSCI, LLC $9.25 $11,100.00
Seabee Construction, Inc. $2.67 $3,204.00 National Native American Construction, Inc. $3.00 $3,600.00 Engineer's Estimate 1,200 SQYD $20.00 $24,000.00
A0380 20401-0000 ROADWAY EXCAVATION
STG Pacific, LLC $112.95 $45,180.00 Winspear Construction, LLC $33.00 $13,200.00
EWS-RSCI, LLC $18.50 $7,400.00
Seabee Construction, Inc. $32.08 $12,832.00 National Native American Construction, Inc. $38.00 $15,200.00 Engineer's Estimate 400 CUYD $25.00 $10,000.00
A0400 20403-0000 UNCLASSIFIED BORROW
STG Pacific, LLC $39.94 $611,082.00 Winspear Construction, LLC $1.00 $15,300.00
EWS-RSCI, LLC $40.00 $612,000.00
Seabee Construction, Inc. $34.21 $523,413.00 National Native American Construction, Inc. $41.00 $627,300.00 Engineer's Estimate 15,300 CUYD $26.00 $397,800.00
6 out of 15Source Selection Information - See FAR 2.101 & 3.104
Project No: ID DOT 21(1)
Project Name: SH-21 Wildlife Overpass at Cervidae Peak, MP 19.3
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0420 20702-0700 GEOTEXTILE FILTER, CLASS 2, TYPE B (NONWOVEN)
STG Pacific, LLC $7.14 $2,856.00 Winspear Construction, LLC $5.00 $2,000.00
EWS-RSCI, LLC $4.75 $1,900.00
Seabee Construction, Inc. $2.67 $1,068.00 National Native American Construction, Inc. $3.00 $1,200.00 Engineer's Estimate 400 SQYD $5.00 $2,000.00
A0440 25101-0100 PLACED RIPRAP, METHOD A, CLASS 1
STG Pacific, LLC $310.70 $37,284.00 Winspear Construction, LLC $190.00 $22,800.00
EWS-RSCI, LLC $163.00 $19,560.00
Seabee Construction, Inc. $160.38 $19,245.60 National Native American Construction, Inc. $169.00 $20,280.00 Engineer's Estimate 120 CUYD $130.00 $15,600.00
A0460 25125-0000 BOULDER (ROCKFALL, 3-FT DIAMETER)
STG Pacific, LLC $1,229.00 $30,725.00 Winspear Construction, LLC $412.00 $10,300.00
EWS-RSCI, LLC $500.00 $12,500.00
Seabee Construction, Inc. $277.00 $6,925.00 National Native American Construction, Inc. $294.00 $7,350.00 Engineer's Estimate 25 EACH $250.00 $6,250.00
A0480 25501-4000 MECHANICALLY STABILIZED EARTH WALL, PRECAST CONCRETE PANEL FACED
STG Pacific, LLC $76.99 $523,532.00 Winspear Construction, LLC $165.00 $1,122,000.00
EWS-RSCI, LLC $100.00 $680,000.00
Seabee Construction, Inc. $144.34 $981,512.00 National Native American Construction, Inc. $173.00 $1,176,400.00 Engineer's Estimate 6,800 SQFT $55.00 $374,000.00
A0500 25701-0200 CONTRACTOR FURNISHED MECHANICALLY STABILIZED EARTH WALL DESIGN
STG Pacific, LLC Lump Sum $31,567.00 Winspear Construction, LLC Lump Sum $243,000.00 EWS-RSCI, LLC Lump Sum $35,000.00 Seabee Construction, Inc. Lump Sum $53,460.81 National Native American Construction, Inc. Lump Sum $64,098.00 Engineer's Estimate ALL LPSM Lump Sum $30,000.00
7 out of 15Source Selection Information - See FAR 2.101 & 3.104
Project No: ID DOT 21(1)
Project Name: SH-21 Wildlife Overpass at Cervidae Peak, MP 19.3
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0520 25701-0400 CONTRACTOR FURNISHED REINFORCED CONCRETE RETAINING WALL DESIGN
