G-110_2023.01.18.pdf
PDF 825 KB Posted
- Attached to
- Lobby Security Upgrades Keating Federal Building Construction Project Federal contract opportunity
- Solicitation number
- 47PC0222R0025
About this file
This is a solicitation for a construction project to renovate the lobby of the Kenneth B. Keating Federal Building in Rochester, NY. The base bid work includes modifications to planters, security fences and gates, structural improvements to columns G4 and H4, provision of a temporary accessible public entrance, installation of a storefront and curtain wall system, construction of an airlock vestibule with accessible doors and a rotary door, ensuring a protected path for public entry and egress, modifying underground utilities, and constructing a security station, gun locker and storage room. The pre-bid site visit will be held on May 11, 2022. Questions are due by May 18, 2022 and bids are due June 1, 2022. The solicitation is being conducted by the General Services Administration Public Buildings Service Region 2.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P
P
P
P
P
P
P
P BENCH P BENCH P
P BENCH P
B E N C H
BENCHP P
B E N C H
B E N C H
B E N C H
P
B E N C H
B E N C H
B E N C H
P
P
S
STAIR
87 86 85 84 83 82 81 80
122 123
S U P E R V
IS
O R x
P
B E N C H
B E N C H
P
PEDESTRIAN ROUTE
PROPERTY LINE
EXISTING
LOADING
DOCK
POTENTIAL
DUMPSTER
AREA
EXISTING
PUBLIC
ENTRANCE -
CLOSED OFF
FROM PUBLIC
OR EMPLOYEE
ENTRY DURING
CONSTRUCTION
PROVIDE
TEMPORARY
SIGNAGE TO
DIRECT
EMPLOYEES
AND THE
PUBLIC AWAY
FROM THIS
ENTRANCE
TEMPORARY
PUBLIC
ENTRANCE
3 4 5 6 7
N
M
L
K
J
H
G
F
G-110
G-110
PROVIDE FULL HEIGHT
TEMPORARY BARRIER DURING
EXTERIOR WORK AND
DISRUPTIVE WORK TO THE
WEST OF THIS BARRIER.
PROVIDE TEMPORARY
BARRIER
PROVIDE LOCKABLE
DOOR
ROUGH OUTLINE OF
WORK AREA - NO
PUBLIC OR EMPLOYEE
ENTRANCE DURING
CONSTRUCTION
MODIFY EXISTING
SPACE FOR
TEMPORARY PUBLIC
ENTRANCE
PROVIDE TEMPORARY 6'-0"
TALL CHAIN LINK FENCE
WITH BALLASTED BASES
SWING GATE LEFT
UNLOCKED DURING
BUSINESS HOUR FOR
USE BY THE PUBLIC
PROVIDE TEMPORARY
SIGNAGE TO DIRECT PUBLIC
TO THE TEMPORARY
ENTRANCE
EXISTING STAIR FOR
PUBLIC ENTRANCE
EXISTING RAMP FOR
PUBLIC ENTRANCE
EXISTING STOREFRONT
OPENING LEFT UNLOCKED
DURING BUSINESS HOUR
FOR USE BY THE PUBLIC
8' - 0"
8' - 0"
/4
13' - 6" ±
13' - 2 1/2" ±
PROVIDE MOVABLE PARTITION
TO COMPLETE THE REMAINING
WORK OUTSIDE OF THE FULL
HEIGHT TEMPORARY BARRIER.
PROVIDE
LOCKABLE
DOOR
PROVIDE 42"
WIDE LOCKABLE
SWING GATE
PROVIDE 42"
WIDE
LOCKABLE
SWING GATE
G-100
1. ALL CONTRACTORS ARE RESPONSIBLE FOR MAKING THEIR WORKERS AWARE OF THE
PRESENCE OF IDENTIFIED AND SUSPECT ASBESTOS CONTAINING MATERIAL (ACM) SO THAT
THESE MATERIALS ARE NOT UNINTENTIONALLY DISTURBED. ANY DISTURBANCE TO ACM MUST
BE PERFORMED BY A LICENSED ASBESTOS ABATEMENT CONTRACTOR. REFER TO THE
ASBESTOS SURVEY AND ASSESSMENT REPORT DATED DECEMBER 28, 2015, AND THE REPORT
DATED JANUARY 25, 2018 FOR MORE INFORMATION AND COORDINATION REGARDING ACM
IDENTIFIED WITHIN THE PROJECT LIMITS.
