Addendum and Acknowledgment Doc F-STAr.doc
DOC document 250 KB Posted
- Attached to
- REVISED Flow Sensor Test Article (F-STAr) pump
- Solicitation number
- 4-B176-Q-00517-00
- Issued by
-
Department of Energy Office of Science
About this file
This document is an Addendum and Acknowledgement for Request for Quotation (RFQ) No. 4-B176-Q-00517-00 issued by Argonne National Laboratory for a Flow Sensor Test Article (F-STAr) pump. The addendum extends the offer deadline to 5:00pm CDT on 08/19/2024 and provides responses to 29 questions related to the technical specifications, including preferred discharge line size, flange type, motor speed, cooling requirements, materials, and testing. The pump will be installed in Argonne National Laboratory's Mechanisms Engineering Test Loop (METL) to support sodium-cooled nuclear reactor development. The evaluation will be based on lowest price and technical acceptability. The solicitation requires the contractor to design, fabricate, test, and deliver the pump in accordance with the technical and quality assurance requirements specified in the document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum and Acknowledgement Doc.doc | DOC document | |
| Enclosure 1 Instructions to Offerors_G4-135011.doc | DOC document | |
| Enclosure 2 ANL-70 Request for Quotation.doc | DOC document | |
| Enclosure 4 Specifications and Statement of Work.pdf | ||
| Enclosure 3 FSTAR Pump Supplier Evaluation Criteria rv6.pdf | ||
| G14642XD-2 REV01.pdf | ||
| G14642XD-1 REV01.pdf | ||
| Addendum and Acknowledgement Doc 2.doc | DOC document | |
| Appendix A-71COM-13-FEB-2023.PDF | ||
| Enclosure 4 Specification Document.pdf | ||
| Enclosure 1 Instructions to Offerors_G4-135011.doc | DOC document | |
| Addendum and Acknowledgement Doc.doc | DOC document | |
| Enclosure 2 ANL-70 Request for Quotation.doc | DOC document | |
| Enclosure 3 Evaluation Criteria.pdf | ||
| Specification Document.pdf | ||
| ANL-70 Request for Quotation.doc | DOC document | |
| G14642XD-2 REV00.pdf | ||
| Reps Certs ANL-70B (Blank).doc | DOC document | |
| G14642XD-1 REV00.pdf |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MOLLY MURTAUGH
Procurement Specialist 2 Office of the Chief Financial Officer
Procurement Department
Argonne National Laboratory
9700 South Cass Avenue, Bldg. 201
Lemont, IL 60439
(630)252-3094 mmurtaugh@anl.gov
TO ALL OFFERORS:
Subject:
Request for FORMDROPDOWN No. 4-B176-Q-00517-00 Addendum No. 01 Attached herewith for your information and use in preparing your proposal for subject project is one (1) copy of Addendum No. 01.
Kindly acknowledge receipt of this Addendum by signing and returning one (1) copy of this letter.
Please email a signed copy of this letter to mmurtaugh@anl.gov with the final proposal.
Sincerely, MOLLY MURTAUGH
Procurement Specialist 3
Procurement Department
Receipt Acknowledged:
Company:
By:
cc:
File
CF
Addendum No.
TO
REQUEST FOR FORMDROPDOWN
4-B176-Q-00517-00
FOR
Argonne National Laboratory
BLDG. 201 OCF
9700 S. Cass Ave.
Lemont, IL 60439
08/13/2024 This addendum is being issued to modify the subject REQUEST FOR Quotation (RFQ) 4-B176-Q-00517-00 as follows:
Offer deadline extended to 5:00pm CDT on 08/19/2024.
Q&A responses below:
1. What are the liquid levels in the tank.
i. Maximum 25.25”per dwg G24642XD-2
ii. Minimum
iii. Normal operating
· The maximum and normal operating liquid levels are the top line (25.25” for the 9.5” opening, and 28.75” for the 11.5” opening). The minimum level can be set by minimum level needed for the specified pump submergence depth.
