621-20-103 Bid Specs Volume 2.pdf

PDF 4 MB Posted

Attached to
Z1DA--36C249-21-AP-4216 - 621-20-103 - Renovate Bldg. 77 for Customer Service
Solicitation number
36C24921B0018
Issued by

About this file

This solicitation document is for a construction project to renovate Building 77 at the Quillen VA Medical Center in Johnson City, Tennessee to provide customer service facilities. The project magnitude is estimated between $500,000 and $1,000,000. The solicitation is issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9. The solicitation number is 36C24921B0018. The project scope involves renovations and upgrades to existing systems including HVAC, electrical, fire suppression and alarm. The response due date is not provided in this document.

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL SPECIFICATIONS

Renovate Building 77 for Customer Service

VA Project Number: 621-20-103

Department of Veterans Affairs MidSouth Healthcare Network

Quillen VA Medical Center Lamont Street & Veterans Way

Johnson City, TN 37604

BID DOCUMENTS

June 23, 2021

Raymond-Pond SDVOSB JV, LLC 1224 Royal Drive

Suite 100 Conyers, GA 30094

RAYMOND PROJECT NUMBER – 1418.025

POND PROJECT NUMBER – 1200973

VOLUME 2

This Page Intentionally Left Blank

Project No. 621-20-103 June 23, 2021

Renovate Bldg 77 for Customer Service Bid Documents

00 01 07 - 1

SECTION 00 01 07

PROFESSIONAL SEALS

1.1 DESIGN PROFESSIONALS OF RECORD

A. Structural Engineer:

1. Angela Booth

2. Georgia #PE-030374

3. Responsible for Divisions 03, 05, and 13.

B. Architect:

1. Lorraine White

2. South Carolina #9392

3. Responsible for Divisions 02 and 06-12.

C. Fire Protection Engineer:

1. Brandon Hofstead

2. Tennessee #122803

3. Responsible for Division 21 and

Sections 28 08 00 and 28 31 00.

D. Mechanical Engineer:

1. Charles A. Hanning III

2. Alabama #29025-E

3. Responsible for Division 23.

E. Electrical Engineer:

1. Joseph Stitt

2. Tennessee #122991

3. Responsible for Divisions 26-28

(except 28 08 00 and 28 31 00).

- - - E N D - - -

00 01 10 - 1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

VOLUME 1

DIVISION 00 - SPECIAL SECTIONS

00 01 07 Professional Seals N/A

00 01 10 Table of Contents 12-20

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 03-20

01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build) 03-20

01 33 23 Shop Drawings, Product Data, and Samples 05-17

Submittal Register

01 35 26 Safety Requirements 07-20

01 42 19 Reference Standards 11-20

01 45 00 Quality Control 03-19

01 45 29 Testing Laboratory Services 11-18

01 45 35 Special Inspections 03-19

Statement of Special Inspections

Schedule of Special Inspections

01 57 19 Temporary Environmental Controls 01-11

01 58 16 Temporary Interior Signage 07-15

01 74 19 Construction Waste Management 09-13

01 91 00 General Commissioning Requirements 10-15

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

DIVISION 03 – CONCRETE (NOT USED)

DIVISION 04 – MASONRY (NOT USED)

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18

05 40 00 Cold-Formed Metal Framing 05-16

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

06 20 00 Finish Carpentry 08-16

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

00 01 10 - 2

07 21 13 Thermal Insulation 01-21

07 60 00 Flashing and Sheet Metal 01-21

07 84 00 Firestopping 02-16

07 92 00 Joint Sealants 10-17

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21

08 14 00 Interior Wood Doors 01-21

08 41 13 Aluminum-Framed Entrances and Storefronts 01-21

08 42 29.23 Sliding Automatic Entrances 12-20

08 71 00 Door Hardware 01-21

08 71 13 Automatic Door Operators 01-21

08 80 00 Glazing 10-15

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 02-15

09 22 16 Non-Structural Metal Framing 06-18

09 29 00 Gypsum Board 04-20

09 51 00 Acoustical Ceilings 12-18

09 65 13 Resilient Base and Accessories 02-16

09 65 19 Resilient Tile Flooring 05-18

09 68 00 Carpeting 10-15

09 70 00 Wall Finishes 01-21

09 72 16 Vinyl-Coated Fabric Wall Coverings 10-15

09 91 00 Painting 01-16

DIVISION 10 – SPECIALTIES

10 14 00 Signage 10-15

10 22 19 Demountable Partitions 04-16

DIVISION 11 – EQUIPMENT (NOT USED)

DIVISION 12 – FURNISHINGS (NOT USED)

VOLUME 2

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural

Components

01-14

DIVISION 14 – CONVEYING EQUIPMENT (NOT USED)

DIVISION 21 - FIRE SUPPRESSION

21 08 00 Commissioning of Fire Suppression Systems 11-16

21 13 13 Wet-Pipe Sprinkler Systems 06-15

00 01 10 - 3

DIVISION 22 – PLUMBING (NOT USED)

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 02-20

23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment

02-20

23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment

02-20

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20

23 07 11 HVAC and Boiler Plant Insulation 02-20

23 08 00 Commissioning of HVAC Systems 02-20

23 09 23 Direct-Digital Control System for HVAC 09-11

23 31 00 HVAC Ducts and Casings 02-20

23 37 00 Air Outlets and Inlets 02-20

23 81 43 Air-Source Unitary Heat Pumps 03-20

DIVISION 25 – INTEGRATED AUTOMATION (NOT USED)

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16

26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17

26 05 26 Grounding and Bonding for Electrical Systems 01-17

26 05 33 Raceway and Boxes for Electrical Systems 01-18

26 09 23 Lighting Controls 01-18

26 24 16 Panelboards 01-18

26 27 26 Wiring Devices 01-18

26 51 00 Interior Lighting 01-18

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19

27 05 33 Raceways and Boxes for Communications Systems 10-18

27 10 00 Control, Communication and Signal Wiring 06-15

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18

28 05 13 Conductors and Cables for Electronic Safety and

Security

10-18

28 05 28.33 Conduits and Backboxes for Electronic Safety and

Security

09-11

28 08 00 Commissioning of Electronic Safety and Security Systems 11-16

28 13 00 Physical Access Control System 10-11

28 31 00 Fire Detection and Alarm 10-11

DIVISION 31 – EARTHWORK (NOT USED)