STG Pacific, LLC Lump Sum $6,130.00 Winspear Construction, LLC Lump Sum $325,000.00 EWS-RSCI, LLC Lump Sum $20,000.00 Seabee Construction, Inc. Lump Sum $53,460.81 National Native American Construction, Inc. Lump Sum $64,098.00 Engineer's Estimate ALL LPSM Lump Sum $30,000.00
A0540 25801-0000 REINFORCED CONCRETE RETAINING WALL (PRECAST)
STG Pacific, LLC $95.00 $275,500.00 Winspear Construction, LLC $175.00 $507,500.00
EWS-RSCI, LLC $145.00 $420,500.00
Seabee Construction, Inc. $106.92 $310,068.00 National Native American Construction, Inc. $128.00 $371,200.00 Engineer's Estimate 2,900 SQFT $65.00 $188,500.00
A0560 30202-2000 ROADWAY AGGREGATE, METHOD 2
STG Pacific, LLC $86.05 $49,909.00 Winspear Construction, LLC $100.00 $58,000.00
EWS-RSCI, LLC $29.00 $16,820.00
Seabee Construction, Inc. $47.05 $27,289.00 National Native American Construction, Inc. $56.00 $32,480.00 Engineer's Estimate 580 TON $45.00 $26,100.00
A0580 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1
STG Pacific, LLC $156.46 $78,230.00 Winspear Construction, LLC $145.00 $72,500.00
EWS-RSCI, LLC $160.00 $80,000.00
Seabee Construction, Inc. $160.38 $80,190.00 National Native American Construction, Inc. $185.00 $92,500.00 Engineer's Estimate 500 TON $140.00 $70,000.00
A0600 41201-0000 TACK COAT
STG Pacific, LLC $4,290.63 $8,581.26 Winspear Construction, LLC $1,825.00 $3,650.00
EWS-RSCI, LLC $1,000.00 $2,000.00
Seabee Construction, Inc. $1,283.06 $2,566.12 National Native American Construction, Inc. $1,482.00 $2,964.00 Engineer's Estimate 2.0 TON $1,000.00 $2,000.00
8 out of 15Source Selection Information - See FAR 2.101 & 3.104
Project No: ID DOT 21(1)
Project Name: SH-21 Wildlife Overpass at Cervidae Peak, MP 19.3
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0620 41301-0400 ASPHALT PAVEMENT MILLING, 1 1/2-INCH DEPTH
STG Pacific, LLC $27.14 $70,564.00 Winspear Construction, LLC $10.00 $26,000.00
EWS-RSCI, LLC $5.00 $13,000.00
Seabee Construction, Inc. $4.81 $12,506.00 National Native American Construction, Inc. $5.00 $13,000.00 Engineer's Estimate 2,600 SQYD $13.00 $33,800.00
A0640 55601-0900 BRIDGE RAILING, STEEL (6 FT STEEL MESH FENCING)
STG Pacific, LLC $749.84 $292,437.60 Winspear Construction, LLC $320.00 $124,800.00
EWS-RSCI, LLC $600.00 $234,000.00
Seabee Construction, Inc. $427.69 $166,799.10 National Native American Construction, Inc. $494.00 $192,660.00 Engineer's Estimate 390 LNFT $175.00 $68,250.00
A0660 60216-0000 LARGE PRECAST CONCRETE ARCH CULVERT (WILDLIFE OVERCROSSING STRUCTURE)
STG Pacific, LLC $12,297.27 $1,844,590.50 Winspear Construction, LLC $14,250.00 $2,137,500.00
EWS-RSCI, LLC $18,665.00 $2,799,750.00
Seabee Construction, Inc. $17,339.75 $2,600,962.50 National Native American Construction, Inc. $20,511.00 $3,076,650.00 Engineer's Estimate 150 LNFT $7,500.00 $1,125,000.00
A0680 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS
STG Pacific, LLC $41.68 $25,008.00 Winspear Construction, LLC $41.00 $24,600.00
EWS-RSCI, LLC $35.00 $21,000.00
Seabee Construction, Inc. $40.63 $24,378.00 National Native American Construction, Inc. $49.00 $29,400.00 Engineer's Estimate 600 LNFT $45.00 $27,000.00