2. ASBESTOS-CONTAINING MATERIALS IDENTIFIED IN THE REPORT SHALL BE ABATED PRIOR TO
ANY CONSTRUCTION OR CONSTRUCTION-RELATED ACTIVITIES THAT COULD DISTURB THESE
MATERIALS.
3. THE FOLLOWING ASBESTOS-CONTAINING MATERIAL(S) HAVE BEEN IDENTIFIED WITHIN THE
PROJECT AREAS: LOBBY - MUDDED JOINT PACKING ON DRAIN LINES AND DOMESTIC WATER
LINES ABOVE THE ACOUSTIC SUSPENDED CEILING PANELS – APPROXIMATELY 3 LOCATIONS.
4. IF UNANTICIPATED SUSPECT MATERIALS ARE IDENTIFIED DURING CONSTRUCTION (I.E. SUSPECT
ACM, PCBS, ETC.), CEASE OPERATIONS AND IMMEDIATELY NOTIFY THE OWNER OR THEIR
REPRESENTATIVE FOR FURTHER DIRECTION. UNDER NO CIRCUMSTANCES SHALL THE
CONTRACTOR COLLECT AND/OR ANALYZE BULK SAMPLES OF SUSPECT MATERIALS WITHOUT
THE APPROVAL OF THE OWNER OR THEIR REPRESENTATIVE.
1. ALL CONTRACTORS ARE RESPONSIBLE FOR MAKING THEIR WORKERS AWARE OF THE
PRESENCE OF IDENTIFIED AND SUSPECT LEAD CONTAINING MATERIAL (LCM) SO THAT THESE
MATERIALS ARE NOT UNINTENTIONALLY DISTURBED.
2. CONTRACTORS SHALL BE RESPONSIBLE FOR COMPLYING WITH OSHA 29 CFR 1926.62: LEAD
EXPOSURE IN CONSTRUCTION; INTERIM FINAL RULE FOR ALL ACTIVITIES DURING WHICH AN
EMPLOYEE MAY BE OCCUPATIONALLY EXPOSED TO LEAD.
3. NO TESTING HAS BEEN PERFORMED ON BUILDING COMPONENTS THAT WILL BE IMPACTED BY
THIS PROJECT TO DETERMINE IF THEY ARE COATED WITH LEAD-BASED PAINT.
4. FURNISHING OF THIS INFORMATION IS NOT INTENDED TO RELIEVE THE CONTRACTOR OF ITS
RESPONSIBILITIES UNDER OSHA TO DETERMINE THE PRESENCE, LOCATION, AND QUANTITY OF
EXISTING LEAD-CONTAINING MATERIALS THAT THEIR EMPLOYEES AND SUBCONTRACTORS
MAY BE EXPOSED TO, AND TO WARN THEIR EMPLOYEES OF THE POTENTIAL DANGERS OF THE
DISTURBANCE OF LEAD-CONTAINING MATERIALS.
N
M
REMOVE AND DISCARD EXISTING
SUSPENDED ACP CEILING SYSTEM
REMOVE AND DISCARD EXISTING
DOOR FRAME
REMOVE AND SALVAGE FOR
REINSTALLATION EXISTING
STOREFRONT FRAME, DOORS,
AND ALL ASSOCIATED HARDWARE
REMOVE EXISTING CMU
PARTITION SYSTEM TO THE
EXTENT SHOWN - FULL HEIGHT
ETR CABINET UNIT
HEATER
PROTECT EXISTING TO REMAIN
FIRE ALARM, LIGHT SWITCH,
CARD READER
INFRASTRUCTURE, AND
INTERCOM DURING REMOVALS.
RELOCATE
EXISTING
LIGHT
SWITCH
NOTES:
1. TEMPORARILY SUPPORT
SUSPENDED DEVICES, FIXTURES
AND EQUIPMENT INCLUDED BUT
NOT LIMITED TO LIGHT FIXTURES,
SPRINKLERS, ETC.
GRIND EDGE SMOOTH AND
PREPARE FOR FINISH
/8
STORAGE
CORRIDOR
VESTIBULE
REMOVE AND SALVAGE FOR
REINSTALLATION EXISTING DOOR
AND DOOR HARDWARE
N
M
3' - 6 1/2" 2' - 10"
2' - 0"
2' - 8 1/2"
MIN.