DIVISION 32 – EXTERIOR IMPROVEMENTS (NOT USED)

00 01 10 - 4

DIVISION 33 – UTILITIES (NOT USED)

DIVISION 34 – TRANSPORTATION (NOT USED)

DIVISION 48 – ELECTRICAL POWER GENERATION (NOT USED)

13 05 41 - 1

SECTION 13 05 41

SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS

PART 1 - GENERAL

1.1 DESCRIPTION:

A. Provide seismic restraint in accordance with the requirements of the drawings, VA Handbook H18-8: Seismic Design Requirements and this specification in order to maintain the integrity of non-structural components and equipment of the building so that they remain safe and functional in case of seismic event.

B. The design of seismic restraints of non-structural components to resist seismic load shall be based on Seismic Design parameters indicated below in accordance with VA H-18-8 in conjunction with ASCE 7, as specified in H-18-8 Section 4.0, for existing building retrofit projects. Specific requirements for Critical and Essential facilities are covered in Section 4.0 of H-18-8, including applying Ip = 1.5 for all nonstructural components in Critical facilities.

1. International Building Code 2018 Edition

2. American Society of Civil Engineers Minimum Design Loads and

Associated Criteria for Buildings and Other Structures (ASCE 7)7-16

3. Facility Occupancy Category per VA H-18-8: Critical Facility

4. Site Class: D

5. Building Risk Category: IV

6. Mapped MCER 0.2 s period Spectral Response Acceleration Parameter

(Ss): 0.294

7. Mapped MCER 1.0 s period Spectral Response Acceleration Parameter

(S1): 0.09

8. Short period Spectral Response Acceleration Parameter (Sds): 0.307

9. Short period Spectral Response Acceleration Parameter (Sd1): 0.144

10. Building Seismic Design Category: D

11. Component Importance Factor (Ip): 1.5

12. Component Response Modification Factor (Rp): 2 1/2

13. Component Overstrength Factor: 2

C. Definitions: Non-structural building components are components or systems that are not part of the building’s structural system whether inside or outside, above or below grade. Non-structural components of buildings include but are not limited to (Refer to VA H-18-8, ASCE 7 for additional examples):

13 05 41 - 2

1. Architectural Elements: Facades that are not part of the structural system and its shear resistant elements; cornices and other architectural projections and parapets that do not function structurally; glazing; nonbearing partitions; suspended ceilings;

stairs isolated from the basic structure; cabinets; bookshelves;

medical equipment; and storage racks, etc.

2. Electrical Elements: Power and lighting systems; substations;

switchgear and switchboards; auxiliary engine-generator sets;

transfer switches; motor control centers; motor generators; selector and controller panels; fire protection and alarm systems; special life support systems; and telephone and communication systems, etc.

3. Mechanical Elements: Heating, ventilating, and air-conditioning systems; medical gas systems; plumbing systems; sprinkler systems;

pneumatic systems; boiler/chiller/utility plant/other equipment and components, etc.

1.2 RELATED WORK:

Related specifications include but are not limited to those shown below.

Coordinate all work with the applicable specification for that work.

A. Structural Steel Framing: Section 05 12 00, STRUCTURAL STEEL FRAMING

B. Acoustical Ceilings: Section 09 51 00 ACOUSTICAL CEILINGS

C. Interior Lighting: Section 26 51 00, INTERIOR LIGHTING

1.3 QUALITY CONTROL:

A. Shop-Drawing Preparation:

1. Non-structural seismic restraint systems shop drawings and delegated design calculations shall be prepared by a professional structural engineer with a minimum of 5 years’ experience in the design and detailing of seismic force restraints. The professional structural engineer shall be registered in the state where the project is located and submit qualifications with list of projects illustrating compliance with the experience requirement of this section.

2. Submit design tables and information used for the design-force levels, stamped and signed by a professional structural engineer registered in the State where project is located.

B. Coordination:

1. Do not install seismic restraints until seismic restraint submittals are approved by the Contracting Officers Representative (COR).

2. Coordinate trapezes or other multi-pipe hanger systems prior to submission of shop drawings for review.

13 05 41 - 3

C. Seismic Certification:

In structures assigned to Seismic Design Category C, D, E, or F, permanent equipment and components are to have Special Seismic

Certification in accordance with requirements of section 13.2.2 of ASCE

7, except for equipment and components that are considered inherently rugged as listed in Section 4.2.2 of VA H18-8, and shall comply with section 13.2.6 of ASCE 7.

1.4 SUBMITTALS:

A. Submit a complete and coordinated set of bracing and signed and sealed anchorage drawings and calculations for all non-structural elements requiring seismic restraint by the delegated professional structural engineer mentioned in Section 1.3.A.1 for review prior to installation including:

1. Description, layout, and location of all items to be anchored or braced with anchorage or brace points noted and dimensioned.

2. Details of all anchorage and bracing at large scale with all members, parts brackets shown, together with all connections, bolts, welds etc. clearly identified and specified. Details shall be coordinated with all project conditions and trades prior to shop drawing submission for review.

3. Complete calculations including but not limited to seismic design criteria, computer model input and output, seismic design forces and capacities, design tables and information used for all proprietary design elements such as post installed anchors, stamped and signed by a professional structural engineer specified in section 1.3 A.1.

4. For all post installed anchorages submit the appropriate

International Code Council Engineering Service (ICC-ES) evaluation reports, California’s Office of Statewide Health Planning and

Development(OSHPD) pre-approvals, or lab test reports verifying compliance with OSHPD Interpretation of Regulations 28-6.