A0700 61702-0000 TERMINAL SECTION (SHORT RADIUS GUARDRAIL)
STG Pacific, LLC $20,840.21 $20,840.21 Winspear Construction, LLC $20,500.00 $20,500.00
EWS-RSCI, LLC $18,100.00 $18,100.00
Seabee Construction, Inc. $19,245.89 $19,245.89 National Native American Construction, Inc. $23,075.00 $23,075.00 Engineer's Estimate 1 EACH $5,000.00 $5,000.00
9 out of 15Source Selection Information - See FAR 2.101 & 3.104
Project No: ID DOT 21(1)
Project Name: SH-21 Wildlife Overpass at Cervidae Peak, MP 19.3
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0720 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT
STG Pacific, LLC $4,168.04 $16,672.16 Winspear Construction, LLC $4,100.00 $16,400.00
EWS-RSCI, LLC $3,600.00 $14,400.00
Seabee Construction, Inc. $3,902.64 $15,610.56 National Native American Construction, Inc. $4,679.00 $18,716.00 Engineer's Estimate 4 EACH $3,500.00 $14,000.00
A0740 61707-4000 STRUCTURE TRANSITION RAILING, MGS SYSTEM
STG Pacific, LLC $134.85 $6,742.50 Winspear Construction, LLC $133.00 $6,650.00
EWS-RSCI, LLC $185.00 $9,250.00
Seabee Construction, Inc. $128.31 $6,415.50 National Native American Construction, Inc. $154.00 $7,700.00 Engineer's Estimate 50 LNFT $115.00 $5,750.00
A0760 61711-0000 IMPACT ATTENUATOR
STG Pacific, LLC $46,583.99 $46,583.99 Winspear Construction, LLC $45,600.00 $45,600.00
EWS-RSCI, LLC $40,000.00 $40,000.00
Seabee Construction, Inc. $40,630.21 $40,630.21 National Native American Construction, Inc. $48,714.00 $48,714.00 Engineer's Estimate 1 EACH $27,000.00 $27,000.00
A0780 61801-0000 CONCRETE BARRIER
STG Pacific, LLC $164.25 $47,632.50 Winspear Construction, LLC $270.00 $78,300.00
EWS-RSCI, LLC $90.00 $26,100.00
Seabee Construction, Inc. $149.69 $43,410.10 National Native American Construction, Inc. $179.00 $51,910.00 Engineer's Estimate 290 LNFT $120.00 $34,800.00
A0800 61901-0000 FENCE (WILDLIFE)
STG Pacific, LLC $122.37 $1,309,359.00 Winspear Construction, LLC $100.00 $1,070,000.00
EWS-RSCI, LLC $84.00 $898,800.00
Seabee Construction, Inc. $95.16 $1,018,212.00 National Native American Construction, Inc. $115.00 $1,230,500.00 Engineer's Estimate 10,700 LNFT $40.00 $428,000.00
10 out of 15Source Selection Information - See FAR 2.101 & 3.104
Project No: ID DOT 21(1)
Project Name: SH-21 Wildlife Overpass at Cervidae Peak, MP 19.3
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0820 61901-0000 FENCE (WILDLIFE WITH BURIED APRON)
STG Pacific, LLC $149.47 $538,092.00 Winspear Construction, LLC $120.00 $432,000.00
EWS-RSCI, LLC $90.00 $324,000.00
Seabee Construction, Inc. $112.80 $406,080.00 National Native American Construction, Inc. $122.00 $439,200.00 Engineer's Estimate 3,600 LNFT $60.00 $216,000.00
A0840 61902-4500 GATE, WOVEN WIRE, 4 FEET WIDTH (SINGLE)
STG Pacific, LLC $735.53 $2,206.59 Winspear Construction, LLC $2,320.00 $6,960.00
EWS-RSCI, LLC $2,050.00 $6,150.00
Seabee Construction, Inc. $641.53 $1,924.59 National Native American Construction, Inc. $2,564.00 $7,692.00 Engineer's Estimate 3 EACH $800.00 $2,400.00
