Amendment A001.pdf

PDF 189 KB Posted

Attached to
ID DOT 21(1) SH-21 Wildlife Overpass at Cervidae Peak, MP 19. 3
Solicitation number
69056721B000009
Issued by

About this file

This amendment modifies a solicitation for a construction project. The Idaho Department of Transportation Federal Highway Administration is seeking bids for the ID DOT 21(1) SH-21 Wildlife Overpass at Cervidae Peak, MP 19.3 project. Amendment A001 revises the specifications and permits section to add scheduling requirements. Bidders must submit a baseline schedule addressing work through project completion, attend a schedule submittal meeting, and obtain approval of the baseline schedule submittal from the schedule manager prior to mobilization and commencement of work on site. Schedule submittals must be approved monthly to receive full progress payments. The amendment does not change any other terms or conditions of the solicitation.

View the file

Other files

File Type Posted
BidTab_ID DOT 21(1).pdf PDF
BidSum-ID DOT 21(1) SH-21 Wildflife Overpass_FINAL_03_22_2022.pdf PDF
QA2_03-17-2022.pdf PDF
QA_03-17-2022.pdf PDF
Amendment A007.pdf PDF
QA_03-16-2022.pdf PDF
Amendment A006.pdf PDF
QA_03-09-2022.pdf PDF
Amendment A005.pdf PDF
Amendment A004.pdf PDF
QA_03-08-2022.pdf PDF
Amendment A003.pdf PDF
Amendment A002.pdf PDF
Page A-1.pdf PDF
QA_03-07-2022.pdf PDF
QA_03-03-2022.pdf PDF
QA_03-02-2022.pdf PDF
QA_03-01-2022.pdf PDF
QA_02-15-2022.pdf PDF
id-02101_Plans.pdf PDF
id-02101_Vertical Report.pdf PDF
id-02101_SH-21 Gradebook.pdf PDF
id-02101_Earthwork.pdf PDF
id-02101_Horizontal Report.pdf PDF
IFB 69056721B000009 .pdf PDF
GM 51-20 - SH-21 Wildlife Overpass - Final Foundations Recommendations (Rev 01B).pdf PDF
id-02101_XS.pdf PDF
Additiona physical data.zip ZIP file
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

N/A

PAGE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)

A001 02/24/2022 N/A See Box 14

6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A

Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.

X

69056721B000009

9B. DATED (SEE ITEM 11)

03/10/2022

10A. MODIFICATION OF CONTRACT/ORDER NO.

N/A

10B. DATED (SEE ITEM 13)

CODE: N/A FACILITY CODE: N/A

N/A

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

(__ ) is extended, ( x ) is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

N/A

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN

ITEM 10A.

N/A

B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D OTHER (Specify type of modification and authority)

N/A

E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

ID DOT 21(1), SH-21 Wildflife Overpass at Cervidae Peak, MP 19.3

Amendment A001 is issued to revise the following:

NOTICE TO BIDDERS Page A-2b. Part IV, Specifications and Permits. Adds Scheduling Requirements.

ENCLOSURES: Page A-2b

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

N/A

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION NOT USABLE

30-105 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

A-2b

(This page intentionally left blank)

Scheduling Requirements. Carefully review Section 155 (Schedules for Construction Contracts) of the Special Contract Requirements. This new scheduling specification requires the following activities prior to Section 155 mobilization and commencing work on the project site: 1) a baseline schedule submittal (schedule, schedule narrative, and submittal log) addressing work through project completion, 2) a schedule submittal meeting, and 3) approval of the baseline schedule submittal. The schedule submittal is to be managed by a schedule manager. Schedule submittals are required to be submitted/approved monthly to receive full progress payments.

Revised by Amendment A001

Notice to Bidders Project: ID DOT 21(1), SH-21 Wildflife Overpass at Cervidae Peak, MP 19.3