5. Delegated professional structural engineer qualifications.

B. Submit for review prior to installation, the following for seismic protection of piping in addition to items noted in Section 1.4.A:

1. Single-line piping diagrams on a floor-by-floor basis. Show all suspended piping for a given floor on the same plain.

2. Type of pipe (Copper, steel, cast iron, insulated, non-insulated, etc.).

3. Pipe contents.

13 05 41 - 4

4. Structural framing for the seismic and gravity support and the main superstructure for which the bracing and or anchorage is attached.

5. Location of all gravity load pipe supports and spacing requirements.

6. Numerical value of gravity load reactions.

7. Location of all seismic bracing.

8. Numerical value of applied seismic brace loads.

9. Type of connection (Vertical support, vertical support with seismic brace etc.).

10. Seismic brace reaction type (tension or compression): Details illustrating all support and bracing components, methods of connections, and specific anchors to be used.

C. Submit for review prior to installation, the following items for seismic protection of suspended ductwork and suspended electrical and communication cables, in addition to items noted in Section 1.4.A:

1. Details illustrating all support and bracing components, methods of connection, and specific anchors to be used.

2. Numerical value of applied gravity and seismic loads and seismic loads acting on support and bracing components.

3. Maximum spacing of hangers and bracing.

1.5 APPLICABLE PUBLICATIONS:

A. The Publications listed below (including amendments, addenda revisions, supplements and errata) form a part of this specification to the extent referenced. The publications are referenced in text by basic designation only.

B. American Concrete Institute (ACI):

355.2-19 ...............Qualification for Post-Installed Mechanical

Anchors in Concrete and Commentary

C. American Institute of Steel Construction (AISC):

Load and Resistance Factor Design, Volume 1, Second Edition

D. ASTM International (ASTM):

A36/A36M-19 ............Standard Specification for Carbon Structural

Steel

A53/A53M-18 ............Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and

Seamless

13 05 41 - 5

A307-14e1 ..............Standard Specifications for Carbon Steel Bolts, Studs, and Threaded Rod 60,000 PSI Tensile

Strength

A325-14 ................Standard Specification for Structural Bolts, Steel, Heat Treated, 120/105 ksi Minimum

Tensile Strength

A325M-14 ...............Standard Specification for High-Strength Bolts for Structural Steel Joints [Metric]

A490-14a ...............Standard Specification for Heat-Treated Steel

Structural Bolts, 150 ksi Minimum Tensile

Strength

A490M-14a ..............Standard Specification for High-Strength Steel

Bolts, Classes 10.9 and 10.9.3, for Structural

Steel Joints [Metric]

A500/A500M-18 ..........Standard Specification for Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in

Rounds and Shapes

A501/A501M-14 ..........Standard Specification for Hot-Formed Welded and Seamless Carbon Steel Structural Tubing

A615/A615M-20 ..........Standard Specification for Deformed and Plain

Carbon Steel Bars for Concrete Reinforcement

A992/A992M-11(2015) ....Standard Specification for Steel for Structural

Shapes for Use in Building Framing

A996/A996M-16 ..........Standard Specification for Rail Steel and Axle

Steel Deformed Bars for Concrete Reinforcement

E488/E488M-18 ..........Standard Test Methods for Strength of Anchors in Concrete Elements

E. American Society of Civil Engineers

1. Minimum Design Loads and Associated Criteria for Buildings and Other

Structures (ASCE 7) Edition as indicated in section 1.1 B of this specification. Associated Criteria for Buildings and Other

Structures (ASCE 7): 7-16

F. International Building Code (IBC) Edition as indicated in Section 1.1 B of this specification.

G. VA Handbook H18-8 Seismic Design Requirements, VA H-18-8, November

2019(REVISED MAY 1,2020)

H. National Uniform Seismic Installation Guidelines (NUSIG)

I. Sheet Metal and Air Conditioning Contractors National Association

13 05 41 - 6

J. (SMACNA): Seismic Restraint Manual - Guidelines for Mechanical Systems, 3RD EDITION 2008 and Addendum

1.6 REGULATORY REQUIREMENT:

A. IBC as shown in Section 1.1 B of this specification.

B. Exceptions: The omission of seismic restraints shall be allowed only in accordance with VA H18-8 and ASCE 7.

PART 2 - PRODUCTS

2.1 STEEL:

A. Structural Steel: ASTM A36.

B. Structural Tubing: ASTM A500, Grade B.

C. Structural Tubing: ASTM A501.

D. Steel Pipe: ASTM A53/A53M, Grade B.

E. Bolts & Nuts: ASTM A307.

PART 3 - EXECUTION

3.1 CONSTRUCTION, GENERAL:

A. Provide equipment supports and anchoring devices to withstand the seismic design forces, so that when seismic design forces are applied, the equipment cannot displace, overturn, or become inoperable.

B. Provide anchorages in conformance with recommendations of the equipment manufacturer and as shown on approved shop drawings and calculations.

C. Construct seismic restraints and anchorage to allow for thermal expansion.

D. Testing Before Final Inspection:

1. Test 10-percent of anchors in masonry and concrete per ASTM E488, and ACI 355.2 to determine that they meet the required load capacity. If any anchor fails to meet the required load, test the next 20 consecutive anchors, which are required to have zero failure, before resuming the 10-percent testing frequency.

2. Before scheduling Final Inspection, submit a report on this testing indicating the number and location of testing, and what anchor-loads were obtained.

3. Construct seismic restraints and anchorages to not interfere with other trades or damage existing or in-situ elements of the constructed building.

3.2 EQUIPMENT RESTRAINT AND BRACING:

A. See drawings for equipment to be restrained or braced.

13 05 41 - 7

3.3 MECHANICAL DUCTWORK AND PIPING; ELECTRICAL BUSWAYS, CONDUITS

A. Support and brace mechanical ductwork and piping; electrical busways, conduits to resist directional forces (lateral, longitudinal and vertical).