2. Do you need a certain discharge line size?
· We prefer 1.5” Sch 40. But we can size up or down if needed.
3. What type of flange connection do you need on the discharge line?
· We prefer a Grayloc hub or butt weld end.
4. What is your preference on the 9.5” opening vs the 11.5” opening?
· Our preference is the 9.5” opening as it will require less modifications to our current system. However, the 11.5” opening is available if needed.
5. What speed would you prefer to operate at: 1800, 3600 rpm
· No preference.
6. Do you have motor specifications and a preferred manufacturer?
· We would like the motor to be inverter duty and controlled by a VFD.
7. What Voltage motor do you prefer?
· 480VAC preferred but 240VAC is acceptable.
8. Do you want a VFD for the motor?
· Yes.
9. Can the pump have one or more submerged radial bearings?
· Submerged hydrodynamic bearings are ok. Mechanical bearings are not preferred due to low lifetimes in liquid sodium.
10. Do you want tapped locations for vibration monitors?
· Yes. At least one located above the flange.
11. Do you want locations and ports for thermal couples?
· Yes. TC located out the discharge and TCs located at bearings.
12. Do you want cooling fins to mitigate the radiant heat from the liquid sodium?
· Cooling can be added as necessary to prevent the bearings or other temperature sensitive components from overheating. We prefer gas cooling (air or other). Liquid cooling is acceptable if measures are included to prevent/contain leaks (design subject to review).
13. What materials are acceptable as bushings in the sodium?
· Refer to “Sodium--NaK engineering handbook. Volume IV. Sodium pumps, valves, piping, and auxiliary equipment” (https://www.osti.gov/biblio/6278134) page 49-91 (PDF page 30-51) for information on sodium-bearing materials.
14. Is graphite acceptable for the gas control bushing in the cooling chamber?
· Graphite is acceptable for sealing in the gas spaces. It is required that measures be added to prevent graphite debris from entering and contaminating the fluid.
15. Is a mag-drive unit acceptable?
· Yes.
16. Is a cooling chamber below the trust bearing acceptable?
· Yes. We prefer gas cooling. Liquid cooling is acceptable if measures are included to prevent/contain leaks (design subject to review).
17. What are your operational modes for testing?
· We would prefer to operate the pump using a VFD to control the speed/flowrate. We would like to operate the pump between the entire range of minimum and maximum permissible speeds. If certain speeds shall be excluded then that must be noted.
18. What are the temperature transients vs time we might see?
· We intend to operate the pump at steady state or long transients (~1 C/min). Transient limits should be noted and we will restrict operation of our system.
19. How soon do you need a pump?
· As soon as feasible.
20. Do we quote spare parts?
· Quote consumable spare parts that are not off-the-shelf or have long lead times (e.g. bushings, wear rings, bearings, etc).
21. Do we quote commission services?
· Can quote commissioning services as a separate line but are not required. Please indicate whether commissioning services are offered in the future if needed.
22. Will witnessed testing be required?
· Yes.
23. Other than base line performance testing (flow, head, amps), vibration and bearing temperature, what will be required?
· The testing listed above is sufficient. No additional testing required.
24. Will any additional ports be required in the pump mounting flange? CONTRACTOR recommends N2 port for cooling fins
· Ports can be added as specified by the design. Ports shall be leak tight to prevent gas in tank from escaping. Additionally, the cooling gas must be segregated from the tank gas. The tank gas will have sodium vapors and we cannot vent these directly to the atmosphere.
25. Is SimScale Full FEA (linear, nonlinear, thermomechanical, dynamic) and CFD (compressible, incompressible, conjugate HT, radiation) acceptable for section 7.3.2.
· Yes.
26. Will drawings generated in Auto Desk Inventor 2024 be acceptable.
· Yes.
27. CONTRACTOR is not ISO 9001 certified. Will this be a Problem for ANL?
· No. If a QC plan exists but is not ISO 9001 certified, please provide a brief description. If no QC plan exists please note.
28. Is the tank material?
· 304H.
29. What is the fastener materials used to bolt the pump to the tank flange?
· Stainless.