4' - 0" CLR
M
IN
2' X 4' TABLE
GUN LOCKER
CELL PHONE LOCKER
LOCK DOOR
TEMPORARILY
RELOCATE EXISTING
X-RAY MACHINE FOR
TEMPORARY USE
RELOCATE EXISTING
MAGNETOMETER FOR
TEMPORARY USE
PATCH FLOOR FLUSH
WITH ADJACENT
EXISTING FINISHED
FLOOR AT AREAS OF
REMOVED CMU
PARTITION AND
STOREFRONT OPENING
TEMPORARY PUBLIC
ENTRANCE AND
PUBLIC EXIT
CAP WITH S.S. CORNER
GUARD SUCH THAT NO
ROUGH MASONRY
EDGES ARE EXPOSED
PROVIDE SUSPENDED
ACOUSTIC CEILING
FRAMING AND PANELS -
PROVIDE PANEL CLIPS TO
SECURE PANELS IN PLACE.
LOCATE ETR LIGHTING
AND OTHER CEILING
MOUNTED ITEMS IN THE
TEMPORARY CEILING.
CEILING HEIGHT TO MATCH
EXISTING.
PATCH WALLS AT AREA
OF REMOVALS TO
RECEIVE PAINT TO
MATCH ADJACENT WALL
FINISH, TYPICAL
TEMPORARY
PUBLIC
ENTRANCE
T01
PROVIDE WALL BASE
PATCH AT AREAS OF
REMOVAL, TYPICAL
TO SLAB
BO STRUCTURE
TEMPORARY PARTITION TYPE:
UL U419 (NON-BEARING)
RATING 2 HOUR
STC 53
METAL STUD / SOUND INSULATION / GYPSUM WALL BOARD / BALLISTIC
6" 18 GAUGE CORROSION-
PROTECTED STEEL STUDS
AT 24" O.C. (MAX)
6" ACOUSTIC INSULATION
6" 18 GAUGE CORROSION-
PROTECTED STEEL
RUNNERS
(2) LAYER 1/2" TYPE X"
CEILING AS SCHEDULED
ACOUSTIC INSULATION
8"
PUBLIC CORRIDORWORK AREA
NOTES:
1. PROVIDE SEALANT AT ALL
JOINTS AND EDGES TO
PREVENT SOUND AND DUST
MITIGATION.
2. DRYWALL FINISH: WORK
AREA LEVEL 2; PUBLIC
CORRIDOR LEVEL 4 -
PAINTED (COLOR AS
SELECTED BY ARCHITECT).
SECURE ETR CEILING
SYSTEM TO TEMPORARY
PARTITION AS REQUIRED
3' - 0"
A F
F
A F
F
EQ EQ
1/2" THICK PAINTED FIRE
RETARDANT PLYWOOD, TYPICAL
CONTINUOUS 1/4" THICK PLEXI-
GLASS VISION PANEL - PRE-DRILL
HOLES & SCREW TO WOOD
STUDS, TYPICAL
FIRE RETARDANT 2"X4" WOOD
STUDS @ 16" O.C., TYPICAL
NOTE:
PROTECT ETR TERRAZZO FLOOR
SYSTEM. TEMPORARY PARTITION
SHALL NOT BE FASTENED TO
FLOOR.
SAND BAGS, TYPICAL
CONTIUOUS FIRE RETARDANT
1"X PAINTED WOOD TOE KICK
ADHESIVE BACKED FELT WEAR
PAD AT EACH 2x4 WOOD STUD TO
PROTECT ETR TERRAZZO FLOOR
1/2" THIICK PAINTED FIRE
RETARDANT PLYWOOD TYPICAL
2 LAYERS FIRE RETARDANT POLY SHEETING
SECURED TO TEMPORARY PARITION AND TO THE
ETR SUSPENDED CEILING GRID TO PREVENT
DUST MITIGATION - CONT. TAPE SEAMS AND
PERIMETER AND OVERLAP SECOND LAYER OF
POLY BY 6" AT ALL LAPS AND EDGES
ETR SUSPENDED ACOUSTICAL
CEILING GRID SYSTEM
LINE OF CONCRETE WAFFLE SLAB
FLOOR ABOVE
N
M
RESTORE EMPLOYEE
ENTRANCE
REMOVE S.S.