B. Brace duct branches with a minimum of 1 brace per branch.

C. Provide supports and anchoring so that, upon application of seismic forces, piping remains fully connected as operable systems which will not displace sufficiently to damage adjacent or connecting equipment, or building members.

D. Piping Connections: Provide flexible connections where pipes connect to equipment. Make the connections capable of accommodating relative differential movements between the pipe and equipment under conditions of earthquake shaking.

3.4 PARTITIONS(NOT USED)

3.5 CEILINGS AND LIGHTING FIXTURES

A. At intervals required to meet the seismic demand forces, laterally brace suspended ceilings against lateral and vertical movements, and provide with a physical separation at the walls.

B. Independently support and laterally brace all lighting fixtures. Refer to applicable portion of lighting specification, Section 26 51 00, INTERIOR LIGHTING.

21 08 00 - 1

SECTION 21 08 00

COMMISSIONING OF FIRE SUPPRESSION SYSTEMS

PART 1 - GENERAL

1.1 DESCRIPTION

A. The requirements of this Section apply to all sections of Division 21.

B. This project will have selected building systems commissioned. The complete list of equipment and systems to be commissioned is specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS. The commissioning process, which the Contractor is responsible to execute, is defined in Section 01 91 00 GENERAL COMMISSIONING REQUIRMENTS. A

Commissioning Agent (CxA) appointed by the VA will manage the commissioning process.

1.2 RELATED WORK

A. Section 01 00 00 GENERAL REQUIREMENTS.

B. Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.

C. Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

1.3 SUMMARY

A. This Section includes requirements for commissioning the Fire

Suppression systems, subsystems and equipment. This Section supplements the general requirements specified in Section 01 91 00

General Commissioning Requirements.

B. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for more details regarding processes and procedures as well as roles and responsibilities for all Commissioning Team members.

1.4 DEFINITIONS

A. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for definitions.

1.5 COMMISSIONED SYSTEMS

A. Commissioning of a system specified in Division 21 is part of the construction process. Documentation and testing of these systems, as well as training of the VA’s Operation and Maintenance personnel in accordance with the requirements of Section 01 91 00 and of Division

21, is required in cooperation with the VA and the Commissioning Agent.

B. The Fire Suppression systems commissioning will include the systems listed in Section 01 91 00 General Commissioning Requirements.

21 08 00 - 2

1.6 SUBMITTALS

A. The commissioning process requires review of selected Submittals. The

Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to

Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.

B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL

COMMISSIONING REQUIREMENTS.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 CONSTRUCTION INSPECTIONS

A. Commissioning of the building fire suppression systems will require inspection of individual elements of the fire suppression construction throughout the construction period. The Contractor shall coordinate with the Commissioning Agent in accordance with Section 01 91 00 and the Commissioning plan to schedule inspections as required to support the Commissioning Process.

3.2 PRE-FUNCTIONAL CHECKLISTS

A. The Contractor shall complete Pre-Functional Checklists to verify systems, subsystems, and equipment installation is complete and systems are ready for Systems Functional Performance Testing. The

Commissioning Agent will prepare Pre-Functional Checklists to be used to document equipment installation. The Contractor shall complete the checklists. Completed checklists shall be submitted to the VA and to the Commissioning Agent for review. The Commissioning Agent may spot check a sample of completed checklists. If the Commissioning Agent determines that the information provided on the checklist is not accurate, the Commissioning Agent will return the marked-up checklist to the Contractor for correction and resubmission. If the

Commissioning Agent determines that a significant number of completed checklists for similar equipment are not accurate, the Commissioning

Agent will select a broader sample of checklists for review. If the

Commissioning Agent determines that a significant number of the broader sample of checklists is also inaccurate, all the checklists for the type of equipment will be returned to the Contractor for correction and

21 08 00 - 3 resubmission. Refer to SECTION 01 91 00 GENERAL COMMISSIONING

REQUIREMENTS for submittal requirements for Pre-Functional Checklists, Equipment Startup Reports, and other commissioning documents.

3.3 CONTRACTORS TESTS

A. Contractor tests as required by other sections of Division 21 shall be scheduled and documented in accordance with Section 01 00 00 GENERAL

REQUIREMENTS. All testing shall be incorporated into the project schedule. Contractor shall provide no less than 7 calendar days’ notice of testing. The Commissioning Agent will witness selected

Contractor tests at the sole discretion of the Commissioning Agent.

Contractor tests shall be completed prior to scheduling Systems

Functional Performance Testing.

3.4 SYSTEMS FUNCTIONAL PERFORMANCE TESTING

A. The Commissioning Process includes Systems Functional Performance

Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems

Functional Performance Test procedures for review and approval by the

COR. The Contractor shall review and comment on the tests prior to approval. The Contractor shall provide the required labor, materials, and test equipment identified in the test procedure to perform the tests. The Commissioning Agent will witness and document the testing.

The Contractor shall sign the test reports to verify tests were performed. See Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS, for additional details.

- - - END - - -

21 13 13 - 1

SECTION 21 13 13

WET-PIPE SPRINKLER SYSTEMS

PART 1 - GENERAL

1.1 DESCRIPTION

A. Design, installation and testing shall be in accordance with

NFPA 13.

B. The design and installation a wet-pipe system complete and ready for operation, for the new Customer Service center of Building 77.

C. Modification of the existing sprinkler system as indicated on the drawings and as further required by these specifications.

1.2 RELATED WORK

A. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

B. Section 07 84 00, FIRESTOPPING.

C. Section 09 91 00, PAINTING.

D. Section 28 31 00, FIRE DETECTION AND ALARM.

1.3 DESIGN CRITERIA

A. Design Basis Information: Provide design, materials, equipment, installation, inspection, and testing of the automatic sprinkler system in accordance with the requirements of NFPA 13.

1. Sprinkler Protection: Sprinkler hazard classifications shall be in accordance with NFPA 13. The hazard classification examples of uses and conditions identified in the Annex of NFPA 13 shall be mandatory for areas not listed below. To determining spacing and sizing, apply the following coverage classifications:

a. Light Hazard Occupancies: Offices and customary access areas.

b. Ordinary Hazard Group 1 Occupancies: Copy/Printer room.