A0860 61902-4900 GATE, WOVEN WIRE, 12 FEET WIDTH (COMBINATION)
STG Pacific, LLC $1,961.43 $17,652.87 Winspear Construction, LLC $2,520.00 $22,680.00
EWS-RSCI, LLC $2,200.00 $19,800.00
Seabee Construction, Inc. $1,710.75 $15,396.75 National Native American Construction, Inc. $2,820.00 $25,380.00 Engineer's Estimate 9 EACH $1,300.00 $11,700.00
A0880 61902-4900 GATE, WOVEN WIRE, 12 FEET WIDTH (SINGLE)
STG Pacific, LLC $1,716.25 $6,865.00 Winspear Construction, LLC $2,330.00 $9,320.00
EWS-RSCI, LLC $2,050.00 $8,200.00
Seabee Construction, Inc. $1,496.90 $5,987.60 National Native American Construction, Inc. $2,564.00 $10,256.00 Engineer's Estimate 4 EACH $1,000.00 $4,000.00
A0900 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
STG Pacific, LLC $214.24 $5,141.76 Winspear Construction, LLC $152.00 $3,648.00
EWS-RSCI, LLC $120.00 $2,880.00
Seabee Construction, Inc. $197.80 $4,747.20 National Native American Construction, Inc. $185.00 $4,440.00 Engineer's Estimate 24 HOUR $150.00 $3,600.00
11 out of 15Source Selection Information - See FAR 2.101 & 3.104
Project No: ID DOT 21(1)
Project Name: SH-21 Wildlife Overpass at Cervidae Peak, MP 19.3
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0920 62201-0600 BACKHOE LOADER, 8 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 30-INCH WIDTH
STG Pacific, LLC $214.24 $5,141.76 Winspear Construction, LLC $170.00 $4,080.00
EWS-RSCI, LLC $110.00 $2,640.00
Seabee Construction, Inc. $320.76 $7,698.24 National Native American Construction, Inc. $300.00 $7,200.00 Engineer's Estimate 24 HOUR $120.00 $2,880.00
A0940 62301-0000 GENERAL LABOR
STG Pacific, LLC $565.17 $13,564.08 Winspear Construction, LLC $40.00 $960.00
EWS-RSCI, LLC $60.00 $1,440.00
Seabee Construction, Inc. $133.65 $3,207.60 National Native American Construction, Inc. $125.00 $3,000.00 Engineer's Estimate 24 HOUR $75.00 $1,800.00
A0960 62402-0300 FURNISHING AND PLACING TOPSOIL, 4-INCH DEPTH
STG Pacific, LLC $43,878.06 $39,490.25 Winspear Construction, LLC $31,000.00 $27,900.00
EWS-RSCI, LLC $18,500.00 $16,650.00
Seabee Construction, Inc. $26,730.40 $24,057.36 National Native American Construction, Inc. $25,000.00 $22,500.00 Engineer's Estimate 0.90 ACRE $30,000.00 $27,000.00
A0980 62501-0000 TURF ESTABLISHMENT
STG Pacific, LLC $11,462.11 $19,485.59 Winspear Construction, LLC $4,000.00 $6,800.00
EWS-RSCI, LLC $3,500.00 $5,950.00
Seabee Construction, Inc. $22,396.93 $38,074.78 National Native American Construction, Inc. $3,300.00 $5,610.00 Engineer's Estimate 1.70 ACRE $3,200.00 $5,440.00
A1000 63302-0000 SIGN SYSTEM
STG Pacific, LLC $820.86 $4,104.30 Winspear Construction, LLC $145.00 $725.00
EWS-RSCI, LLC $500.00 $2,500.00
Seabee Construction, Inc. $336.80 $1,684.00 National Native American Construction, Inc. $135.00 $675.00 Engineer's Estimate 5 SQFT $85.00 $425.00
12 out of 15Source Selection Information - See FAR 2.101 & 3.104
Project No: ID DOT 21(1)
Project Name: SH-21 Wildlife Overpass at Cervidae Peak, MP 19.3