CORNER AND
TURN OVER TO
OWNER
PROVIDE SUSPENDED ACOUSTIC
CEILING FRAMING AND PANELS -
PROVIDE PANEL CLIPS TO SECURE
PANELS IN PLACE. LOCATE ETR
LIGHTING AND OTHER CEILING
MOUNTED ITEMS IN THE
TEMPORARY CEILING
ALIGN
PROVIDE CMU WALL TO
MATCH ADJACENT CMU
WALL; PROVIDE
PLASTER FINISH TO
MATCH ADJACENT
PLASTER FINISH AT
CORRIDOR SIDE
REINSTALL SALVAGED
DOOR AND DOOR
HARDWARE; PROVIDE
NEW HOLLOW METAL
DOOR FRAME IN
MASONRY OPENING
INSTALL SALVAGED
DOOR AND DOOR
FRAME SYSTEM IN ITS
ORIGINAL LOCATION
A L
IG
N
REMOVE TEMPORARY ACOUSTIC
CEILING SYSTEM IN ITS ENTIRETY;
SALVAGE ACOUSTIC CEILING
PANELS FOR REINSTALLATION
STORAGE
CORRIDOR
VESTIBULE
PAINT ALL WALL SURFACES TO
MATCH ADJACENT BUILDING
STANDARD
PAINT CMU TO
MATCH
ADJACENT
FINISH
PROVIDE WALL BASE TO MATCH
BUILDING STANDARD
NKB
N. .______________________________________________________
ARCHITECTURE & ENGINEERING, PC..
K BHANDARI
RENOVATION
SHEET SIZE: 34 X 44
DRAWING NO.
CHECKED BY
DRAWN BY
FLOOR NO.
FILE NAME
DRAWING TITLE
SUB. DATE
SUBMISSION
GSA PM
PROJECT NO.
PROJECT
DESCRIPTION
PROJECT
TITLE
FACILITY CODE
OTHER
BUILDING NOs.
BUILDING NO.
CITY/ST./ZIP
STREET
NAME
CONSTR. FIRM
SUB A/E
PRIME A/E
A/E CON. NO.
D R
A W
IN
G
P R
O J E
C T
B U
IL
D
IN
G
C O
N T
R A
C T
O R
S G
R A
P H
IC
S C
A L
E R
E V
IS
IO
N N
O T
E S
C E
R T
IF
IC
A T
IO
N
S
MARK DATE DESCRIPTION
SHEET OF
NK BHANDARI ARCHITECTURE
C&S ENGINEERS
GS-07-P-16-UC-D-7008
K E
Y P
L A
N
SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT - FOR OFFICIAL USE ONLY. Do not remove this notice. Properly destroy documents when no longer needed.
DATE:
A
SUB A/E
CONSTR. CON. -
NYS EDUCATION LAW, SECTION 7209 AND 69.5(B)
PROHIBITS ANY PERSON TO ALTER THESE DRAWINGS
OTHER THAN A LICENSED ARCHITECT OR THE DESIGN
ENGINEER. INFORMATION ON THESE DRAWINGS FOR
GSA ONLY, AND CAN BE UTILIZED BY GSA AS THEY
DEEM NECESSARY.
COPYRIGHT 2022
N. K. BHANDARI, ARCHITECTURE & ENGINEERING, P.C.
1005 W. Fayette Street, Suite 500 Syracuse, NY 13204
Phone Fax www.nkbpc.com
315.428.1177 315.428.9822
499 Col. Eileen Collins Blvd Syracuse, NY 13212
Phone www.cscos.com
315.455.2000
U.S. General Services Administration
100 STATE STREET
ROCHESTER, NY 14614
B
C
D
3 4 51
C:\Users\pdd\Documents\R21_16320.xx.126 GSA Keating Lobby Security - Design_CENTRAL_pdudkowskiD8JHD.rvt
/1
/2
:5 :4
P
M
PHASING PLAN SHEETS
LOBBY SECURITY UPGRADES
PDD
BNV 3/11/2022
RWA A5010736
3/11/2022
5 60
FOR CONSTRUCTION
G-110
PETER SMITH
KENNETH B. KEATING
1. WORKING HOURS: REFER TO THE SPECIFICATIONS FOR THE NORMAL WORKING HOURS. THE
CONTRACTOR CAN PERFORM THE SCOPE OF THIS CONTRACT EITHER DURING NORMAL
BUSINESS HOURS, AFTER HOURS, OR ON WEEKENDS, AT THE DISCRETION OF THE CONTRACTOR
TO COMPLETE THE WORK. ALL PROJECT WORK IS TO BE PERFORMED TAKING INTO ACCOUNT
ALL REQUIREMENTS AS DELINEATED IN THE GENERAL REQUIREMENTS AND IN THE FOLLOWING
GENERAL STAGING NOTES.