2. Water Supply: The existing water supply will not be impacted as part of renovations. Area does not increase hydraulic demands of Building

77.

1.4 SUBMITTALS

A. Submit as one package in accordance with Section 01 33 23, SHOP

DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detailed working drawings that are signed by a NICET Level III or Level IV Sprinkler Technician or stamped by a Registered Professional Engineer licensed in the field of Fire Protection Engineering. As the Government review is for technical adequacy only, the installer remains responsible for

21 13 13 - 2 correcting any conflicts with other trades and building construction that arise during installation. Partial submittals will not be accepted. Material submittals shall be approved prior to the purchase or delivery to the job site. Suitably bind submittals in notebooks or binders and provide an index referencing the appropriate specification section. In addition to the hard copies, provide submittal items in

Paragraphs 1.4(A)1 through 1.4(A)5 electronically in pdf format on a compact disc or as directed by the COR. Submittals shall include, but not be limited to, the following:

1. Qualifications:

a. Provide a copy of the installing contractors fire sprinkler and state contractor’s license.

b. Provide a copy of the NICET certification for the NICET Level III or Level IV Sprinkler Technician who prepared and signed the detailed working drawings unless the drawings are stamped by a

Registered Professional Engineer licensed in the field of Fire

Protection Engineering.

c. Provide documentation showing that the installer has been actively and successfully engaged in the installation of commercial automatic sprinkler systems for the past ten years.

2. Drawings: Submit detailed 1:100 (1/8 inch) scale (minimum) working drawings conforming to the Plans and Calculations chapter of NFPA

13. Drawings shall include graphical scales that allow the user to determine lengths when the drawings are reduced in size. Include a plan showing the piping to the water supply test location.

3. Manufacturer’s Data Sheets: Provide data sheets for all materials and equipment proposed for use on the system. Include listing information and installation instructions in data sheets. Where data sheets describe items in addition to those proposed to be used for the system, clearly identify the proposed items on the sheet.

4. Final Document Submittals: Provide as-built drawings, testing and maintenance instructions in accordance with the requirements in

Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. In addition, submittals shall include, but not be limited to, the following:

a. A complete set of as-built drawings showing the installed system with the specific interconnections between the system switches and the fire alarm equipment. Provide a complete set in the

21 13 13 - 3 formats as follows. Submit items 2 and 3 below on a compact disc or as directed by the COR.

1) One full size (or size as directed by the COR) printed copy.

2) One complete set in electronic pdf format.

3) One complete set in AutoCAD format or a format as directed by the COR.

b. Material and Testing Certificate: Upon completion of the sprinkler system installation or any partial section of the system, including testing and flushing, provide a copy of a completed Material and Testing Certificate as indicated in NFPA

13. Certificates shall be provided to document all parts of the installation.

c. Operations and Maintenance Manuals that include step-by-step procedures required for system startup, operation, shutdown, and routine maintenance and testing. The manuals shall include the manufacturer's name, model number, parts list, and tools that should be kept in stock by the owner for routine maintenance, including the name of a local supplier, simplified wiring and controls diagrams, troubleshooting guide, and recommended service organization, including address and telephone number, for each item of equipment.

d. One paper copy of the Material and Testing Certificates and the

Operations and Maintenance Manuals above shall be provided in a binder. In addition, these materials shall be provided in pdf format on a compact disc or as directed by the COR.

e. Provide one additional copy of the Operations and Maintenance

Manual covering the system in a flexible protective cover and mount in an accessible location adjacent to the riser or as directed by the COR.

1.5 QUALITY ASSURANCE

A. Installer Reliability: The installer shall possess a valid State fire sprinkler contractor's license. The installer shall have been actively and successfully engaged in the installation of commercial automatic sprinkler systems for the past ten years.

B. Materials and Equipment: All equipment and devices shall be of a make and type listed by UL or approved by FM, or other nationally recognized testing laboratory for the specific purpose for which it is used. All materials, devices, and equipment shall be approved by the VA. All

21 13 13 - 4 materials and equipment shall be free from defect. All materials and equipment shall be new unless specifically indicated otherwise on the contract drawings.

1.6 APPLICABLE PUBLICATIONS

A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.

B. National Fire Protection Association (NFPA):

13-19 ..................Installation of Sprinkler Systems

25-20 ..................Inspection, Testing, and Maintenance of Water-

Based Fire Protection Systems

101-21 .................Life Safety Code

170-21 .................Fire Safety Symbols

C. Underwriters Laboratories, Inc. (UL):

Fire Protection Equipment Directory (2011)

D. Factory Mutual Engineering Corporation (FM):

Approval Guide

PART 2 - PRODUCTS

2.1 PIPING & FITTINGS

A. Piping and fittings for sprinkler systems shall be in accordance with

NFPA 13.

1. Plain-end pipe fittings with locking lugs or shear bolts are not permitted.

2. Piping sizes 50 mm (2 inches) and smaller shall be black steel

Schedule 40 with threaded end connections.

3. Piping sizes 65 mm (2 ½ inches) and larger shall be black steel

Schedule 10 with grooved connections. Grooves in Schedule 10 piping shall be rolled grooved only.

4. Plastic piping shall not be permitted except for drain piping.

5. Flexible sprinkler hose shall be FM Approved and limited to hose with threaded end fittings with a minimum inside diameter or 1-inch and a maximum length of 6-feet.

2.2 SPRINKLERS

A. All sprinklers shall be FM approved quick response. Provide FM approved quick response sprinklers in all areas, except that standard response sprinklers.

B. Temperature Ratings: In accordance with NFPA 13.

21 13 13 - 5

2.3 SPRINKLER CABINET

A. Provide sprinkler heads of all ratings and types installed in existing sprinkler cabinet located in G003 – Utility Room.