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1020 63308-3000 OBJECT MARKER, TYPE 3
STG Pacific, LLC $634.77 $2,539.08 Winspear Construction, LLC $450.00 $1,800.00
EWS-RSCI, LLC $440.00 $1,760.00
Seabee Construction, Inc. $283.34 $1,133.36 National Native American Construction, Inc. $375.00 $1,500.00 Engineer's Estimate 4 EACH $350.00 $1,400.00
A1040 63309-0000 DELINEATOR
STG Pacific, LLC $62.90 $1,572.50 Winspear Construction, LLC $84.00 $2,100.00
EWS-RSCI, LLC $40.00 $1,000.00
Seabee Construction, Inc. $41.70 $1,042.50 National Native American Construction, Inc. $60.00 $1,500.00 Engineer's Estimate 25 EACH $42.00 $1,050.00
A1060 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID
STG Pacific, LLC $0.74 $4,070.00 Winspear Construction, LLC $1.00 $5,500.00
EWS-RSCI, LLC $0.75 $4,125.00
Seabee Construction, Inc. $0.64 $3,520.00 National Native American Construction, Inc. $1.00 $5,500.00 Engineer's Estimate 5,500 LNFT $1.00 $5,500.00
A1080 63401-0400 PAVEMENT MARKINGS, TYPE B, BROKEN
STG Pacific, LLC $0.74 $222.00 Winspear Construction, LLC $1.00 $300.00
EWS-RSCI, LLC $0.75 $225.00
Seabee Construction, Inc. $0.64 $192.00 National Native American Construction, Inc. $1.00 $300.00 Engineer's Estimate 300 LNFT $5.00 $1,500.00
A1100 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
STG Pacific, LLC $2,315.22 $9,260.88 Winspear Construction, LLC $104.00 $416.00
EWS-RSCI, LLC $155.00 $620.00
Seabee Construction, Inc. $90.88 $363.52 National Native American Construction, Inc. $128.00 $512.00 Engineer's Estimate 4 EACH $300.00 $1,200.00
13 out of 15Source Selection Information - See FAR 2.101 & 3.104
Project No: ID DOT 21(1)
Project Name: SH-21 Wildlife Overpass at Cervidae Peak, MP 19.3
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1120 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
STG Pacific, LLC $2,790.37 $83,711.10 Winspear Construction, LLC $22.50 $675.00
EWS-RSCI, LLC $55.00 $1,650.00
Seabee Construction, Inc. $19.51 $585.30 National Native American Construction, Inc. $26.00 $780.00 Engineer's Estimate 30 EACH $75.00 $2,250.00
A1140 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
STG Pacific, LLC $17,170.73 $34,341.46 Winspear Construction, LLC $4,375.00 $8,750.00
EWS-RSCI, LLC $12,500.00 $25,000.00
Seabee Construction, Inc. $3,822.45 $7,644.90 National Native American Construction, Inc. $5,128.00 $10,256.00 Engineer's Estimate 2 EACH $6,000.00 $12,000.00
A1160 63502-2100 TEMPORARY TRAFFIC CONTROL, CRASH CUSHION
STG Pacific, LLC $14,097.79 $56,391.16 Winspear Construction, LLC $4,680.00 $18,720.00
EWS-RSCI, LLC $5,000.00 $20,000.00
Seabee Construction, Inc. $4,089.75 $16,359.00 National Native American Construction, Inc. $16,665.00 $66,660.00 Engineer's Estimate 4 EACH $4,500.00 $18,000.00
A1180 63502-3100 TEMPORARY TRAFFIC CONTROL, TRAFFIC SIGNAL SYSTEM
STG Pacific, LLC $47,335.94 $47,335.94 Winspear Construction, LLC $19,380.00 $19,380.00
EWS-RSCI, LLC $42,000.00 $42,000.00
Seabee Construction, Inc. $16,947.08 $16,947.08 National Native American Construction, Inc. $21,152.00 $21,152.00 Engineer's Estimate 1 EACH $25,000.00 $25,000.00