2. SECURITY DURING AFTER HOURS WORK: ALL PROJECT WORK PERFORMED AFTER-HOURS WILL
BE REQUIRED TO HAVE GOVERNMENT FURNISHED PERSONNEL PRESENT DURING THE AFTER-
HOUR CONSTRUCTION OR DEMOLITION ACTIVITIES (EITHER J'S ASSOCIATES OR FEDERAL
PROTECTIVE SERVICES PERSONNEL). THE CONTRACTOR SHALL PROVIDE A TWO (2) WEEK LOOK-
AHEAD SCHEDULE TO ADVISE THE GOVERNMENT AS TO WHEN AFTER-HOURS WORK WILL NEED
TO BE PERFORMED FOR THE KENNETH B. KEATING FEDERAL BUILDING AND UNITED STATES
COURTHOUSE BUILD OUT PROJECT. NOTIFICATION OF ANY ADJUSTMENTS TO THE AFTER-
HOURS SCHEDULE WILL NEED TO BE PROVIDED TO THE GOVERNMENT A MINIMUM OF SEVENTY-
TWO (72) HOURS IN ADVANCE OF THE SCHEDULED WORK. THE CONTRACTOR IS RESPONSIBLE
FOR PAYMENT OF GOVERNMENT FURNISHED PERSONNEL DURING THE AFTER-HOUR
CONSTRUCTION OR DEMOLITION ACTIVITIES.
3. NOISE / VIBRATION DISRUPTION: NO CONSTRUCTION OR DEMOLITION ACTIVITIES WILL BE
ALLOWED TO GENERATE UNACCEPTABLE LEVELS OF NOISE OR VIBRATION TO DISRUPT THE
NORMAL OPERATION / TRANSACTION OF OFFICIAL GOVERNMENT BUSINESS DURING THE
NORMAL BUSINESS HOURS. ANY CONSTRUCTION OR DEMOLITION ACTIVITIES THAT GENERATE
UNACCEPTABLE LEVELS OF NOISE OR VIBRATION WILL NEED TO BE PERFORMED AFTER NORMAL
BUSINESS HOURS. THE CONTRACTOR SHALL TAKE ALL NECESSARY PRECAUTIONS TO ASSURE
THAT ROUTINE BUSINESS OPERATIONS ARE NOT DISRUPTED DURING NORMAL BUSINESS HOURS.
THE GOVERNMENT SHALL BE THE SOLE DETERMINER OF WHAT CONSTITUTES UNACCEPTABLE
LEVELS OF NOISE OR VIBRATION.
4. STORAGE: SPACE ON THE PREMISES MAY BE MADE AVAILABLE FOR THE CONTRACTOR'S
STORAGE AND RELATED ACTIVITIES, PROVIDED THAT ITS USE WILL NOT INTERFERE WITH
OPERATIONS OF THE GOVERNMENT. ARRANGE AND GAIN APPROVAL FOR USE OF THIS SPACE
THROUGH THE CONTRACTING OFFICER.
5. EXTERIOR WALL INTERFACE: DUE TO THE BUILDING GEOMETRY, SYSTEMS, AND MATERIALS, SPECIAL CONSIDERATION MUST BE GIVEN TO ANY CONSTRUCTED INTERFACE WITH THE
EXTERIOR ENVELOPE OF THE BUILDING. SPECIAL CONSTRUCTION TECHNIQUES ARE TO BE
EMPLOYED WHEN ANY WORK IS CONSTRUCTED ADJACENT TO OR IN THE VICINITY OF THE
EXTERIOR ENVELOPE. INFORMATION REGARDING THESE SPECIAL CONSIDERATIONS CAN BE
FOUND ELSEWHERE IN THIS SET OF CONSTRUCTION DOCUMENTS (DRAWINGS AND
SPECIFICATIONS).