2.4 PIPE HANGERS, SUPPORTS AND RESTRAINT OF SYSTEM PIPING

A. Pipe hangers, supports, and restraint of system piping shall be in accordance with NFPA 13.

2.5 WALL, FLOOR AND CEILING PLATES

A. Provide chrome plated steel escutcheon plates.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Installation shall be accomplished by the licensed contractor. Provide a qualified technician, experienced in the installation and operation of the type of system being installed, to supervise the installation and testing of the system.

B. Installation of Piping: Accurately cut pipe to measurements established by the installer and work into place without springing or forcing.

Concealed piping in spaces that have finished ceilings. Piping shall not obstruct the minimum means of egress clearances required by NFPA

101. Pipe hangers, supports, and restraint of system piping, shall be installed accordance with NFPA 13.

C. Affix cutout disks, which are created by cutting holes in the walls of pipe for flow switches and non-threaded pipe connections to the respective waterflow switch or pipe connection near to the pipe from where they were cut.

D. Provide escutcheon plates for exposed piping passing through walls, floors, or ceilings.

E. Sleeves: Provide for pipes passing through masonry or concrete. Provide space between the pipe and the sleeve in accordance with NFPA 13. Seal this space with a UL Listed through penetration fire stop material in accordance with Section 07 84 00, FIRESTOPPING. Where core drilling is used in lieu of sleeves, also seal space. Seal penetrations of walls, floors and ceilings of other types of construction, in accordance with

Section 07 84 00, FIRESTOPPING.

F. Firestopping shall be provided for all penetrations of fire resistance rated construction. Firestopping shall comply with Section 07 84 00, FIRESTOPPING.

21 13 13 - 6

G. Painting of Pipe: In finished areas where walls and ceilings have been painted, paint primed surfaces with two coats of paint to match adjacent surfaces, except paint valves and operating accessories with two coats of gloss red enamel. Exercise care to avoid painting sprinklers. Painting of sprinkler systems above suspended ceilings and in crawl spaces is not required. Painting shall comply with Section 09

91 00, PAINTING. Any painted sprinkler shall be replaced with a new sprinkler.

H. Repairs: Repair damage to the building or equipment resulting from the installation of the sprinkler system by the installer at no additional expense to the Government.

I. Interruption of Service: There shall be no interruption of the existing sprinkler protection, water, electric, or fire alarm services without prior permission of the Contracting Officer. Contractor shall develop an interim fire protection program where interruptions involve occupied spaces. Request in writing at least one week prior to the planned interruption.

3.2 INSPECTION AND TEST

A. Prior to the start of sprinkler system scope upgrades, hydrostatically test existing fire suppression system throughout area.

B. Preliminary Testing: Flush newly installed systems prior to performing hydrostatic tests in order to remove any debris which may have been left as well as ensuring piping is unobstructed. Hydrostatically test system, as specified in NFPA 13, in the presence of the Contracting

Officers Representative (COR) or his designated representative.

C. Final Inspection and Testing: Subject system to tests in accordance with NFPA 13, and when all necessary corrections have been accomplished, advise COR to schedule a final inspection and test.

Connection to the fire alarm system shall have been in service for at least ten days prior to the final inspection, with adjustments made to prevent false alarms. Furnish all instruments, labor and materials required for the tests and provide the services of the installation foreman or other competent representative of the installer to perform the tests. Correct deficiencies and retest system as necessary, prior to the final acceptance. Include the operation of all features of the systems under normal operations in test.

23 05 11 - 1

SECTION 23 05 11

COMMON WORK RESULTS FOR HVAC

PART 1 - GENERAL

1.1 DESCRIPTION

A. The requirements of this Section apply to all sections of Division 23.

B. Definitions:

1. Exposed: Piping, ductwork, and equipment exposed to view in finished rooms.

2. Exterior: Piping, ductwork, and equipment exposed to weather be it temperature, humidity, precipitation, wind, or solar radiation.

C. Abbreviations/Acronyms:

1. ac: Alternating Current

2. AC: Air Conditioning

3. ACU: Air Conditioning Unit

4. ACR: Air Conditioning and Refrigeration

5. AI: Analog Input

6. AISI: American Iron and Steel Institute

7. AO: Analog Output

8. ASJ: All Service Jacket

9. AWG: American Wire Gauge

10. BACnet: Building Automation and Control Networking Protocol

11. BAg: Silver-Copper-Zinc Brazing Alloy

12. BAS: Building Automation System

13. BCuP: Silver-Copper-Phosphorus Brazing Alloy

14. bhp: Brake Horsepower

15. Btu: British Thermal Unit

16. Btu/h: British Thermal Unit Per Hour

17. CDA: Copper Development Association

18. C: Celsius

19. CD: Compact Disk

20. CFM: Cubic Foot Per Minute

21. CH: Chilled Water Supply

22. CHR: Chilled Water Return

23. CLR: Color

24. CO: Carbon Monoxide

25. COR: Contracting Officer’s Representative

26. CPD: Condensate Pump Discharge

27. CPM: Cycles Per Minute

23 05 11 - 2

28. CPVC: Chlorinated Polyvinyl Chloride

29. CRS: Corrosion Resistant Steel

30. CTPD: Condensate Transfer Pump Discharge

31. CTPS: Condensate Transfer Pump Suction

32. CW: Cold Water

33. CWP: Cold Working Pressure

34. CxA: Commissioning Agent

35. dB: Decibels

36. dB(A): Decibels (A weighted)

