60_17140186 PRICE PROPOSAL FORM .pdf

PDF 127 KB Posted

Attached to
Design/Build Construction for Recapitalize Central Steam Distribution System at USCG Academy, New London, CT
Solicitation number
70Z04724RPCNI0009
Issued by

About this file

This document is a Price Proposal Form for a Design/Build Construction contract to recapitalize the central steam distribution system at the U.S. Coast Guard Academy in New London, CT. The project includes replacing steam and condensate piping throughout the campus, repairing manholes, providing concrete stairs, trench drains, mechanical ventilation, and coordinating with other contractors.

The Base Item covers the core scope of work, with Option Items 0001, 0002, and 0003 providing additional design-build work for specific sections of steam and condensate piping, mechanical rooms, and other areas. Contractors must provide pricing for the Design and Construction phases, as well as the total price for the Base Item and Option Items. This opportunity is posted exclusively for contractors on the current DHS/USCG National Multiple Award Construction Contract III (NMACC III) - Pool 1.

View the file

Other files

File Type Posted
SF30 70Z04725RPCNI0009_0006.pdf PDF
TOSI_70Z04724RPCNI0009 Academy Steam_Final.pdf PDF
Past performance Questionnaire.docx.pdf PDF
Additional Information for Amend 0004 USCG Academy Steam 70Z04724RPCNI009.pdf PDF
Attachment 12 - Historic Resources Inventory and Determination of Eligibility Report - 1996.pdf PDF
Attachment 13 - Confined Space ID and Entry Program.pdf PDF
Attachment 11 - ICAM - USCG Academy.pdf PDF
Amendment 0004 USCG Academy Steam 70Z04724RPCNI0009.pdf PDF
Attachment 10 - USCGA MS4 Permit.pdf PDF
Revised Price Proposal Form 70Z04724RPCNI0009.pdf PDF
RFI Responses 70Z04724RPCNI0009_Academy Steam.pdf PDF
NMACC III Contract Terms.pdf PDF
Amend 0003 USCG Academy Steam 70Z04725RPCNI0009.pdf PDF
SF30 Amend 0002 USCG Academy.pdf PDF
Site Visit Attendance Log Academy Steam_V1.pdf PDF
SF30 Amend 0001 USCG Academy.pdf PDF
TOA_DB_USCGA Steam _ Final.pdf PDF
Appendix B - Final Testing and Balancing Report.pdf PDF
Appendix E - Drawing Standards and Management CSTO.pdf PDF
RFP Specs 60_17140186 USCGA Steam.pdf PDF
Appendix F - Design Narrative.docx DOCX document
Appendix A - Equip Enroll Matrix_SILC Catalog 2024.xlsx XLSX spreadsheet
Appendix D - Drawing Format and Handling _Job Guide.pdf PDF
Appendix C - Final Lead and Asbestos Survey.pdf PDF
Wage Determination_ CT 20230034 dtd 8_9_2024.pdf PDF
60_17140186 USCGA CF Drawings.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRICE PROPOSAL FORM

Recapitalize Central Steam Distribution System CGA

PROJECT 60-17140186

TASK ORDER ANNOUNCEMENT #: 70Z04724RPCNI0009

Overall project description – Project includes replacing steam and condensate piping throughout the

USCG Academy. The steam and condensate piping are either located in a tunnel, passageway or direct buried. The steam and condensate piping has been prioritized and divided into BASE and OPTIONS.

See RFP Drawing Sheet G-002 and G-003 as well as Section 1800.1.1-1.3. Steam lines are noted by a respective “section number”. Section numbers are designated by a number callout. However, some sections are designated by a number followed by a letter. For example. “Section 5D-10C”. This section starts outside near Leamy Hall and terminates in the Chase C Mechanical Room. Remove all unused steam and condensate piping (abandoned).

Engage with Field Turf Point of Contact and Siemens Controls for respective work.

Base Item: Replace steam and condensate piping as indicated by section number. Repair Manhole #5 and Manhole #6. Provide concrete stairs to access the Manhole #6 door near Leamy Hall. Provide trench drains to existing tunnel Section 7-8. Provide mechanical ventilation for tunnels, electrical work, lighting, and doors. Coordinate with Field Turf regarding the removal / reinstallation of artificial turf and drainage near Cadet Field (football field). Provide all labor, material, equipment, mobilization, demobilization, permitting, construction support, quality control services, selected demolition, lead and asbestos abatement, and ancillary items required for site development and construction, excluding items identified in Option Items.

Design Price: $______________________

Construction Price: $______________________

TOTAL BASE: $____________________

The TOTAL BASE ITEMS shall be deemed to include all costs required for the specified work to be completed in accordance with the plans and specifications.

Option Item 0001: Design-Build Price – Steam and condensate piping (various section #s)

Provide all labor, material, equipment, mobilization, demobilization, permitting, construction support, quality control services, and ancillary items required.

TOTAL OPTION 0001: $____________________

Option Item 0002: Design-Build Price – Mechanical Rooms

Option 0002 applies specific to the Mechanical Rooms at Chase B Annex, Michel Hall, and Billard

Hall. The specific boundaries of the mechanical drawings are shown on the RFP Drawings. See scope of work on Electrical and Mechanical sheets 400 series and sheet M-600 for select equipment. Replace all steam / condensate piping and hot water supply / return piping within the indicated mechanical room boundaries. Scope of work includes all hydronic specialties, Siemens Controls, heat exchangers, pumps, steam control valves, painting, pressure reducing stations, and exhaust fans, piping supports, and all appurtenances complete. Remove all unused steam and condensate piping (abandoned).

Provide all labor, material, equipment, mobilization, demobilization, permitting, lead and asbestos abatement, construction support, quality control services, and ancillary items required related to

Mechanical Rooms.

TOTAL OPTION 0002: $____________________

Option Item 0003: Design-Build Price – Steam and condensate piping (various section #s)

Provide all labor, material, equipment, mobilization, demobilization, permitting, construction support, quality control services, and ancillary items required.

TOTAL OPTION 0003: $____________________

TOTAL PRICE

(Base Line Item 0001 and Option Line Items 0001, 0002, and 0003 ): $__________________