6. SECURITY CLEARANCE: ALL CONTRACTOR AND SUBCONTRACTOR PERSONNEL PERFORMING
WORK AT THE BUILDING WILL BE REQUIRED TO OBTAIN THE REQUISITE SECURITY CLEARANCE
TO PERFORM THE WORK. THE REQUIRED CLEARANCE FOR THIS FEDERAL INSTALLATION IS A
HSPD-12 CLEARANCE (HOMELAND SECURITY PRESIDENTIAL DIRECTIVE 12). THE GOVERNMENT
WILL ASSIST THE CONTRACTOR AND SUBCONTRACTOR PERSONNEL IN ADMINISTERING THE
SECURITY CLEARANCE PROCESS. THE CONTRACTOR AND SUBCONTRACTORS SHALL ASSUME
ALL COSTS INCURRED BY THE CONTRACTOR AND SUBCONTRACTORS IN OBTAINING THESE
SECURITY CREDENTIALS.
7. CONSTRUCTION KEYING AND ACCESS TO WORK AREAS: THE USE OF SWIPE CARDS,
CONSTRUCTION CORES, AND PERMANENT CORES SHALL BE UTILIZED IN IMPLEMENTING THE
PROJECT SCOPE AS DELINEATED ELSEWHERE IN THE CONSTRUCTION DOCUMENTS (DRAWINGS
AND SPECIFICATIONS).
1. PHASING SHOWN IS THE SUGGESTED SCHEDULE AND INTENT OF THE DESIGN PROFESSIONAL.
THESE PHASES ARE INTENDED TO MINIMIZE IMPACT ON OCCUPANTS, PROVIDE SUFFICIENT
WORKSPACE, AND TO PROVIDE A SAFE CONSTRUCTION SITE. CONTRACTOR MAY PROPOSE
ALTERNATIVE PHASING, BUT WILL ONLY BE ACCEPTABLE UPON WRITTEN APPROVAL OF THE
GSA/AUTHORITY HAVING JURISDICTION.
2. CONTRACTOR TO MAINTAIN BUILDING OCCUPANT AND CONTRACTOR EGRESS ROUTES DURING
ALL PHASES OF WORK.
3. KEEP ALL CORRIDORS FREE OF CONSTRUCTION MATERIALS SO WORKERS CAN VACATE THE SITE
SAFELY WITHOUT OBSTRUCTIONS IN CASE OF A FIRE OR FIRE ALARM DURING EACH PHASE.
4. ALL FLAMMABLE LIQUIDS THAT ARE USED AT THE WORK SITE DURING NORMAL WORKING HOURS
MUST BE STORED OFF SITE AT THE END OF THE WORK DAY. EXAMPLES OF FLAMMABLE
MATERIALS ARE PROPANE TANKS, CLEANING FLUIDS, ETC.
5. THE SUPERINTENDENT SHALL HAVE WEEKLY JOB MEETINGS WITH THE CONSTRUCTION CREWS
TO DISCUSS WHAT ACTIONS THE WORKERS SHALL TAKE DURING THE CONSTRUCTION PERIOD TO
MITIGATE POTENTIAL FIRE SAFETY RISKS.
6. REFER TO SPECIFICATION SECTION 015000 FOR ADDITIONAL INFORMATION ON FIRE PROTECTION
SYSTEM IMPAIRMENTS AND FIRE WATCHES.
7. THE GSA REGIONAL FIRE PROTECTION ENGINEER SHALL MAKE THE FINAL DETERMINATION OF THE
ADEQUACY OF PROPOSED EQUIVALENT LEVELS OF FIRE PROTECTION BEFORE THE DISRUPTION
OF ANY FIRE PROTECTION SYSTEM.
8. THROUGHOUT ALL CONSTRUCTION ACTIVITIES EGRESS FROM THE STAIRS SHALL BE PERMITTED
AT ALL TIMES.
9. THROUGHOUT ALL CONSTRUCTION ACTIVITIES, AN EMERGENCY EGRESS PATHWAY NO LESS
THAN 44” SHALL BE MAINTAINED THROUGH THE CONSTRUCTION SITE TO AN EXIT DISCHARGE
POINT. DOORS WITH DELAYED EGRESS HARDWARE, TIED TO THE FIRE ALARM SYSTEM,
COMPLYING WITH NFPA 101 7.2.1.6.1 TO CONTROL ACCESS TO THE EXIT PASSAGEWAY SHALL BE
PERMITTED. EGRESS PATHWAY SHOULD BE CONSTRUCTED OF NO LESS THAN 2 HOUR RATED
FULL-HEIGHT CONSTRUCTION ASSEMBLIES (3 5/8” METAL STUDS WITH (2) LAYERS OF 5/8” GWB
TYPE X ON EACH SIDE). CONTRACTOR SHALL RELOCATE EGRESS PATHWAY AS REQUIRED
THROUGHOUT CONSTRUCTION TO ACCOMPLISH WORK AND MAINTAIN EGRESS.