37. DDC: Direct Digital Control

38. DI: Digital Input

39. DO: Digital Output

40. DVD: Digital Video Disc

41. DN: Diameter Nominal

42. DWV: Drainage, Waste and Vent

43. EPDM: Ethylene Propylene Diene Monomer

44. EPT: Ethylene Propylene Terpolymer

45. ETO: Ethylene Oxide

46. F: Fahrenheit

47. FAR: Federal Acquisition Regulations

48. FD: Floor Drain

49. FED: Federal

50. FG: Fiberglass

51. FGR: Flue Gas Recirculation

52. FOS: Fuel Oil Supply

53. FOR: Fuel Oil Return

54. FSK: Foil-Scrim-Kraft facing

55. FWPD: Feedwater Pump Discharge

56. FWPS: Feedwater Pump Suction

57. GC: Chilled Glycol Water Supply

58. GCR: Chilled Glycol Water Return

59. GH: Hot Glycol Water Heating Supply

60. GHR: Hot Glycol Water Heating Return

61. gpm: Gallons Per Minute

62. HDPE: High Density Polyethylene

63. Hg: Mercury

64. HOA: Hands-Off-Automatic

65. hp: Horsepower

23 05 11 - 3

66. HPS: High Pressure Steam (414 kPa (60 psig) and above)

67. HPR: High Pressure Steam Condensate Return

68. HW: Hot Water

69. HWH: Hot Water Heating Supply

70. HWHR: Hot Water Heating Return

71. Hz: Hertz

72. ID: Inside Diameter

73. IPS: Iron Pipe Size

74. kg: Kilogram

75. klb: 1000 lb

76. kPa: Kilopascal

77. lb: Pound

78. lb/hr: Pounds Per Hour

79. L/s: Liters Per Second

80. L/min: Liters Per Minute

81. LPS: Low Pressure Steam (103 kPa (15 psig) and below)

82. LPR: Low Pressure Steam Condensate Gravity Return

83. MAWP: Maximum Allowable Working Pressure

84. MAX: Maximum

85. MBtu/h: 1000 Btu/h

86. MBtu: 1000 Btu

87. MED: Medical

88. m: Meter

89. MFG: Manufacturer

90. mg: Milligram

91. mg/L: Milligrams Per Liter

92. MIN: Minimum

93. MJ: Megajoules

94. ml: Milliliter

95. mm: Millimeter

96. MPS: Medium Pressure Steam (110 kPa (16 psig) through 414 kPa (60 psig))

97. MPR: Medium Pressure Steam Condensate Return

98. MW: Megawatt

99. NC: Normally Closed

100. NF: Oil Free Dry (Nitrogen)

101. Nm: Newton Meter

102. NO: Normally Open

23 05 11 - 4

103. NOx: Nitrous Oxide

104. NPT: National Pipe Thread

105. NPS: Nominal Pipe Size

106. OD: Outside Diameter

107. OSD: Open Sight Drain

108. OS&Y: Outside Stem and Yoke

109. PC: Pumped Condensate

110. PID: Proportional-Integral-Differential

111. PLC: Programmable Logic Controllers

112. PP: Polypropylene

113. PPE: Personal Protection Equipment

114. ppb: Parts Per Billion

115. ppm: Parts Per Million

116. PRV: Pressure Reducing Valve \

117. PSIA: Pounds Per Square Inch Absolute

118. psig: Pounds Per Square Inch Gauge

119. PTFE: Polytetrafluoroethylene

120. PVC: Polyvinyl Chloride

121. PVDC: Polyvinylidene Chloride Vapor Retarder Jacketing, White

122. PVDF: Polyvinylidene Fluoride

123. rad: Radians

124. RH: Relative Humidity

125. RO: Reverse Osmosis

126. rms: Root Mean Square

127. RPM: Revolutions Per Minute

128. RS: Refrigerant Suction

129. RTD: Resistance Temperature Detectors

130. RTRF: Reinforced Thermosetting Resin Fittings

131. RTRP: Reinforced Thermosetting Resin Pipe

132. SCFM: Standard Cubic Feet Per Minute

133. SPEC: Specification

134. SPS: Sterile Processing Services

135. STD: Standard

136. SDR: Standard Dimension Ratio

137. SUS: Saybolt Universal Second

138. SW: Soft water

139. SWP: Steam Working Pressure

140. TAB: Testing, Adjusting, and Balancing

23 05 11 - 5

141. TDH: Total Dynamic Head

142. TEFC: Totally Enclosed Fan-Cooled

143. TFE: Tetrafluoroethylene

144. THERM: 100,000 Btu

145. THHN: Thermoplastic High-Heat Resistant Nylon Coated Wire

146. THWN: Thermoplastic Heat & Water-Resistant Nylon Coated Wire

147. T/P: Temperature and Pressure

148. USDA: U.S. Department of Agriculture

149. V: Volt

150. VAC: Vacuum

151. VA: Veterans Administration

152. VAC: Voltage in Alternating Current

153. VA CFM: VA Construction & Facilities Management

154. VA CFM CSS: VA Construction & Facilities Management, Consulting

Support Service

155. VAMC: Veterans Administration Medical Center

156. VHA OCAMES: Veterans Health Administration – Office of Capital

Asset Management Engineering and Support

157. VR: Vacuum condensate return

158. WCB: Wrought Carbon Steel, Grade B

159. WG: Water Gauge or Water Column

160. WOG: Water, Oil, Gas

1.2 RELATED WORK

A. Section 01 00 00, GENERAL REQUIREMENTS.

B. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

C. Section 01 74 19, CONSTRUCTION WASTE MANAGEMENT.

D. Section 01 91 00, GENERAL COMMISSIONING REQUIREMENTS.

E. Section 07 84 00, FIRESTOPPING.

F. Section 07 92 00, JOINT SEALANTS.

G. Section 09 91 00, PAINTING.

H. Section 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL

COMPONENTS.

I. Section 23 05 12, GENERAL MOTOR REQUIREMENTS FOR HVAC and STEAM

GENERATION.

J. Section 23 05 41, NOISE AND VIBRATION CONTROL FOR HVAC PIPING and

EQUIPMENT.

K. Section 23 05 93, TESTING, ADJUSTING, AND BALANCING FOR HVAC.

L. Section 23 07 11, HVAC AND BOILER PLANT INSULATION.

23 05 11 - 6

M. Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.

N. Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC.

O. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.

P. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES.

1.3 APPLICABLE PUBLICATIONS

A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only. Where conflicts occur these specifications and the VHA standard will govern.