A1200 63503-0400 TEMPORARY TRAFFIC CONTROL, CONCRETE BARRIER
STG Pacific, LLC $42.65 $63,975.00 Winspear Construction, LLC $31.50 $47,250.00
EWS-RSCI, LLC $50.00 $75,000.00
Seabee Construction, Inc. $37.42 $56,130.00 National Native American Construction, Inc. $45.00 $67,500.00 Engineer's Estimate 1,500 LNFT $40.00 $60,000.00
14 out of 15Source Selection Information - See FAR 2.101 & 3.104
Project No: ID DOT 21(1)
Project Name: SH-21 Wildlife Overpass at Cervidae Peak, MP 19.3
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1220 63503-0700 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
STG Pacific, LLC $5.79 $6,948.00 Winspear Construction, LLC $1.25 $1,500.00
EWS-RSCI, LLC $5.00 $6,000.00
Seabee Construction, Inc. $1.18 $1,416.00 National Native American Construction, Inc. $1.00 $1,200.00 Engineer's Estimate 1,200 LNFT $1.00 $1,200.00
A1240 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
STG Pacific, LLC $17.88 $6,615.60 Winspear Construction, LLC $13.00 $4,810.00
EWS-RSCI, LLC $30.00 $11,100.00
Seabee Construction, Inc. $11.23 $4,155.10 National Native American Construction, Inc. $15.00 $5,550.00 Engineer's Estimate 370 SQFT $10.00 $3,700.00
A1260 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
STG Pacific, LLC $367.93 $14,717.20 Winspear Construction, LLC $60.00 $2,400.00
EWS-RSCI, LLC $75.00 $3,000.00
Seabee Construction, Inc. $43.43 $1,737.20 National Native American Construction, Inc. $55.00 $2,200.00 Engineer's Estimate 40 HOUR $55.00 $2,200.00
A1280 63507-0700 TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR
STG Pacific, LLC $1,114.86 $100,337.40 Winspear Construction, LLC $683.00 $61,470.00
EWS-RSCI, LLC $1,000.00 $90,000.00
Seabee Construction, Inc. $596.34 $53,670.60 National Native American Construction, Inc. $600.00 $54,000.00 Engineer's Estimate 90 DAY $550.00 $49,500.00
A1300 64603-0000 FIXTURE (CAMERA PEDESTAL)
STG Pacific, LLC $1,494.05 $8,964.30 Winspear Construction, LLC $1,100.00 $6,600.00
EWS-RSCI, LLC $2,300.00 $13,800.00
Seabee Construction, Inc. $534.61 $3,207.66 National Native American Construction, Inc. $705.00 $4,230.00 Engineer's Estimate 6 EACH $1,000.00 $6,000.00
15 out of 15Source Selection Information - See FAR 2.101 & 3.104
Project No: ID DOT 21(1)
Project Name: SH-21 Wildlife Overpass at Cervidae Peak, MP 19.3
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1320 64603-0000 FIXTURE (JUMP-OUT)
STG Pacific, LLC $10,159.77 $111,757.47 Winspear Construction, LLC $18,000.00 $198,000.00
EWS-RSCI, LLC $22,500.00 $247,500.00
Seabee Construction, Inc. $19,245.89 $211,704.79 National Native American Construction, Inc. $23,075.00 $253,825.00 Engineer's Estimate 11 EACH $10,000.00 $110,000.00
Total Schedule - All Items
STG Pacific, LLC $7,272,729.09 Winspear Construction, LLC $7,660,000.00
EWS-RSCI, LLC $8,276,530.00
Seabee Construction, Inc. $8,383,766.92 National Native American Construction, Inc. $9,962,862.00 Engineer's Estimate $4,454,000.00