10. CONTRACTOR SHALL PROVIDE TEMPORARY SIGNAGE THROUGHOUT THE SITE, WHICH DIRECTS ALL VISITORS OF THE FEDERAL BUILDING TO THE NORTHERN ENTRANCE FOR THE DURATION OF
CONSTRUCTION. SIGNAGE SHALL INCLUDE GSA LOGO, WRITTEN DIRECTIONS AND AN
ILLUSTRATED MAP. COORDINATE WITH GSA REGARDING FINAL WORDING AND DIAGRAMS FOR
SIGNS.
11. DESIGN INTENT IS THAT ALL VISITING OCCUPANTS SHALL ENTER AND EXIT THROUGH THE NORTH
LOBBY DURING THE PERIOD OF CONSTRUCTION. CONTRACTOR SHALL RELOCATE SECURITY
EQUIPMENT AS REQUIRED FOR SCREENING AT THIS LOCATION AS INDICATED ON THE PLANS, AND
RELOCATE IT TO THE PERMANENT LOCATION SHOWN ON THE DRAWINGS AT THE COMPLETION OF
CONSTRUCTION.
12. CONTRACTOR SHALL SUBSTANTIALLY COMPLETE WORK IN THE MAN PUBLIC LOBBY SUCH THAT THE MAIN PUBLIC LOBBY IS NOT OUT OF COMMISSION, AND THE TEMPORARY PUBLIC ENTRANCE IS NOT UTILIZED FOR A DURATION IN EXCESS OF 6 MONTHS (183 CALENDAR DAYS), OR AS APPROVED
BY THE PROPERTY MANAGER.
13. CONTRACTOR SHALL REMOVE THE EXISTING CURTAINWALL AND INSTALL THE NEW CURTAINWALL
BETWEEN THE MONTHS OF APRIL AND OCTOBER, AND AS APPROVED BY GSA’S PROPERTY
MANAGER. CONTRACTOR IS NOT PERMITTED TO REMOVE THE EXISTING CURTAINWALL AND
INSTALL THE NEW CURTAINWALL OUTSIDE OF THIS TIMEFRAME.
NO SCALEG-110
2 OVERALL KEY PLAN
NO SCALEG-110
1 OVERALL PHASING PLAN
ASBESTOS AWARENESS NOTES
LEAD AWARENESS NOTES
3/16" = 1'-0"G-110 G-110
4 DEMOLITION PLAN - TEMPORARY PUBLIC ENTRANCE
3/16" = 1'-0"G-110 G-110
CONSTRUCTION PLAN - TEMPORARY PUBLIC
ENTRANCE
0 4' 8' 12'
0 4' 8' 12'
1" = 1'-0"G-110
5 TEMPORARY FULL HGT PARTITION
1 1/2" = 1'-0"G-110
6 MOVABLE TEMPORARY PARTITION
PHASING NOTES:
GENERAL STAGING NOTES:
0 1' 2' 0 1/2' 1' 2'
1. PHASING 1 WORK SHALL CONSIST OF RELOCTING THE EXISTING SCREENING STATION AND
EQUIPMENT TO THE TEMPORARY LOCATION INDICATED ON THE PHASING PLAN.
2. PHASE 2 WORK SHALL CONSIST OF THE DEMOLITION, RENOVATIONS, AND CONSTRUCTION OF THE
LOBBY EXPANSION.
3. PHASE 3 WORK SHALL SHALL CONSIST OF THE RELOCATION OF SECURITY EQUIPMENT FROM THE
TEMPORARY LOCATION TO THE PERMANENT LOCATION, AND CONSTRUCTION TO RESTORE THE
NORTH EMPLOYEE ENTRANCE.
PHASING:
1 5/18/22 ADDENDUM NO. 1
2 1/18/23 ADDENDUM NO. 2
3/16" = 1'-0"G-110
CONSTRUCTION PLAN - RESTORING EMPLOYEE
ENTRANCE
0 4' 8' 12'
| Sheets |
| AE600 - SCHEDULES AND DIAGRAMS |
| AE601 - INTERIOR FINISH PLAN AND SCHEDULES |
| G-110 - PHASING PLAN SHEETS |
File details come from the government source that posted it. Updated .