B. Air Movement and Control Association (AMCA):

410-1996 ...............Recommended Safety Practices for Users and

Installers of Industrial and Commercial Fans

C. American Society of Mechanical Engineers (ASME):

B31.1-2018 .............Power Piping

B31.9-2014 .............Building Services Piping

ASME Boiler and Pressure Vessel Code:

BPVC Section IX-2019 Welding, Brazing, and Fusing Qualifications

D. American Society for Testing and Materials (ASTM):

A36/A36M-2014 ..........Standard Specification for Carbon Structural

Steel

A575-1996(R2018) .......Standard Specification for Steel Bars, Carbon, Merchant Quality, M-Grades

E. Association for Rubber Products Manufacturers (ARPM):

IP-20-2015 .............Specifications for Drives Using Classical

V-Belts and Sheaves

IP-21-2016 .............Specifications for Drives Using Double-V

(Hexagonal) Belts

IP-24-2016 .............Specifications for Drives Using Synchronous

Belts

IP-27-2015 .............Specifications for Drives Using Curvilinear

Toothed Synchronous Belts

F. Manufacturers Standardization Society (MSS) of the Valve and Fittings

Industry, Inc.:

SP-58-2018 .............Pipe Hangers and Supports-Materials, Design, Manufacture, Selection, Application, and

Installation

SP-127-2014a ...........Bracing for Piping Systems: Seismic–Wind–

Dynamic Design, Selection, and Application

23 05 11 - 7

G. Military Specifications (MIL):

MIL-P-21035B-2013 .....Paint High Zinc Dust Content, Galvanizing

Repair (Metric)

H. National Fire Protection Association (NFPA):

70-2017 ...............National Electrical Code (NEC)

101-2018 ..............Life Safety Code

I. Department of Veterans Affairs (VA):

PG-18-10-2016 .........Physical Security and Resiliency Design Manual

1.4 SUBMITTALS

A. Submittals, including number of required copies, shall be submitted in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND

SAMPLES.

B. Information and material submitted under this section shall be marked

“SUBMITTED UNDER SECTION 23 05 11, COMMON WORK RESULTS FOR HVAC”, with applicable paragraph identification.

C. If the project is phased submit complete phasing plan/schedule with manpower levels prior to commencing work. The phasing plan shall be detailed enough to provide milestones in the process that can be verified.

D. Contractor shall make all necessary field measurements and investigations to assure that the equipment and assemblies will meet contract requirements, and all equipment that requires regular maintenance, calibration, etc are accessable from the floor or permanent work platform. It is the Contractor’s responsibility to ensure all submittals meet the VA specifications and requirements and it is assumed by the VA that all submittals do meet the VA specifications unless the Contractor has requested a variance in writing and approved by COR prior to the submittal. If at any time during the project it is found that any item does not meet the VA specifications and there was no variance approval the Contractor shall correct at no additional cost or time to the Government even if a submittal was approved.

E. If equipment is submitted which differs in arrangement from that shown, provide documentation proving equivalent performance, design standards and drawings that show the rearrangement of all associated systems.

Additionally, any impacts on ancillary equipment or services such as foundations, piping, and electrical shall be the Contractor’s responsibility to design, supply, and install at no additional cost or

23 05 11 - 8 time to the Government. VA approval will be given only if all features of the equipment and associated systems, including accessibility, are equivalent to that required by the contract.

F. Prior to submitting shop drawings for approval, Contractor shall certify in writing that manufacturers of all major items of equipment have each reviewed contract documents and have jointly coordinated and properly integrated their equipment and controls to provide a complete and efficient installation.

G. Submittals and shop drawings for interdependent items, containing applicable descriptive information, shall be furnished together.

Coordinate and properly integrate materials and equipment to provide a completely compatible and efficient installation.

H. Coordination/Shop Drawings:

1. Submit complete consolidated and coordinated shop drawings for all new systems, and for existing systems that are in the same areas.

2. The coordination/shop drawings shall include plan views, elevations and sections of all systems and shall be on a scale of not less than 1:32 (3/8-inch equal to one foot). Clearly identify and dimension the proposed locations of the principal items of equipment. The drawings shall clearly show locations and adequate clearance for all equipment, piping, valves, control panels and other items. Show the access means for all items requiring access for operations and maintenance. Provide detailed coordination/shop drawings of all piping and duct systems. The drawings should include all lockout/tagout points for all energy/hazard sources for each piece of equipment. Coordinate lockout/tagout procedures and practices with local VA requirements.

3. Do not install equipment foundations, equipment or piping until coordination/shop drawings have been approved.

4. In addition, for HVAC systems, provide details of the following:

a) Mechanical equipment rooms.

b) Hangers, inserts, supports, and bracing.

c) Pipe sleeves.

d) Duct or equipment penetrations of floors, walls, ceilings, or roofs.

I. Manufacturer's Literature and Data: Include full item description and optional features and accessories. Include dimensions, weights, materials, applications, standard compliance, model numbers, size, and

23 05 11 - 9 capacity. Submit under the pertinent section rather than under this section.

1. Submit belt drive with the driven equipment. Submit selection data for specific drives when requested by the COR.

2. Submit electric motor data and variable speed drive data with the driven equipment.

3. Equipment and materials identification.

4. Fire-stopping materials.

5. Hangers, inserts, supports and bracing. Provide complete stress analysis for variable spring and constant support hangers.

6. Wall, floor, and ceiling plates.

J. Rigging Plan: Provide documentation of the capacity and weight of the rigging and equipment intended to be used. The plan shall include the path of travel of the load, the staging area and intended access, and qualifications of the operator and signal person.

K. HVAC Maintenance Data and Operating Instructions:

1. Maintenance and operating manuals in accordance with Section 01 00

00, GENERAL REQUIREMENTS, Article, INSTRUCTIONS, for systems and equipment.

2. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide:

a) Include complete list indicating all components of the systems.

b) Include complete diagrams of the internal wiring for each item of equipment.

c) Diagrams shall have their terminals identified to facilitate installation, operation…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .